What is Earned Schedule in project control

Earned Schedule as a ratio: 17 weeks of time earned over 20 weeks elapsed gives a pace of 0.85, an aggregate figure that does not know which tasks were critical

This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.

Your schedule performance index reads 0.97, the project is six months late, and nobody in the room can explain how both things are true. That is not a reporting mistake. It is what the classic SPI does near the end of a project, and it is the reason Earned Schedule exists. This article explains what Earned Schedule measures, what it demonstrably cannot see, and how to use it without mistaking an indicator for a verdict.

Why SPI stops telling the truth

The classic index compares two amounts of money: what you have earned (EV) against what the plan said you would have earned by now (PV). Early on that works. But a project that finishes, finishes: on the last day EV equals the full budget, PV equals the full budget, and SPI equals exactly 1.00. A schedule index that reads 1.00 on a project delivered six months late is not measuring the schedule. It is measuring how much of the work is done — which is a different question, and one you already have an answer to. The flaw is in the units. You cannot express lateness in euros and expect it to survive to the end. Lateness is measured in time.

What Earned Schedule measures

The fix, published by Walt Lipke in 2003, is to stop measuring the schedule in money. Earned Schedule in project control asks a deceptively simple question: on which date did the plan expect the value you have earned so far? You take the value earned today, walk left along the planned curve until you find the point where the plan predicted exactly that amount, and read the date underneath. That date, expressed as elapsed time from the start, is the Earned Schedule — the time you have actually earned. Compare it with the time that has actually passed and you have the pace.
The cumulative plan curve with today marked: the value earned so far is traced back to the earlier date when the plan expected it, giving time earned of 17 weeks against 20 weeks elapsed
Earned Schedule reads backwards: from the value you have, back to the date the plan expected it.
Three quantities, and one ratio:
  • ES — time earned: how far into the plan your progress actually corresponds to.
  • AT — actual time: how far into the calendar you are.
  • SPI(t) = ES / AT — the pace. 1.00 is on plan, 0.85 means that in one week you complete 85% of what the plan expected, above 1.00 is ahead.
Because both terms are times, the ratio does not collapse to 1.00 at the finish. It stays readable to the last day. That single property is the whole contribution of the method, and it is worth having. It is also the whole of it: what follows is everything people routinely read into the number that is not in it.

It does not know which tasks were critical

This is the limitation that matters most, and the one most often left out. Earned Schedule is an aggregate volume measure. It weighs all the work in the plan together and asks how much of it has accrued. It has no concept of the network of dependencies, and no idea which of your tasks the finish date actually hangs on. So this is entirely possible, and not rare: SPI(t) reads 1.05 — ahead of plan — because three large, non-critical work packages ran early, while the single activity on the critical path is eight weeks late and nothing downstream of it can start. The aggregate is healthy. The project is not. The reverse happens too, and causes needless alarm: a pile of low-priority, off-path work slips, the index drops to 0.90, and the delivery date never moves because none of it was on the path. The practical rule: never read SPI(t) without also looking at the critical path. The index tells you how the mass of work is behaving; only the network tells you what that does to the finish date. Some practitioners compute Earned Schedule on the critical path alone as a second figure, precisely to keep the two questions apart.

The p-factor: did the work follow the plan?

There is a formal way to measure the problem above, and it comes from the same author. Lipke’s p-factor, or schedule adherence, asks whether the value you earned was earned where the plan wanted it earned. The construction is simple. At the earned-schedule point, the plan says how much each individual task should have accrued. Compare that, task by task, with what each task has actually accrued today, and keep the smaller of the two. Add those up, divide by the total value earned, and you have p: p = Σ min(EV, PV at ES) / Σ PV at ES A p of 1.00 means every hour of progress landed on work the plan wanted underway at that point. A p of 0.80 means a fifth of what you earned was earned somewhere else — on tasks that happened to be available rather than tasks that were due. That gap is rarely innocent. Work done out of sequence is usually the work that could be done because it was unconstrained, while the constrained work — which is disproportionately the work on the critical path — waited. And value earned ahead of its predecessors carries rework risk: some of it will have to be revisited when the predecessor finally lands, which means part of your EV is, in Lipke’s terms, not yet effective. So the pair reads like this. SPI(t) tells you how much you earned. The p-factor tells you whether it counted. A project running at SPI(t) 1.02 with a p-factor of 0.75 is not ahead: it is building up a queue of out-of-sequence work and a critical path nobody has touched. The two numbers together are what make the aggregate reading safe to use.

