This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.
A nursery school takes about a year to build. In January somebody wants the plan, and the honest answer is that nobody yet knows which landscaper will lay the playground in September, whether the slides will be ordered from one supplier or two, or how many days the installation will take. You can invent those tasks now, and they will look precise. Or you can plan what you know at the level you know it, and come back for the rest when it is close enough to see.
The second option has a name: rolling wave planning. It is one of the oldest ideas in scheduling and one of the least practised, because it asks the planner to leave part of the plan deliberately coarse — which feels like not doing the job. This article is about why that is the job, and how to do it in a schedule without losing control of dates, budget or people.
In short
- Rolling wave planning means detailing the work as it gets close: tasks and named people for the next window, planning packages for everything beyond it.
- The usual window is 30, 60 or 90 days. It is worth the effort on projects longer than about six months.
- A planning package is not an empty line: it carries a duration, an effort estimate, a budget figure, a trade and its links — a landscaper, not a person called Marco.
- When a package enters the window you break it into tasks, and the first test is whether the detail fits the package. If it does not, you have found a slippage before the work started.
- The window moves forward at every control cycle: monthly on a project of months, weekly on a project of weeks. If you never roll it, you are not doing rolling wave planning; you are doing a half plan.
Planning is not scheduling
The two words get used as one, and rolling wave planning is easier to understand once they are separated. Planning a project covers scope, risk, communication, budget, procurement: the decisions about what the project is and how it will be run. Scheduling is the part of that plan that lives on a calendar: the activities, the people assigned to them, the money spread over time, and later the progress recorded against them.
Rolling wave planning is a scheduling technique. It does not say “decide the scope later” — the scope, the intermediate objectives and a cost estimate, however rough, have to exist before it makes any sense. What it says is that the schedule of that scope does not need the same density everywhere.
What rolling wave planning is
Rolling wave planning is a form of progressive elaboration: the work that is close in time is planned in detail, the work that is far away is planned at a higher level, and the boundary between the two — the planning window — moves forward as the project advances. The window is usually 30, 60 or 90 days; which one depends on how fast the project changes and how far ahead people and suppliers can realistically be committed.
The rule of thumb I use: on a project shorter than about six months, plan it all — the window would cover most of it anyway. Beyond six months, the tasks you write today for month nine are guesses dressed as a schedule, and the effort spent maintaining them is effort taken from the work that is actually starting.
The technique is not an excuse for a thin plan. It is a way of matching the precision of the schedule to the information available, which is the same principle that governs any estimate: the cone of uncertainty is wide in January whether you like it or not, and a task list written in January for September does not narrow it. It only hides it.
The low-density plan: what a planning package carries
Beyond the window, the schedule is made of planning packages: one line each for a piece of work that will be broken down later. In the nursery-school example there are four of them — Requirements, Design, Construction, Operating services — and the whole project fits on one page.

A package is coarse, not empty. Each line carries five things, and if one of them is missing the package is not ready to be committed to:
- A duration you can defend. Construction, 180 days. Not a start and finish date derived from a task list that does not exist yet.
- An effort estimate in hours, from whatever estimating method the information supports — usually a top-down or parametric figure at this stage.
- A budget figure, so the cost curve of the whole project exists from day one, even if the far part of it is drawn with a thick pencil.
- A trade, not a person. “Landscaper”, “electrician”, “developer”: the kind of resource the work needs. Who exactly will do it is a decision for when the wave arrives.
- Links to the work before and after it. A package is a task like any other: it has predecessors and successors, so a delay upstream moves it and the critical path can run through it. A package with no links does not move when the work before it slips, and the end date of the project ignores it.
What a package does not carry is just as important: no task list, no named people, no day-level links between activities nobody has defined (the package itself is linked; what is inside it is not, yet). Writing those in now does not add information to the plan. It adds lines that will have to be deleted, and — worse — dates that somebody will remember.
Generic resources first, named people later
The resource side of rolling wave planning is where most schedules go wrong, in both directions. Some assign nobody to the far work, so the capacity check is blind beyond the window. Others assign real people to tasks in month nine, and then spend the year reassigning them.
The way through is the generic resource: a resource that stands for a trade or a role rather than a person. Assign “Landscaper” to the Construction package with the estimated hours and the plan can already answer the question that matters early — how many landscaper-days does this project need in September? — without pretending to know which landscaper. When the package enters the window, the generic assignment is replaced by names.
In Microsoft Project this is a native concept, not a workaround: a resource has a Generic field, and Microsoft’s field reference describes it in one line — “the Generic field indicates whether a resource is generic or not”. Generic resources take assignments, hours and costs like any other, so the far part of the plan is costed and loaded, just not staffed.
Detailing the next wave
When a package comes within the window, it gets broken down. The planning starts from the WBS — the work breakdown structure — developed to the level needed to describe the deliverables that are close, and stops there. In the nursery school, Construction breaks into Exterior and Interior; Exterior into Design, Playground, Structures, Surfaces; Playground into Trees, Plants, Slides, Climbing wall, Swings, Sandpit, Water area. That is level 4 of the WBS, and it is enough to assign trades with some precision.
A month or two later, when the slides are the next thing to happen, that one line goes to level 5: Identify needs, Market research, Order the slides, Install the slides, and a milestone — Slides completed — to report against. Now the tasks have people with names and finish-to-start links, because now the information exists.

