One WBS, more than one way to see it: outline codes in Microsoft Project

One WBS, every point of view: the same six tasks grouped by phase and by area with outline codes, 320 hours in both

This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.

The plan is well built. The WBS is by phase: structure, services, finishes. Then comes the meeting.

The site manager wants it by area, because the site thinks in buildings. Finance wants it by contractor, because that is how it pays. The client wants to know when their floor will be ready.

There are two usual reactions, and both are wrong. Rebuild the WBS by area, and the phase view is gone. Or copy the tasks that belong in two branches, and from then on hours and costs are counted twice.

In short

  • Microsoft Project has one WBS: the summary-task outline. You choose it once, by deliverable or by phase.
  • Every other point of view (area, contractor, floor) is built with outline codes, one per view, and Group By: no restructuring, no copied tasks.
  • Grouping is enough to look. When a view needs its own budget and its own owner, decide which structure runs the plan.

The structure you manage and the structures you look through

Alex Lyaschenko, who teaches planning in Australia, put it in one line in an article this month: a WBS is a grouping structure, but not every grouping structure is a WBS.

The difference is what you hang on it. A WBS element carries an owner, a budget, progress, a comparison from one update to the next. A grouping is a way of looking: change the criteria and the totals you had a minute ago are gone.

In practice: you choose the WBS once, by deliverable or by phase, as we saw in how to build a work breakdown structure. Every other perspective is a view.

In Project: one outline code per point of view

Project gives you ten task outline codes (Outline Code1 to Outline Code10): fields that only accept values from a list, which can have several levels. They are the right place for area, contractor or floor.

  1. Define the code. Project › Custom Fields, pick Outline Code1, rename it “Area” and type the list: Building A, Building B, External works. If you need a second level (Building A › Ground floor), the code mask allows it.
  2. Assign it to the work tasks, not to the summaries: add the “Area” column to the table and pick the value from the list.
  3. Group. View › Group By › New Group By, by “Area”. Project lines the same tasks up under Building A, Building B, External works, and works out work and cost for each group.
  4. Hide the summary tasks in the grouped view (Format › Summary Tasks): in that view only the tasks that do the work should count.
  5. Save the view with a name such as “Gantt by area”, so the grouping does not have to be rebuilt every time.

The same goes for the contractor, with Outline Code2. The phase WBS stays as it is, and so do the links: only the angle changes.

The same six tasks grouped two ways: on the left by phase, Structure 144 hours, Services 88, Finishes 88; on the right by area with an outline code, Building A 184 hours, Building B 136; the project total is 320 hours in both
Same six tasks, same links: by phase or by area only the groups change. The total stays at 320 hours, because no row was copied.

What about the task that seems to sit in two branches?

This is the question that starts the copying: “does the services installation in Building A belong under Services or under Building A?”. In the WBS it sits under one branch, the one of the structure you chose. In the area view it shows up under Building A because that is the value in its code. Same row, counted once.

When grouping is not enough

Grouping is for looking. It falls short when a point of view has to be managed: an owner for Building B, an approved budget per contractor, a month-on-month comparison of progress by area. A group in Project has no owner, no notes, no target date of its own.

Then there are two honest ways out:

  • decide which view becomes the WBS. If the site is run building by building, the structure goes by building and the phases become the code;
  • split the work into separate plans held together by a master project, one for each view that needs its own owner and budget.

What does not work is the third way, the most common one: two structures in the same plan, with the tasks copied. It is one of the signs of a WBS that does not hold.

Frequently asked questions

How many outline codes can I use?

Ten for tasks (Outline Code1 to Outline Code10), and another ten for resources. Each one has its own list of values, which can be hierarchical.

Can I use a text field instead of an outline code?

Yes, as long as it has a value list: a free text field ends up with “Building A”, “Bldg A” and “building a”, and Group By treats them as three different areas.

Does grouping change the plan?

No. It reorders the view and adds up each group; dates, links and outline stay as they are. You go back with Group By › No Group.


The WBS code, on the other hand, is not a point of view: it is a label that moves with the outline. What happens when you use it as a key is in the WBS code is not an address.

#MSProject #WBS #ProjectPlanning #ProjectControl

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top