One forecast is not the forecast

From the pace you get a duration forecast. The formula usually quoted is IEAC(t) = PD / SPI(t), where PD is the planned duration. It is a legitimate forecast, but it is one member of a family, and quoting it alone hides the assumption inside it. The general form is clearer about what you are assuming: IEAC(t) = AT + (PD − ES) / PF The time already elapsed stays as it is — the past does not rescale — and the remaining plan, PD − ES, is completed at some performance factor PF that you choose deliberately:
  • PF = SPI(t) — the future goes exactly like the past. This collapses to PD / SPI(t). Pessimistic by construction on a project that has been fixing its problems, and the honest default when nothing has changed.
  • PF = 1.00 — the remaining work is delivered at the planned rate. This is the assumption behind every recovery plan ever presented, and it deserves to be stated out loud rather than smuggled in.
  • PF = a target you commit to — the figure a recovery plan actually implies. Computing it backwards from the date you need is usually the most sobering number in the pack.
There are also forecasts built on the critical path rather than on aggregate value, and there is the whole schedule-risk-analysis tradition, which answers with a distribution of dates rather than a single one. Earned Schedule gives you a deterministic point estimate. That is useful and cheap; it is not a probability.

A constant performance factor is a straight line through an S-curve

Whichever PF you pick, the formula spreads it evenly over everything that is left. Projects do not work that way. Progress follows an S-curve: slow to start, fast in the middle, and slow again at the end — and the slow end is not a lack of effort, it is the nature of the work. Look at what the remaining plan actually contains. Commissioning, integration testing, inspections, regulatory approvals, client sign-off, handover: these are the activities that close a project, and most of them do not compress. A second crew does not halve a witnessed test. Doubling the team does not make the authority answer sooner. Their duration is set by something outside your span of control. The consequence is specific and worth stating: a recovery factor applied late in a project is systematically optimistic. At 20% complete, most of the remaining plan is execution, and execution responds to resources. At 85% complete, most of what is left is rigid, so a PF of 1.20 is being applied to work that cannot go 20% faster no matter what you spend. Before you commit to a PF above 1.00, split the remaining plan in two: the part that responds to resources, and the part that does not. Apply the recovery only to the first. The honest forecast is usually the pessimistic-looking one.

What the number tells you to do

Take a 40-week plan, observed at week 20, with a pace of 0.85. Time earned: 20 × 0.85 = 17 weeks. Remaining plan: 40 − 17 = 23 weeks.
  • Carry on at 0.85 and you finish in 20 + 23 / 0.85 = 47.1 weeks, about seven weeks — 49 days — late.
  • Recover to the planned pace of 1.00 and you finish in 20 + 23 = 43 weeks. The delay stops growing. It does not go away.
  • To actually land on week 40 you need a pace of 23 / 20 = 1.15: a 35% improvement on what you have managed so far, sustained for the whole remainder.
That third line is the point of the exercise. “We will make it up” is a sentence that sounds reasonable in a meeting and means, arithmetically, running a third faster than you have managed for five months. Whether that is plausible is a management judgement about crews, approvals and suppliers. The arithmetic does not make it for you; it only tells you what you are claiming.