The moment of detailing comes with a built-in check that no other planning technique gives you for free: does the detail fit the package? The package said 30 days and a certain number of hours. If the five tasks add up to 30, the estimate held. If they add up to 45, you have found a slippage before the work started, while there is still time to re-plan with the client rather than explain afterwards. And if they add up to 20, do not pocket the margin silently: the package was an estimate, and the reason it was wide is worth writing down for the next one.
Rolling the window: the control cycle
The word that matters in the name is rolling. The window is not set once; it advances with the project, and the natural moment to advance it is the control cycle — the same meeting where progress is recorded and the forecast is checked. On a project that lasts months, that is monthly. On a project of a few weeks, weekly. In a crisis the cycle shortens, sometimes to daily, and the window shortens with it.
Each cycle does three things in the same sitting: it records what happened in the window that just closed, it details the packages that are about to enter the next one, and it re-checks the packages still beyond it against what has been learned. How often that sitting should happen, and why the answer depends on the project’s duration, is in How often should you update the project plan?; the mechanics of the update itself — status date, progress, the forecast — are in How to update a Microsoft Project plan.
A schedule where the window was set in January and never moved is the commonest failure of the technique, and it is easy to spot: by April the detailed part is in the past and everything ahead is still packages. That is not a rolling wave. It is a half plan with a good excuse.
Doing it in Microsoft Project
Nothing in the technique needs a special feature; it needs three ordinary ones used with intent.
- A package is a task. Beyond the window, Construction is one auto-scheduled task with its 180-day duration, its generic resource, its hours and its links to the tasks before and after it. Nothing is indented under it yet.
- Detailing is indenting. When the wave arrives, you add the tasks below the package and indent them. The package becomes a summary task and its duration is now the roll-up of its children — which is exactly the test above: compare what Project now shows against the 180 days you had committed to.
- Staffing is replacing. On the new detailed tasks the generic “Landscaper” is replaced by the named people, with the hours that were estimated for the package as the budget to fit inside. The generic resource stays on the packages still beyond the window.
One practical consequence for the baseline. If you save the baseline on the low-density plan — and you should, because that is the plan the client approved — the baseline for Construction is one bar of 180 days. When the package is detailed, the new tasks have no baseline of their own until you decide to set one for them, and the honest way is to baseline the new detail only if it fits the package; if it does not, the conversation about a new baseline comes first. What to compare against once you have re-planned is its own subject.
Where rolling wave planning stops working
It is a technique with a domain, and it is fair to say where the domain ends.
- A client who wants the full detail up front. Some contracts require a complete task-level schedule at signature. You can still plan in waves internally, but the contractual schedule will be the January guess, and you will be measured against it.
- Long-lead items outside the window. A supplier with a six-month lead time has to be ordered from a package, not from a detailed task. The package must carry that date explicitly, or the technique will hide it until it is too late.
- Dependencies that cross the window. If the far work constrains the near work — a permit in month eight that decides the design in month two — that link has to exist between package and task, coarse as it is.
- A team that never rolls it. Said above, worth repeating: without the discipline of the control cycle, the technique degrades into a plan that is detailed only where it no longer matters.
What it does not do, either, is replace a work breakdown structure or an estimate. The packages are only as good as the WBS they came from and the estimating method behind their numbers. Rolling wave planning decides when to go into detail; it says nothing about whether the coarse numbers were right.
Frequently asked questions
What is rolling wave planning, in one sentence?
It is planning the near-term work in detail and the far work at package level, and moving the boundary between the two forward at every control cycle. The name comes from the window that rolls ahead of the project like a wave.
How long should the planning window be?
Usually 30, 60 or 90 days. Pick the shortest window within which you can realistically commit people and suppliers; a longer window only adds tasks that will change. On projects shorter than about six months the window covers most of the project, and the technique adds little.
Is rolling wave planning the same as agile?
No, although they share the idea of not deciding too early. Rolling wave planning keeps a full schedule with dates, durations and a budget for the whole project; only the density changes. An agile backlog does not commit the far work to a calendar at all. You can run a rolling wave schedule and a Kanban board on the same project — the first for the commitments, the second for the day-to-day flow inside the window.
Can I save a baseline on a plan that is still mostly packages?
Yes, and you should: the low-density plan is the one the client approved, so it is the right thing to measure against. When a package is detailed, check that the detail fits it before baselining the new tasks; if it does not, the conversation about a new baseline comes before the baseline.
How do I do it in Microsoft Project?
With ordinary features. A package is a single task with its duration, hours, links and a generic resource — a resource whose Generic field is set, so it stands for a trade rather than a person. When the wave arrives you add the detailed tasks and indent them: the package becomes a summary task whose duration rolls up from the children, and you replace the generic resource with named people on those tasks.
When should I not use rolling wave planning?
When the project is short enough to plan in full, when the contract demands a complete task-level schedule at signature, or when long-lead procurement and cross-window dependencies would be hidden by the coarse packages. In those cases either plan it all, or make sure the packages carry the dates that matter explicitly.
Further reading on this blog
- How to update a Microsoft Project plan: baseline, status date and progress
- How often should you update the project plan?
- What is a baseline in Microsoft Project, and when to save one
- Project estimating methods: top-down, bottom-up, parametric
- The cone of uncertainty: it does not close because time passes
- Work Breakdown Structure: how to build one that survives the project
- Task dependencies: the four link types, hard and soft, and where the link goes
Disclosure: this is the blog of a company that makes project-control software. Nothing above needs our tools: rolling wave planning is a way of deciding how much of the schedule to write now, and the only things it asks of your plan are summary tasks and a generic resource.