This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.
A reader once wrote to me with a problem I still get asked about almost every month. He had a ten-day task and two people to put on it: X, available full time, and Y, who on that particular task could only work from the second to the eighth day. He assigned both, pressed OK, and Project loaded Y on the first, ninth and tenth day as well — exactly when Y was not there. In the Resource Usage view those cells turned red: overallocation.
Stripped to the bone, the question is this: how do you tell Project that a resource works on a task only during part of its span?

Why Project behaves this way
When you assign a resource to a task, Project has no way of knowing that this person, on this specific task, has a narrower window. It takes the task duration, looks at the resource calendar and the assignment units, and spreads the work across the whole available span. If the task runs ten days and the resource calendar says those ten days are working days, the work lands on all ten.
This is not a flaw in the software. It is that the information “Y is only here from day 2 to day 8” has not been given to it yet, in a place it can understand.
The road that looks right and backfires
The natural temptation is to open Resource Information and edit the Resource Availability table, entering date ranges with Max Units at 100% when the person is there and 0% when they are not. It works, in the sense that the immediate result is the one you wanted. But you pay for it later, for three reasons.
The first is that it pins scheduling to fixed dates. That is the opposite of what dynamic scheduling asks for, where tasks must be free to slide along the timeline following their links, with no chains holding them back.
The second is maintenance. When the task slips by two weeks — and it will — those exceptions stay anchored to the dates you typed, which by then mean nothing. You have to remember to go back and fix them. You will not remember.
The third is the most insidious: availability is a property of the person, not of that one task. If you change it to solve a problem on a single task, you have changed Y’s profile across the entire project, including every other task they are assigned to. In a portfolio, where the same people appear on several plans, that is how quiet errors spread.
The same applies, with the same drawbacks, to the individual resource calendar.
Two roads that actually work
The first is to split the task in two: one part for X, one part for Y, so that Y’s exceptions live on a task of their own. It is the simplest solution and needs no explanation. It is not always workable, though: sometimes that task has to stay a single line, because that is how it gets reported, or because splitting it would make the plan unreadable.
The second is to work on the assignment, not on the person. That is the one described below, and it has a precise advantage: the exceptions travel with the assignment, so if the task moves, they move with it.
The procedure, step by step
1. Set the task to Fixed Duration and clear the Effort driven checkbox. Both are in Task Information, Advanced tab. This step is not a detail: it stops Project from reacting when you remove hours from Y, either by shortening the task or by pushing those hours onto the other resources. You want the duration to stay ten days and X’s work to remain untouched.
2. Open the Resource Usage view. That is where you can see — and edit — work assignment by assignment, day by day.
3. Add the Assignment Delay column and enter 1 day on Y’s row. Y starts working on the second day of the task, while X started on the first.
4. In the timephased grid on the right, zero out Y’s hours on days 9 and 10: type 0 in the Work field of those two cells.
5. Look at Y’s total: it has dropped from 80 hours to 56, the seven days that person is actually there. X is still at 80. The task duration is still ten days.
One variation, if you would rather not use the delay: you can get the same result by typing 0 into Y’s hours on the first day too, leaving Assignment Delay at zero. The final total is identical; only the way it reads in the view changes.
Why this is the robust solution
The point is not that it is more elegant. The point is that it needs no maintenance. The zeroed hours and the delay are attributes of the assignment: if tomorrow the task moves three weeks out because a predecessor slipped, Y’s window moves with it and keeps its shape.
With the resource calendar route you would be left with hand-typed dates sitting still while the plan moves around them — quietly becoming wrong.
Frequently asked questions
Which versions of Project does this work in?
All of them, in practice. Assignment Delay, the Resource Usage view and the Fixed Duration / Effort driven options are identical in Project 2010, 2013, 2016, 2019, 2021, 2024 and in the desktop versions shipped with Microsoft 365. The technique was first written up for Project 2007 and the commands are still in the same places.
Why Fixed Duration with Effort driven off?
Because those are the two settings that tell Project not to react when you edit work. With a different task type, removing hours from Y would either shorten the duration or move those hours onto X — neither of which is what you want.
Can I use it with more than two resources?
Yes. The method works one assignment at a time: every resource has its own row in the Resource Usage view, with its own delay and its own hours. You can shape each one differently on the same task.
If the task moves, do I have to redo everything?
No, and that is exactly why this route is preferable to the resource calendar one. The profile you drew belongs to the assignment and travels with the task.
What if the person is unavailable for a long stretch, across the whole project?
That is the opposite case, and it is precisely where the Resource Availability table is the right tool: there you are describing a genuine property of the person — part time, parental leave, a secondment — not a local exception on a single task.