Read it next to the cost index, or not at all

SPI(t) tells you how fast. It says nothing about whether the speed you need is affordable, and recovery is almost always bought — overtime, a second crew, expedited delivery, resequencing that wastes float. Put the cost performance index next to it before you promise anything:
  • SPI(t) < 1 and CPI < 1 — late and overspending. The 35% recovery has to be funded out of a budget that is already short. This is the combination where recovery plans quietly become change requests.
  • SPI(t) < 1 and CPI > 1 — late but efficient. There may be room to buy time, and this is the case where a recovery plan is realistic rather than aspirational.
  • SPI(t) > 1 and CPI < 1 — you are already buying speed. Worth knowing before someone asks for more of it.
A schedule index read alone tends to produce recovery plans that are arithmetically sound and financially impossible. The cost index has the same weakness in its own dimension: one CPI is a number, twelve are a diagnosis.

The weighting decides the number

Everything above rests on one quiet assumption: that the value of each task is a fair measure of its share of the work. That holds when the plan carries baseline costs, or baseline work in hours. It holds much less well when it does not. Tools that compute Earned Schedule on a plan without costs or resources fall back to weighting tasks by duration. Treat any figure produced that way with real caution: in EVM practice, duration-only weighting is not considered a reliable basis. A twelve-week wait for a permit — no effort, no cost, one line in the plan — outweighs a two-week task that consumes half the project’s specialist capacity. The index will happily report a pace, and the pace will be measuring the wrong thing. If your plan has no cost or work baseline, the honest position is that you have a rough indicator, useful for spotting a trend over successive status dates, and not a number to put in front of a client.

None of it survives an unstable baseline

Every figure in this article is measured against the baseline. Earned Schedule does not compare you to reality; it compares you to the plan you froze. If that plan no longer describes the job, the index is arithmetic performed on a fiction. This is the common failure in practice, and it is quiet. Scope arrives task by task — an extra deliverable here, a change of specification there — and gets absorbed into the working schedule without the baseline being touched. Progress is then measured against a plan that never contained that work. SPI(t) drifts downwards, the team is told it is late, and part of that lateness is simply work nobody planned for. Re-baselining is the answer, but it is not a free one:
  • Between status dates the baseline must not move. A trend across readings is the most valuable thing the method gives you, and it is only a trend if the ruler stayed the same.
  • Re-baseline formally, or not at all. A new baseline is a decision with a date, a reason and an approval — not a quiet save.
  • A new baseline resets the record. Accumulated delay disappears from the index the moment the plan absorbs it: SPI(t) returns to 1.00 while the delivery date stays exactly where it was. Keep the previous figures beside the new ones, or you have re-baselined your way to a healthy report.
If you cannot say when the baseline was set and what has been formally added since, the pace you are quoting has no denominator worth trusting.

So what is it good for

Read with those limits in mind, Earned Schedule earns its place:
  • It stays truthful late in the project, exactly when the classic SPI stops working and exactly when the decisions get expensive.
  • It converts into dates and days, which is the language of the people who have to decide something.
  • It is cheap: it needs a baseline, a status date and recorded progress — no new process, no new data collection.
  • It trends well: one reading is an opinion, a series of readings across status dates is evidence, which is also the argument for reading the direction of a delay rather than its size.
What it is not is an oracle. It is one instrument on the panel, and it needs the others around it: the critical path and the p-factor to know whether the aggregate means anything, the cost index to know whether the recovery is affordable, a stable baseline to know what the ruler is, and the judgement of the people doing the work to decide what to do about it.
Disclosure: this is the blog of a company that makes project-control software, so take the paragraph below for what it is. Nothing in the method above requires our tool, or any tool: Earned Schedule is public work, published by Walt Lipke, and a competent spreadsheet computes it from a baseline curve and a status date. If you want the figure computed on your own plan rather than in a spreadsheet, GanttDerivata reads a Microsoft Project file with a saved baseline and a status date, reports the Earned Schedule pace and the forecast finish, and warns you when it had to weight tasks by work or by duration instead of by cost, so you know how much to trust the number. It is a Windows desktop application: your plans never leave your machine. #EarnedSchedule #EarnedValue #ProjectControl #CriticalPath #ProjectManagement