What is a baseline in Microsoft Project, when to set it, and what changes after

Without a baseline, updating is replanning: what a baseline is in Microsoft Project, when to set it, how, and what changes in the plan a moment later

This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.

A ten-day task. Halfway through you realise it needs twelve, you open the Duration field and type 12. The Gantt chart updates, the project slips by two days, everything adds up. Or: at the status date the task is at 40% instead of the 50% you expected, you update the plan and the duration stretches by itself. In both cases you are looking at a plan that says where the project will end. What it no longer says is where it was supposed to end.

In training courses and consulting work I meet many organisations that have used Microsoft Project for years and have never set a baseline. Not by choice: because nobody told them that without that snapshot every update of the plan is, in fact, a replan. This article is about that: what the baseline is, when to set it, how, and what changes in the plan a moment later.

In short

  • The baseline is a photograph of the plan taken a moment before you execute it: for every task, start, finish, duration, work and cost as they were when the plan was approved. The plan then changes; the baseline does not.
  • Without a baseline, updating is replanning: every edit erases the term of comparison, and the delay disappears from the numbers, not from reality.
  • You set it once, when the plan is approved and before the first task starts, from Project → Set Baseline. You set it again only for an approved change, after archiving the previous version in a numbered baseline.
  • After you set it, the Tracking Gantt shows a grey baseline bar under every task bar, and the Variance table says by how much each task has moved.
  • Baseline and status date are the two conditions without which Earned Value and every variance analysis stay at zero.

What a baseline is

The usual definitions all say the same thing from different angles: “a snapshot of the project a moment before its execution”, “the photograph of the plan at the end of planning, approved by the client”, “the time, resource and cost budgets taken together”. It is not a forecast of what will happen: it is the record of what you promised.

In Microsoft Project the baseline is not a separate file: it is a set of fields that sit next to the current ones. For every quantity in the plan there are three columns, and the third is the one you care about.

Today’s planThe baseline (does not change)The difference
StartBaseline StartStart Variance
FinishBaseline FinishFinish Variance
DurationBaseline DurationDuration Variance
WorkBaseline WorkWork Variance
CostBaseline CostCost Variance
The three columns of every quantity. The first is recalculated by the Project engine at every change; the second you write once with Set Baseline; the third is the difference, calculated by Project.

There are eleven baselines: Baseline, with no number, and Baseline1 to Baseline10, each with its own fields (Baseline1 Start, Baseline1 Finish, and so on). The variance columns read only the one without a number: it is the “current” baseline, the one Project uses to draw the Tracking Gantt and calculate variances. The other ten are the archive.

Updating without a baseline is replanning

Back to the ten-day task. Without a baseline, when you type 12 in the duration the plan says “twelve days”, full stop: no trace of the original estimate remains, and the project finish moves without any number saying so. With a baseline set, the same gesture produces different information: “twelve days, ten planned, variance plus two”, and the project finish shows how far it has moved from the promise.

The same extension of a task from 10 to 12 days, without a baseline and with a baseline: in the first case the plan shows only the new value, in the second it shows the new value, the planned one and the variance
Same change, two plans. Without a baseline the plan only knows where it will end; with a baseline it also knows where it was supposed to end, and by how much it has moved.

Updating a plan without a saved baseline is not updating: it is replanning, and losing every time the memory of where you meant to go.

That is why the baseline is the first step of the update cycle, before the status date and the actuals: the full cycle is in the guide on how to update a Microsoft Project plan. Here we focus on the step that makes the others possible.

When to set it: once, and then only with a signature

There is one moment: when the plan is approved, before the first task starts. Not at the kick-off meeting, when the plan is still a draft, and not at the first update, when the first tasks have already been touched. The day the client says “fine” is the day of the baseline.

On that day you set it twice: in Baseline, the one Project reads, and in Baseline1, which from that moment is the signed plan and is never touched again. It costs thirty seconds and cannot be recovered later. Then you note the date and the state of the project at the time of saving: the place I suggest is the Notes field of the project summary task, the one with ID 0, so the note travels with the file.

