This article is part of the guide Microsoft Project add-ons and companion tools: the 2026 guide, which maps what you can add around Microsoft Project, and what each kind of tool is for.
On September 24, 2026 Microsoft sent the last notice. Its title leaves no room for interpretation: Final reminder: Microsoft Project Online retires on September 30, 2026. Six days later the service stops, and with it the Project Web App sites where many organisations have kept their plans for years.
This article sticks to what Microsoft has written about the Project Online retirement and to what you can still do about it: what ends on the 30th and what does not, why the data is the part that cannot wait, the steps for the days that are left, where Microsoft says to go next, and what working with nothing but the .mpp files looks like afterwards.
In short
- Project Online retires on September 30, 2026, in every environment: Worldwide, GCC, GCC High and DoD.
- After that date, in Microsoft’s words, you will no longer be able to access your projects or any associated data in the service.
- Project desktop, Project Server and Planner are not affected. If you open
.mppfiles on your own computer, nothing changes for you. - Microsoft’s notice mentions no window after the date to get the data out. Plan as if access ends that day.
- What must happen before the 30th is the copy: every project saved as an
.mpp, plus what lives on the project sites around it. - The migration can come after, from the files. You lose continuity, not the plans.
- The destinations Microsoft names are Planner, Project Server Subscription Edition and Project Operations.
What ends on September 30, and what does not
The final notice, message MC1478955 in the Microsoft 365 Message Center (public archive copy), sets the date for all environments and describes the consequence in one sentence: after Project Online is retired, “you will no longer be able to access your projects or any associated data within the service.”
The same notice is just as clear about what stays: the change “is exclusive to Project Online and does not affect Project desktop, Project Server, or Planner.” That sentence matters more than it looks, because the names are easy to mix up. Project desktop — Project Standard and Project Professional, the application you install on Windows and use to open .mpp files — keeps working. What ends is the online service built on SharePoint, the one you reach through Project Web App.

The retirement was announced in September 2025. Sales to new customers stopped the following month, and from April 2026 no new sites could be created. For organisations already on the service, it has kept working normally until now, and nothing inside it changes on its own before the date: the copy has to be made by someone.
The data is the part that cannot wait
Microsoft’s notice does not mention any grace period, read-only phase or export window after September 30. In the community discussions on the subject, the most experienced voices give the same advice: since Microsoft has not committed to anything after the date, the safe assumption is that access ends that day.
And the plan is not the only thing to think about. An .mpp file holds the schedule: tasks, dates, links, resources, assignments, baselines. It does not hold what grew around the project in its site — documents, lists of risks and issues, the reports someone built on the reporting data. Those need their own copy.
What to do in the days that are left
Five steps, in this order. The first four are about not losing anything; only the fifth is a decision.
- List every project. Start from the Project Center and write down all of them, including the closed ones you may need for an audit, a claim or a lessons-learned review. A closed project nobody saved is still gone on the 30th.
- Save each one as an
.mpp. The route described by Microsoft’s community moderators goes through the desktop client: in the Project Center select the project, choose Open in Microsoft Project on the Projects tab, then in Project use File > Export > Save Project as File (Microsoft Q&A). You need Project desktop installed to do it. Put the date in the file name: in a year you will want to know which copy this is. - Save what is outside the plan. Documents on the project sites, risk and issue lists, and any report or dashboard built on the Project Online reporting data. If a report matters, keep both its output and a note of what it showed.
- Open a few of the saved files from your disk. Not from the server: from the folder where you saved them. Check that tasks, dates, resources and baselines are there. A backup nobody has opened is a hope, not a backup.
- Only then decide where to go. With the files in hand, the move does not have to be made in a panic before the 30th. It can be chosen calmly afterwards.
Where Microsoft says to go
The final notice names three destinations, and they suit very different organisations:
- Planner, including the premium capabilities that come with the Planner and Project Plan 3 licence. It is Microsoft’s direction for cloud project work, and it is lighter than Project Online.
- Project Server Subscription Edition, for organisations that need something close to the Project Online feature set — portfolio, enterprise resources, scheduling — and can run it on their own SharePoint Server.
- Dynamics 365 Project Operations, for organisations whose project work already lives in Dynamics.
There is also a fourth case the notice does not name, because it is not a product to buy. Some teams used Project Online mostly as a shared place to keep plans. For them, Project desktop with the files in a shared folder may be all that is needed. If you are weighing the options, the comparison in project planner tools besides Microsoft Project is a good place to start.
If all you have left is the .mpp file
For many teams, Project Web App was not only a place to store plans. It was where each person saw their own tasks, where timesheets were filled in and approved, and where the PMO read the portfolio. A file on a disk does none of that on its own — and that gap is what people feel first after a move to plain files.
It is also the gap our tools are built for. They all work the same way: they read the .mpp from disk, with no server behind them.
- Each person’s own tasks — SendTask: open the plan file, pick the resources, send. Each person gets their own tasks and an Excel timesheet, with nothing for them to install.
- Timesheets and approvals — GanttTimesheet: send timesheets, collect them back, approve them row by row and write the actuals into the plan.
- The plan for people who do not have Project — MppToExcel turns an
.mppinto a readable Excel workbook, with Project not installed. - Portfolio reporting — OneClickExporter exports the plans to Power BI ready files, and OneClickReport is the finished Power BI report that reads them.
None of this replaces a portfolio server, and it is not meant to. It covers the everyday jobs Project Web App did, with the files you will have on October 1. The whole suite is on the products page, and SendTask, GanttTimesheet, MppToExcel and OneClickExporter can all be tried before you buy.
Frequently asked questions
Can I still access Project Online data after September 30, 2026?
According to Microsoft, no: after the retirement you will no longer be able to access your projects or any associated data in the service. The final notice mentions no grace period or export window after the date, so the safe plan is to have everything saved before it.
Is Microsoft Project desktop being retired too?
No. Microsoft states that the change is exclusive to Project Online and does not affect Project desktop, Project Server or Planner. Project Standard and Project Professional keep working, and so do the .mpp files they open.
Is Project for the web the same thing as Project Online?
No. Project for the web is a different, lighter product that Microsoft is folding into Planner on its own timeline. It is worth knowing that it cannot export a project to an .mpp file: the closest option is exporting the grid view to Excel. Project Online, the one retiring on September 30, is the service built on SharePoint and reached through Project Web App.
Can I save a Project Online project as .mpp without Project desktop?
The route described by Microsoft’s community moderators goes through the desktop client: open the project from the Project Center in Microsoft Project, then use File, Export, Save Project as File. If nobody in the team has Project desktop installed, sort that out first: it is the step everything else depends on.
Do I have to migrate before September 30?
What has to happen before the 30th is the copy of your data. The move to Planner, Project Server or anything else can happen afterwards, starting from the saved files: you lose the continuity of the service, not the plans. Without the copy, there is nothing to migrate.