Project costs in Microsoft Project: where the number comes from, the budget, indirect costs and the S-curve

Project costs in Microsoft Project: the four places a cost can come from, work resources, material resources, cost resources and the fixed cost on the task

Most Microsoft Project plans I am asked to look at have a cost of zero. Not because the project is free: because nobody typed a rate. The tasks are there, the links are there, the people are assigned, and the one column that would turn the plan into a budget was never filled in. Then the budget lives in a spreadsheet, the schedule lives in Project, and the two disagree from the second week.

This guide is about project costs in Microsoft Project: where a task’s cost comes from, how to build a budget out of the plan you already have, how to see what each resource costs you, how to carry the indirect costs that belong to no task, and how to read the curve the finance people actually want. Nothing here needs an add-in. It needs a few columns that are already there.

In short

  • A task’s cost comes from four places: work resources (hours × rate), material resources (quantity × unit cost), cost resources (an amount typed on the assignment) and a fixed cost typed on the task. Project adds them up and rolls them up to the summary and the project.
  • The budget is the plan with rates on it, baselined. Build the WBS, assign the resources, put the rates in, get the number approved, save the baseline. From then on the meeting is about the Variance column.
  • What each resource costs you is one view away: Resource Sheet with the Cost table, sorted by cost.
  • Indirect and recurring costs — the project manager’s time, the site overheads — belong to no WBS task. Carry them on a hammock task that stretches with the project, so a delay costs money in the plan as it does in life.
  • The finance department does not want the Gantt. It wants the cost S-curve, and Project draws it in six clicks.

Where project costs come from in Microsoft Project

Project does not have a “budget” you type in. It has a cost it calculates, task by task, from four sources, and understanding the four is most of what there is to understand.

Diagram of where a task's cost comes from in Microsoft Project: a work resource at hours times rate, a material resource at quantity times unit cost, a cost resource with an amount typed on the assignment, and a fixed cost on the task, adding up into the task cost which rolls up into the summary and the project summary task
One task, four sources. The task adds them up; the summary adds the tasks; the project summary task adds the summaries. The Cost table shows the same chain in columns.
  • Work resources — people and equipment with a Standard Rate per hour (and, if you use it, an overtime rate and a cost per use). Forty hours of a site engineer at 60 an hour is 2 400. This is where most of a project’s cost usually sits, and where most of the zeros come from: no rate, no cost.
  • Material resources — things consumed in a quantity: cubic metres of concrete, licences, boxes. The rate is per unit, the assignment says how many units, the cost is the product.
  • Cost resources — an amount with no hours and no rate behind it: a travel budget, a permit fee. You type the figure on the assignment. They exist so that a cost can be tracked by category (all the travel on the project) without inventing hours for it.
  • Fixed cost on the task — a figure typed straight into the task’s Fixed Cost column: a subcontract lump sum, a fee. No resource behind it; the task simply costs that much more.

The four add up into the task’s Cost. Summary tasks add up their children; the project summary task (row 0, switched on in the Format tab) adds up the summaries and is the number your budget is made of. The Cost table — right-click the Select All corner of the Gantt Chart view, choose Cost — lays the chain out in columns: Fixed Cost, Fixed Cost Accrual, Total Cost, Baseline, Variance, Actual, Remaining. Those seven columns are the whole cost side of Project; everything below is a way of reading them.

Building the budget from the plan

A budget in Project is not a separate document. It is the plan with rates on it, frozen at the moment it was approved. Four steps, in this order:

  1. Get the work breakdown structure right first. Every cost hangs on a task, so a task that is missing from the WBS is a cost that is missing from the budget. Switch the WBS column on: the code it shows (1.2.3) is what the finance people will want to see next to each line.
  2. Define the resources with their rates, in the Resource Sheet. Work resources with a Standard Rate, material resources with a unit and a rate, cost resources for the categories you want to track. A custom text field on the resource — “Budget type: Labour / Travel / Materials” — lets you group the sheet later by the categories the accounting side uses, instead of by Project’s own types.
  3. Assign, and let the number appear. As resources go on tasks, the Cost column fills in. This is the moment to check the total against the estimate the project was sold on; how that estimate was built, and how far it can be trusted, is the subject of Project estimating methods.
  4. Get it approved, then save the baseline. When the number is accepted — by the sponsor, the client, the steering committee — save the baseline. Total Cost is copied into Baseline Cost on every task, and from now on the column that matters is Variance: Cost minus Baseline Cost, the distance between what you said and what the plan now expects.

Two things worth knowing about that last step. The baseline is what makes the budget a budget: without it the Cost column just follows the plan around, and there is nothing to be over or under. And the baseline should be saved after approval, not before: a baseline saved on a plan that then gets negotiated down is a budget nobody agreed to.

The amount you were authorised to spend, as opposed to what the plan costs, has its own place in Project: budget resources on the project summary task, compared with the plan category by category.

What each resource costs you

“How much have I committed for each resource on this project?” is the question that comes before approval, when the numbers go to whoever pays. Project answers it two ways, one for the detail and one for the summary.

The detail of one resource. In the Gantt Chart view, switch to the Cost table, hide the summary tasks (Format tab, untick Summary Tasks), then apply the built-in filter Using Resource… and pick the resource. What is left is every task that resource is assigned to, with its cost. Copy the rows into Excel if somebody wants to work on them.

