The WBS that doesn’t hold: five signs you can see in the plan

The WBS that does not hold: five WBS mistakes you can see in a Microsoft Project plan in under a minute

This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.

The client asks a simple question: “where are we with the foundations?”. You have the plan open in front of you, four hundred rows, and you do not know where to look. Not because the data is missing: because in the plan the foundations do not exist as a thing. There are thirty-two scattered tasks that, taken together, are the foundations, but the “taken together” lives in your head, not in the file.

That is the symptom of a WBS that does not hold: the work breakdown structure the whole Microsoft Project plan rests on. It does not jump out like a constraint or a missing duration, but it decides whether the plan can answer questions or not. And the common WBS mistakes come down to five signs, all visible in under a minute.

In short

  • The WBS says what the project is made of; the plan says what is done to get it. In Microsoft Project they share one column, which is why a weak breakdown goes unnoticed.
  • Five signs give it away: the flat list, containers with one child, branches of different depth, sixty-day blocks, phases that never close with a milestone.
  • The move that reveals almost all of them takes ten seconds: collapse the plan to the first outline level and look at what is left on screen.
  • The reference numbers: three or four levels, at least two children per container, tasks of one to ten days, one milestone per phase.

The WBS and the Microsoft Project plan are not the same thing

The work breakdown structure says what the project is made of: the products, the deliverables, the parts. The plan says what is done to produce them. The first is a tree of nouns, the second a list of verbs.

In Microsoft Project the two live in the same column: the outline levels, the bold rows that open and close, are the tree of the WBS, and the detail rows are the tasks. It is convenient and treacherous at once: when the breakdown is weak, the plan turns into a to-do list with no skeleton, and nobody notices until a question like the one about the foundations arrives.

Sign 1: the flat list

Four hundred tasks all at the same level, without a single summary. It almost always happens for one reason: the plan was born from a list, an email, a spreadsheet, meeting minutes, and was pasted into Project as it was.

How to see it in ten seconds: use the outline commands to show only the first level. If the plan collapses to five or six rows, there is a skeleton. If it stays just as long, there is not: what you have in front of you is a list, not a plan. It is the first of the checks for a plan you did not build.

Why it is a problem, and not a matter of looks: without summaries there are no intermediate totals. You cannot say what a phase is worth, you cannot say where it stands, you cannot show one on its own in a meeting. Every question about part of the project needs a sum done by hand, every time.

The WBS in Microsoft Project: the same project collapsed to the first outline level, on the left six recognisable phases with their durations, on the right four hundred rows at the same level
The same project, collapsed to the first level. On the left there is a skeleton; on the right there is a list. The difference is not the order: only one of the two can answer questions about a single part.

Sign 2: the container with one child

A phase that holds a single task summarises nothing: it duplicates a row. Two rows saying the same thing, with the same dates and the same cost, one of them in bold.

On its own it is a minor flaw. When there are ten of them, it says something more serious: that the structure was built to show an organisation that is not there. Usually somebody took the table of contents of the specification and turned it into phases, one by one, without asking which of them really held work that could be broken down.

Sign 3: branches of different depth

One part of the project is broken down into five levels, with two-day tasks; another is a single row that says “Commissioning, 40 days”. It is not necessarily a mistake, in rolling wave planning the distant future is kept coarse on purpose, but it is a question to ask every time, because the two possible explanations are opposite.

  • It is deliberate: that part will be detailed when the time comes, and whoever wrote the plan knows it and says so.
  • It is not deliberate: nobody has thought that part through. The famous “40 days” is an estimate dropped there to close the plan, and there is nothing inside.

Only the answer of whoever built the plan tells the two apart. But it is worth knowing before you sign: the least detailed part of the plan is where you carry the most risk, because it is the only part nobody has looked into yet.

Sign 4: the sixty-day block

A detail task with a huge duration is a black hole: it cannot be followed, cannot be measured, cannot be split between two people. For two months the answer to “where is it?” will be an invented percentage.

