This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.
“Can you send it in a format I can open?” It is the sentence that ends every meeting where you showed the plan. Whoever asks, the client, the boss, the supplier, the colleague in production, does not have Microsoft Project and never will, and they are right: the licence is for whoever builds the plan, not for whoever reads it.
The trouble is that every way to share a Microsoft Project plan loses something, and hardly anyone knows what. There are five ways, you choose between them with one question, what does the recipient need to do with it?, and choosing the wrong one is why some forty-page PDFs never get opened.
In short
- The recipient comes before the format: they need to read, work on it or decide. Three different answers.
- The five ways and what each loses: the PDF keeps the look and loses the calculation; the image loses everything but the message; Excel keeps the data and loses the engine; a viewer shows the plan but often will not let you change the view; a dashboard loses the detail, and that is its purpose.
- To tell each person what they have to do you do not need Project Server: their own tasks, by email, are enough.
- What leaves with the file cannot be seen in the view: rates, names, notes, links and the history of the baselines. What goes out is a cleaned copy.
Sharing a Microsoft Project plan: read, work on it, or decide?
Before choosing the format, decide what has to happen on the other side. There are three cases, and they do not overlap.
- They only need to look: progress, the main dates, where we are. They want a picture, not a document.
- They need to work on it: filter their tasks, do sums, cross it with their own data. They want data, not a picture.
- They need to decide: approve, authorise, choose between options. They want a few big things, and the date.
The worst present for someone who has to decide is a three-hundred-row PDF. The worst for someone who has to work on it is an image they must copy by hand. Two symmetrical mistakes, and I have seen both made in the same week.
Way 1: the PDF, faithful and silent
Project prints to PDF what you see, view by view. It arrives exactly as it is on screen: columns, bars, colours, timescale. It opens anywhere, asks nothing of anyone, and cannot be edited.
What is lost: everything that is not visible. The PDF does not contain the links, the durations you did not put in a column, the calculation behind the dates. The recipient cannot filter, sort or search in any useful way. And above all: what you print is the current view. Send the view you work in, three hundred rows at a daily scale, and you get an unreadable document where the reader seems to be the one at fault.
How to do it well: build a view specifically for the recipient before printing. Few columns, a wide timescale, a filter that keeps only what matters to them. Ten minutes the first time and zero every time after, because the view is saved. The long version is in the view your boss understands at first glance.
Way 2: the image, a slide rather than a plan
Project copies part of a view to the clipboard as a picture, ready to paste into a presentation or an email. The Timeline, the band at the top with only the tasks you choose, was born for exactly this: take the ten rows that matter, put them on the timeline, copy, paste.
What is lost: everything but the message. That is the point, not a flaw. An image is not a delivery of the plan: it is a sentence said with a picture.
When to use it: for whoever has to decide, always. A timeline with six milestones and today’s position does the job forty pages of PDF do not.
Way 3: Excel, the data without the logic
The Export Wizard lets you choose which fields to take out and writes them to a worksheet. The recipient gets rows and columns: they can filter, sum, build pivot tables, cross them with their own data.
What is lost: the engine. Excel keeps the results of the calculation, the dates as they are right now, but not the links, not the constraints, not the critical path. That sheet recalculates nothing: if someone changes a duration, the other dates stay put, and it becomes a false plan the moment it is edited. Tell the recipient, because it is not obvious.
Two practical precautions. First: it almost always pays to leave the summary rows out of the export, or every sum the recipient does will count everything twice, the classic error nobody finds. Second: the export takes out the columns you choose, including the ones you would rather not have sent. More on that below.
Way 4: viewers, the real file, read-only
There are programs and services that open an .mpp without Project: some free, some paid, of very different quality. The recipient sees the plan as a plan, the structure, the bars, often the links, and cannot change it.
What is lost: it depends on the viewer, which is why it is not the way I recommend by default. Free ones typically do not let you add columns or change the view, which is exactly what you need to review a plan you received seriously. Recent file versions are not always supported. And you are sending the original file, with everything it contains.
When to use it: when on the other side there is someone technical who really has to examine the plan, and you trust them with the whole file. The ones worth considering are in the 2026 guide to Microsoft Project add-ons and companion tools.