Periodic updates do not re-set the baseline. Ever. If you overwrite it at every update, every update the project is “on track” by definition, and the delay disappears from the numbers and stays in reality. The baseline is set again in one case only: an approved change, a variation order signed by the client, a scope change decided by management, an agreed replan. In that case the promise has genuinely changed, and the sequence is this:

  1. archive the plan you are about to abandon in the first free numbered baseline (Baseline2, then 3, then 4), before touching any date;
  2. change the plan according to the approved variation;
  3. set Baseline again with the new plan, so the variance columns restart from the current plan;
  4. note date and reason in the Notes field of task ID 0.
The life of the baseline along the project: set twice when the plan is approved, left alone at periodic updates, archived and set again only for an approved change
Three moments, three different gestures. The double save at the start, no save at the updates, archive plus re-save at every approved change.

From that moment the Finish Variance column measures against the replan, no longer against the signed plan: if the sponsor cares about the second distance, it has to be calculated separately. I covered it in Microsoft Project baselines: what to compare against after you replan, which is the natural continuation of this article.

How to set a baseline in Microsoft Project

The gesture is simple. This is a plan just approved, before the baseline: the Gantt bars are the normal ones, no grey trace underneath. It is the New Corporate Website template that ships with Project, with dates in day/month/year format.

Microsoft Project Gantt Chart of the New Corporate Website plan before the baseline is set: normal bars, no grey baseline bar, project duration 100.5 days and finish on 13 January 2027
The plan before the baseline. Duration 100.5 days, finish on 13 January 2027: that is the promise we are about to photograph.

On the Project tab choose Set Baseline and then Set Baseline again. The dialog opens with the drop-down of the eleven baselines and the choice between the whole project and selected tasks.

The Set Baseline dialog in Microsoft Project, with Baseline selected in the drop-down, the Entire project option and the roll-up options for summary tasks
The Set Baseline dialog. The first entry of the drop-down, with no number, is the one Project reads; the other ten are the archive. On day one it is always the entire project.

On the first day you do it twice: choose Baseline1, confirm with OK; open the dialog again, choose Baseline, confirm. The Selected tasks option is for later, for tasks added during execution, which I cover in the questions at the end.

What changes a moment later: Tracking Gantt and Variance table

Apparently nothing. The Gantt is identical, no message. But the scheduling engine has changed gear: from this moment every recalculation of the plan is compared with the photograph. To see it, switch to the Tracking Gantt view.

The Tracking Gantt view in Microsoft Project right after setting the baseline: under every red bar of the critical tasks there is the grey baseline bar, perfectly aligned, all tasks at 0%
The Tracking Gantt right after the baseline. Under every bar there is the grey baseline bar, still perfectly aligned: no variance, because nothing has changed.

Every task now has two bars. The lower one, grey, is the baseline; the upper one is the current plan, red if the task is on the critical path and blue if it is not. Until you touch anything the two bars coincide. Now let us do exactly what happens at every update: the task Research Previous Experience goes from 5 to 8 days.

The Tracking Gantt after extending Research Previous Experience from 5 to 8 days: the red bars of the critical tasks downstream have moved to the right of the grey baseline bars, project duration 103.5 days and finish on 18 January 2027
Research Previous Experience from 5 to 8 days. Every critical task downstream has detached from its grey bar, and the project went from 100.5 to 103.5 days: finish on 18 January instead of 13 January 2027.

The effect is immediate and you do not need to read a number: the distance between the coloured bar and the grey one is the delay. If you want the number, open the Variance table (View → Tables → Variance), which puts current start and finish next to the baseline ones and calculates the difference.

The Variance table in Microsoft Project after the change: Start, Finish, Baseline Start, Baseline Finish, Start Variance and Finish Variance columns, with 3 days of finish variance on every task downstream of Research Previous Experience
The Variance table. Research Previous Experience has 0 days of start variance and 3 days of finish variance; every task downstream has 3 days on both. That is the variance analysis, ready.