The rule I use in class is the 8/80 rule: no task should be shorter than eight hours of work or longer than eighty, two weeks. Below that, the plan becomes a list of gestures and you spend your days updating it; above it, it is no longer controllable. It is not a law of nature, on long projects the upper limit stretches, but if a plan has many tasks of one or two months, that plan was not built to be updated. And indeed it almost never is.

Its opposite exists and is just as wrong: the plan with twelve hundred half-day rows, where updating costs more than the work it describes.

Sign 5: phases that never close

You scroll the plan and find no milestones: no zero-duration tasks, no diamonds in the Gantt. Phases end because their last task ends, and nobody ever stated what “this phase is closed” means.

It is the most underrated of the five signs, and the most expensive. A milestone is a checkpoint: Detailed design approved, Acceptance test passed, System handed over. Without them the project has no moments when someone says yes or no, and the delay becomes visible only once it has happened. That is exactly why a strategic dashboard is built on milestones and deadlines.

Practical rule: every phase closes with a milestone, and the milestone of one phase is the predecessor of the first task of the next. It is also the right way to link two phases, instead of drawing links between summary rows.

If the plan is yours

The breakdown is done before opening Project, and it is done top-down: the project into parts, the parts into sub-parts, until every piece is small enough to hand to someone with a date. Only then do you write the tasks needed to produce it. Four numbers to keep in mind while you build it:

  • Three or four levels are almost always enough. Six levels are a sign you are breaking down someone else’s work.
  • At least two children for every container, or that container is not needed.
  • One to ten days per task, unless there is a stated exception.
  • One milestone per phase, with a name that states a check passed, not work done.

And one thing not to do: build the phases afterwards, selecting rows already written and indenting them until the plan “looks tidy”. What comes out is a structure that mirrors the order in which the tasks came to your mind, which is not the order in which the project is made.

If the plan was sent to you

Three moves, in this order, before reading a single row.

  1. Collapse everything to the first level. What stays on screen is the idea the planner has of the project. If you take it in at a glance and recognise the project, the structure holds. If you see four hundred rows, or six names that mean nothing to you, you already have the answer.
  2. Open one level at a time and look at the balance: how many children each phase has, whether one is empty, whether one holds half the project.
  3. Show the WBS column and sort by it: the hierarchical numbering makes jumps in level and branches that stop too early obvious.

The question to ask is not “is the WBS right?”, which leads nowhere. It is: “can you show me where, in this plan, the thing I am asking about is?”. If answering means scrolling and selecting scattered rows, the structure does not hold, and now two of you know it, which is already a gain.

Frequently asked questions

Do I really have to build the WBS first, or can I build it straight in Project?

You can build it in Project, and on small projects that is what I do too. The point is not the tool: it is the order of thought. If you start by writing tasks and organise them afterwards, you get a structure that mirrors the order they came to mind. If you start from the parts of the project and then write the work inside each one, you get a structure that mirrors the project. The difference shows at the first change of scope.

How many levels should a WBS have?

Three or four cover almost every project. The criterion is not the number itself: you go down until every element of the last level can be given to one person, with an estimable duration and a verifiable result. When you get there, you are done. If you keep going down, you are planning the work of people who know how to do it better than you.

Can I change the structure once the project has started?

Moving rows and changing indents is allowed, and Project recalculates everything. What breaks is the comparison with the past: the saved baseline is tied to the tasks, and a deep reorganisation makes variances hard to read, especially if some tasks are deleted. If the restructuring is large and the project is under way, treat it as a real replan, with a new baseline while keeping the old one.

Is the WBS code in Project the same thing as the WBS?

No, and it is a common misunderstanding. The WBS code is the hierarchical numbering Project assigns by itself following the outline levels: 1, 1.1, 1.1.2. It helps you find your way and talk on the phone, but it is a consequence of the structure, not the structure. You can also define a custom code with your own letters and formats, to match the numbering of the specification.

Are four hundred rows too many?

It depends on how long the project runs and how many people work on it, not on the number itself. The right question is another: who updates this plan, how often, and in how much time? If the answer is “one person, every two weeks, in half a day”, four hundred rows are sustainable. If nobody has an answer, the plan is already too big, whatever the number.

The same checks as a sheet to keep next to the keyboard: the Microsoft Project plan review checklist, with a one-page PDF to print.