Don’t assign resources to summary tasks (the budget shows why)

Resources do not belong on phases: assigning a resource to a summary task in Microsoft Project doubles the phase budget

This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.

The plan says the budget is €120,000. The quote in your hand says €70,000. Nobody got a rate wrong, nobody added tasks: every number is correct, and the total is false. Nine times out of ten the cause is the same, and it sits where nobody thinks to look.

Somebody assigned resources to summary tasks.

In short

  • Summary tasks in Microsoft Project are containers: their duration, work and cost are the sum of the tasks inside, calculated by Project.
  • A resource assigned to a summary row does not replace that sum: it adds to it, calculated over the duration of the whole phase.
  • On a phase of three 10-day tasks in sequence the budget doubles, from 240 to 480 hours, and no row looks wrong.
  • Whoever receives the plan can find it in thirty seconds: show the Resource Names column and look only at the bold rows.
  • The phase owner belongs in a custom field; a cost that lasts as long as the phase belongs on a dedicated task.

Summary tasks are not tasks

A Microsoft Project plan has two kinds of rows, and looking alike is all they have in common. Detail tasks are the work: they have a duration somebody estimated, links, people assigned. Summary tasks, the bold rows with the little triangle to open and close them, are not work: they are containers. You do not decide their duration, Project calculates it, from the start of the first child to the finish of the last. The same goes for cost and hours: Project rolls them up, from the children to the parent, and shows you the total of the phase.

This is where the damage happens. When you assign a resource to a summary task, that cost does not replace the sum of the children. It is added to it, and added over the full duration of the container, which is the duration of the whole phase.

The arithmetic that doubles the budget

Take a tiny phase, so the numbers can be checked in your head. The phase is called Design and holds three tasks in sequence, ten working days each. Each one has the engineer, Bianchi, assigned full time at €50 an hour, eight hours a day.

  • Each task is 10 days × 8 hours = 80 hours, or €4,000.
  • The three tasks make 240 hours and €12,000. Project adds them up on the phase row, which shows 240 hours and €12,000. So far so good: the phase summarises, it does not add.

Now somebody, to mark the phase as “Bianchi’s”, assigns Bianchi to the summary row as well. The phase lasts thirty working days, because the three tasks are in sequence. Project does the only arithmetic it knows: 30 days × 8 hours = 240 hours, at €50 an hour, €12,000. And it adds them.

The same Microsoft Project phase with resources assigned only to the detail tasks, 240 hours and 12,000 euros, and with the resource assigned to the summary task too, 480 hours and 24,000 euros
Same phase, same real work. On the right Bianchi is also assigned to the summary row: hours and cost double, and no row looks wrong.

The phase total becomes 480 hours and €24,000 for work worth 240 and €12,000. We checked it in Project Professional: those are exactly the numbers it shows. The budget has doubled, and not a single row looks wrong. The three tasks tell the truth; the phase tells the truth about what you put into it. It is the sum that lies. On a plan with forty phases and a few of these assignments scattered around, the forecast cost is a figure that means nothing, and the fun starts when someone takes it to the steering committee.

Cost is only the most visible damage

The other three show up later, and cost more.

  • The phantom overallocation. For Project, Bianchi works 100% on the detail task and 100% on the summary that contains it: on the same day, 200%. In the test, the Resource Usage view showed a 200% peak and 16 hours a day for the whole phase, in red, and there is no way to fix it by working on the tasks, because the conflict is with himself. This is the moment somebody gives up on resource levelling and concludes that “Project doesn’t work”.
  • Progress measurement breaks. If you save the baseline with this error inside, the total value of the project is born inflated. Every index calculated on that total, percentage complete, earned value, the work curve, is measured against a base that does not exist. The plan will say you are behind even when you are on time, simply because the denominator is wrong.
  • The phase can no longer be read. The whole point of a summary row is to answer “how much is this phase worth?”. With an assignment of its own, that row stops being a sum and becomes a sum plus something else, and nobody looking at it can tell how much of each.

Why everyone does it, and where that information belongs instead

People who assign resources to phases are not careless: they are trying to put something true into the plan, and that looks like the right place. There are three reasons, all legitimate, and for each one Project has a better place.