The screenshots are from the current desktop version of Project. Commands and columns are in the same places from Project 2010 to Project 2024 and in the desktop versions shipped with Microsoft 365: the ribbon colour changes, the method does not.

What a well-managed baseline lets you do

Five things, and none of them is possible without it.

  • Variance analysis of time, work and cost: the variance columns only make sense if there is a term of comparison.
  • The real delay of the tasks, and its direction: a delay that grows at every update is an emergency even if small, one that is absorbing itself is a problem that solves itself. You see it by comparing two consecutive updates, and it is the fact that decides when to tell the client.
  • Earned Value: the planned value is the baseline spread over time, and without a baseline and a status date every index in the Earned Value guide is worth zero.
  • Project’s reports that show variances against the baseline, including the graphical ones, populate themselves.
  • The history of the project: with the numbered baselines you can see on screen how the plan changed over time, and how many times the date was moved.
The baseline is there but the variances stay at zero? The five causes and how to fix them: I set the baseline but the variances don’t show: what am I doing wrong?

The mistakes I see most often

  • No baseline set. Variance table all zeros, Tracking Gantt with no grey bars: the plan has no memory. It is the most frequent case.
  • Baseline re-set at every update. The project is always on track by definition, and the client discovers the delay close to the deadline.
  • Set too early, on the kick-off draft, and then the plan changes before starting: the baseline photographs a promise nobody made.
  • Set too late, at the first update, with the first tasks already progressed: the actual dates end up inside the baseline, and the variance on those tasks will be zero by construction.
  • Tasks added later, with no baseline. Tasks inserted during execution have empty baseline fields and escape every comparison, until you save them with the Selected tasks option.
  • No note on when and why the baseline was set: after six months nobody remembers.

The opposite case: when the baseline is not needed yet

Not every Project file deserves a baseline. A plan still under construction, used to explore scenarios and estimate, has no promise to photograph: setting one would only create meaningless variances, and the temptation to re-set it every day. The same goes for a feasibility study or for the plan used to prepare a bid: there the baseline comes later, when the bid is accepted and the plan becomes a commitment. The rule stays the one above: the baseline is set when someone has said “fine” and that “fine” carries weight. Before then the plan is a hypothesis, and hypotheses are changed without an archive.

Frequently asked questions

The project has already started and I never set a baseline: what do I do?

Set it now, with Project → Set Baseline. The comparison with the original plan is lost, but from this moment every update will have a term of comparison. If a copy of the file from when the plan was approved still exists, you can rebuild the baseline from there, but in practice it is rarely worth the effort: better to start straight away with what you have.

I added tasks after setting the baseline: how do I include them?

Select them, open Set Baseline and choose Selected tasks instead of Entire project. The two check boxes below, on rolling up baselines to summary tasks, push the new values into the totals of the phases and of the project: tick them, otherwise the summary baseline stays the old one. The rest of the plan is not touched.

I deleted tasks after the baseline: why do the baseline costs not add up?

Because the baseline of the summary task remembers the cost and work of the deleted tasks: that was what you promised. The negative variance you see is correct and should be explained that way. If the deletion is part of an approved change, it is one of the cases where you set the baseline again, after archiving the previous one. In Project Professional you can also inactivate the task instead of deleting it: the row stays, struck through, and explains the variance.

Can I see two baselines together in the Gantt?

Yes. In the Multiple Baselines Gantt view (View → Other Views) Project draws Baseline, Baseline1 and Baseline2 one under the other for every task, and from Format → Baseline you can choose which baseline to show in any Gantt. It is the quickest way to show a client how many times the date has moved.

What is the difference between the baseline and the status date?

They are the two coordinates of an update. The baseline says what was promised; the status date says which day the actual data you entered refers to. Without a baseline you do not know how far you have moved; without a status date you do not know relative to when. The variance columns need the first, Earned Value and percent complete the second.


Disclosure: this is the blog of a company that makes project-control software, so take that for what it is. Nothing in the method above requires our tools, or any tool: Set Baseline, the Tracking Gantt and the Variance table are standard Microsoft Project, from 2010 to 2024 and Microsoft 365.