Way 5: the dashboard, the plan you look at in a browser
The plan’s data can be brought into a visualisation tool, Power BI is the most common, and become a page with a few big numbers that whoever has to decide opens on their phone. It is not a format conversion: it is a change of medium. The plan stays where it is, and only the reading goes out.
What is lost: the detail, which is exactly what it should lose. What it costs: some initial set-up, and the discipline of keeping the source updated. It makes sense when the recipients are many and the cadence is fixed, the monthly committee, the board, and none at all for sending a plan to one person once. Why a dashboard is not a more colourful Gantt, and which kinds exist, is in strategic, analytical and operational project dashboards; the step from plan to dashboard is the one we automated with OneClickReport.
The special case: sending each person only their own tasks
One request fits none of the five ways, and it is the most frequent of all: letting each person know what they have to do. Sending the whole plan is wrong by definition, each person cares about their own row, not the other three hundred, and for years the answer was “you need Project Server”. Not any more: it can be done from the desktop, with one email per person, by hand with filters, with a macro or with a dedicated tool.
The benefit is not only convenience: people who receive only their tasks read them. People who receive the whole plan look for their name for thirty seconds and then close the attachment.
The five ways side by side
What leaves together with the plan
Three of these ways, the file sent to a viewer, the Excel export, and partly the PDF, take far more out of the company than what is on your screen. A Microsoft Project plan holds people’s hourly rates, full names, notes written during meetings, links to internal documents, custom fields with the builder’s annotations, and the history of the saved baselines, that is, the story of every time you replanned.
None of it is visible in the view you are looking at, and all of it travels with the file. When the recipient is outside the company there is a regulatory side too, because some of that data is personal. The practical rule is simple and always applies: the original does not go out, a cleaned copy does. By hand it can be done; the boredom of doing it every time is what led us to build GanttShield, which does the same cleaning in one click on a copy, without touching the original file.
If the plan is yours
Prepare once the two outputs you will use for the whole project: a print view for the periodic PDF and a timeline for the committees. Save them with a name. From then on producing the communication costs two clicks, and that is the only way it really gets done every time.
And always write what date what you send refers to. A PDF without a status date is a document somebody will use three weeks from now believing it is current.
If the plan was sent to you
If you receive a PDF and only have to take note, that is fine. If you have to check it, it is not: from a PDF you cannot check anything that matters, constraints, links, tasks without successors, the baseline. Ask for the file. The request is legitimate and can be put without friction: “I need the file to run a couple of checks on the network, then I’ll get back to you”.
If there is real reluctance on the other side, it happens, and often the reason is precisely the rates inside the file, the way out is to ask for a cleaned copy: no costs and no names, but with structure, links and dates intact. It is everything you need to judge a plan, and it contains nothing confidential.
Frequently asked questions
Is there an official free Microsoft viewer for .mpp files?
No. Microsoft does not distribute a free reader for Project files as it does for other formats. There are third-party tools, free and paid, of very uneven quality and upkeep: before building a company process on one, try it on your own files, because support for recent versions is never a given.
Can someone without Project edit the plan and send it back to import?
Technically you can have an Excel sheet filled in and import it again, and it is a workable way to collect progress. It is fragile: one added row, a changed column order or a date in a different format is enough for the import to do damage. If collecting progress is a recurring job, a process designed for it beats a sheet going round by email: see how to collect actuals from your team.
Do the PDF or the image contain the plan’s hidden data?
Much less than the file, and that is their main advantage: they carry out what was visible in the view. Watch out, though, for the columns you had in the table without thinking, costs, names, notes, and for the document properties, which can keep author and company. If the communication is sensitive, look at the PDF before sending it, as you would with any other document.
Why does the Excel export produce double rows?
Because it includes the summary tasks too, which in Project are containers, not work. In Excel they become rows like the others: whoever sums the hours or cost column counts everything twice. The fix is to leave them out of the export, with a filter that keeps only the detail tasks.
What is the best format for the client?
The client almost never needs the plan: they need the answer to three questions, when do we finish, how much does it cost, what is at risk. A timeline with the milestones and today’s position answers better than any attachment. Attach the detailed plan anyway, for completeness: it serves another purpose, showing that there is real work behind those three answers.
The same checks as a sheet to keep next to the keyboard: the Microsoft Project plan review checklist, with a one-page PDF to print.