  • “I want to show who owns the phase.” The most common reason, and a real need: the plan should say who answers for what. But in Project a resource assignment does not mean “is responsible for”; it means “works on it, for so many hours, and costs”. If what you mean is responsibility, it belongs in a renamed custom field: take a Text field, call it Owner, write the name in it. It becomes a column you can filter and group by, and it does not move the budget by a cent.
  • “But that cost really does last as long as the phase.” The site manager on site for the whole job, the crane hire, the project manager at 20% for six months: real costs, and they really do last as long as the phase. The summary row is still the wrong place, because it is a calculated row. The right answer is a dedicated task running alongside the phase, what schedulers call a hammock task: a detail row like the others, with the resource assigned, whose duration follows the phase. The sum works, the cost is visible, and the summary row keeps doing its job.
  • “I assign it to the phase so it spreads over the tasks.” A widespread belief, and it simply does not happen. Assigning a resource to a summary does not assign it to the tasks inside: it creates one more, separate assignment that lives on the container row. The children stay exactly as uncovered as before. If the work needs spreading, spread it: assign the detail tasks one by one, which is also the only way to set each person’s effort over time.

If the plan is yours

The rule is short: resources go only where the work is. The work is in the detail tasks; summary rows are totals, and the Resource Names column stays empty on them. The work breakdown structure gives the plan its shape; the resources go on its leaves.

If the plan was sent to you

Thirty seconds, and you do not need to know the project.

  1. Show the Resource Names column if it is not there already: right-click a column heading, Insert Column.
  2. Look only at the bold rows. They are the summaries. If one of them has a name in the column, you have found the problem. Scroll to the end.
  3. Confirm in the Resource Usage view. Under each person’s name you see their assignments: if one of them is the name of a phase, the assignment is on the container, and you can see how many hours it is worth.

There is also an indirect test that touches nothing, useful on a large plan: open Project > Project Information > Statistics and compare the total work with what you would expect from the number of people and the duration. If the total hours are far more than reasonable, double, triple, it is almost always this, or its close relative, links drawn on summary tasks instead of on the detail tasks. Both are among the checks for a plan you did not build.

When you find it, the question to ask is not “did you make a mistake?”. It is: “is this cost on the phase on top of the tasks, or did you mean it to replace them?”. The answer is almost always the second, and at that point the budget to discuss is a different one.

How to take resources off summary tasks

On a copy of the file, never on the original. Remove the assignment from the summary row: clear the Resource Names cell on that row, or open Task Information > Resources and delete the assignment line. The hours and cost of the phase go back to being the sum of the children, and the phantom overallocation disappears on its own.

Two warnings. If the plan already has a saved baseline, the baseline keeps the inflated numbers: after the fix the variances become large, and they must be read knowing why. And if the assignment made sense, the site manager who really is there, do not just delete it: move it to a dedicated task, or you are taking a real cost out of the budget.

With resources off the summary tasks, the real workload is read by person: The plan seen by person, not by phase.

Frequently asked questions

If it is a mistake, why doesn’t Microsoft Project stop me?

For the software it is not a mistake: it is a legal operation, useful in particular cases. Project has no way of knowing whether that row is a real cost that goes with the phase or an assignment made by accident, so it accepts it and calculates it. No warning, no different colour: just a bigger total.

Does the same happen on the project summary task?

No, and that is the one place Project does stop you. When we tried to assign an ordinary resource to the project summary task, the row with ID 0, Project refused with the message “Only budget resources can be assigned to the project summary task”. A budget resource is accepted, but it carries neither work nor cost into the totals.

Does it apply to material and cost resources too?

The mechanism changes, the problem stays. Work resources are the worst case, because the arithmetic goes through the duration of the container and also creates the overallocation. Cost and material resources are not multiplied by the duration, but their amount is still added to the children’s: in the test, a €1,000 travel cost and seven reams of paper at €10 took the phase from €12,000 to €13,070. The practical rule does not change: that row stays empty.

What if removing the assignment loses a cost that is real?

Then the cost is moved, not deleted. Create a detail task inside the phase, “Site supervision”, “Crane hire”, with the same duration as the phase and the resource assigned there. The cost stays in the budget, the summary row goes back to being a sum, and for the first time that item is visible to whoever reads the plan instead of being hidden in a total.

How do I find them all in a plan with a thousand rows?

With a filter. Project ships a built-in one for exactly this case, in the filter list: summary tasks that have resources assigned. In the test it showed the one phase with Bianchi on it, and nothing once he was removed. If you prefer to build your own, two conditions are enough: Summary equals Yes and Resource Names is not empty.

The project total was wrong in the baseline too: should I save it again?

Yes, knowingly. Saving the baseline again erases the previous point of comparison, and with it the history of the variances. If the project has just started, that is not a problem. If it is under way, save the corrected baseline in one of the numbered baselines and keep the original: this article explains how to keep several baselines side by side and how to choose which one to compare against.

The same checks as a sheet to keep next to the keyboard: the Microsoft Project plan review checklist, with a one-page PDF to print.

#MSProject #ProjectManagement #ProjectBudget #ResourceManagement #PMO