The summary of all resources. Switch to the Resource Sheet view and apply the Cost table there. One row per resource with Cost, Baseline Cost, Variance, Actual Cost and Remaining Cost: the budget committed to each, what has been spent, what is left. Sort by Cost descending and the three resources that carry most of the money are at the top, which is usually where the conversation should start.

Column (Cost table)What it holdsWhen it changes
Costwhat the plan now expects: actual to date plus remainingevery time the plan or the progress moves
Baseline Costthe approved budget, frozenonly when you save a baseline
VarianceCost minus Baseline Costthe number the meeting is about
Actual Costwhat the recorded progress has consumedas you record actuals
Remaining Costwhat the rest of the work will consumeas the remaining work changes
The same five columns exist on tasks and on resources; they are two views of one set of numbers.

One limit to state plainly: this works when the resources belong to this project. With a shared resource pool across several plans, the Resource Sheet of one plan shows only that plan’s assignments, and the question “what does this person cost the company this month” has to be asked of the pool, not of the project.

Indirect and recurring costs: the hammock task

Some costs belong to no task in the WBS and grow with time rather than with work: the project manager’s own hours, the site cabin, the monthly rent of the equipment, the travel that nobody wants to charge to a specific activity. Leave them out and the budget is short by a fixed amount every month; worse, when the finish slips by two months the plan does not show that the overheads slipped with it.

The answer is a hammock task (also called a level-of-effort task): an activity whose start is tied to the start of the project and whose finish is tied to the finish, so that it stretches and shrinks with everything else. Assign the overhead resources to it — the project manager at 50%, the site cabin as a cost resource per month — and the cost of the delay appears in the plan the moment the delay does.

A hammock task for site overheads spanning from the project start milestone to the project finish milestone above a small Gantt chart, with the two techniques for building it in Microsoft Project: paste-linking the start and finish of the milestones, or a summary task holding two milestones linked start-to-start and finish-to-finish
The hammock spans the project. Two ways to build one in Project: paste links on Start and Finish, or a summary holding two milestones linked SS and FF.

Project has no hammock button, but two techniques give the same result:

  1. Paste link. Create the task at outline level 1 with no dates and no duration typed. Copy the Start cell of the first milestone, then on the hammock’s Start cell use Paste Special → Paste Link; do the same from the Finish cell of the last milestone into the hammock’s Finish. The task now follows both ends. It will always show as critical and as long as the project, which misleads readers: give it a custom Flag field set to Yes and a filter “Flag ≠ Yes” to hide it when you present.
  2. Two milestones. Create a summary task — “Support” — containing only two milestones. Link the first start-to-start to the project start milestone and the second finish-to-finish to the project finish milestone. The summary spans between them, and the overhead resources go on it. Nothing to paste, nothing to break, and the same trick works for a single phase: link the milestones to the phase instead of the project.

To charge the overheads as the project runs, update the hammock’s % Complete in proportion to the time elapsed — 40% of the way through the project, 40% complete — and its Actual Cost follows. It is the one task on the plan where “percent of time gone” is the honest measure of progress.

When a fixed cost accrues

The Fixed Cost Accrual column looks like a detail, and it decides the shape of the curve. It has three values: Start, End and Prorated. We measured it in Project 16.0 on a four-week task with a fixed cost of 1,000: with Start the whole 1,000 falls in the first week, with End all of it in the last week, with Prorated 250 a week. The total is always 1,000.

The practical rule: pick the value that matches how the amount will actually be invoiced. A down payment on order is Start, a final payment on completion is End, a monthly fee is Prorated. Leaving the default on every task gives the right total and the wrong cash curve.

The curve the finance people want

A project manager thinks in dates. Whoever pays thinks in cash: how much goes out this month, how much next, when the credit line is needed. The Gantt does not answer that. The cost S-curve does — the project’s cost added up period after period, which starts slow, climbs through the middle of the project and flattens at the end.

Project draws it from the Resource Graph in split view: Resource Sheet on top, all resources selected, Resource Graph below showing Cumulative Cost as a line. The six steps, the one that everybody skips and the way to read two curves against each other are in How to show the cost S-curve in Microsoft Project; the same curve for hours instead of money is in The work S-curve.

One curve is a forecast. Two — baseline against actual, at today’s date — are a control tool, and reading the distance between them in money and in time is the first step towards Earned Value, which is what the cost side of Project is ultimately for.

What Project’s cost side does not do

It is worth being clear about the edges, because the disappointment usually comes from expecting accounting.

  • It is not a ledger. No invoices, no payment terms, no VAT, no purchase orders. Project knows what the work costs, not when the money leaves the account. The S-curve is a cash forecast by accrual, not a cash-flow statement.
  • Actuals are only as good as the progress recorded. Actual Cost is derived from the actual work and the actual dates you enter; if progress is guessed, cost is guessed with it. How to collect it properly is in How to collect actuals from your team.
  • One currency per plan. Rates and costs are in the project’s currency; a multi-currency budget is a spreadsheet job.
  • Shared resources cost across projects, and a single plan cannot see that. With a resource pool, the pool is where the company-wide question is answered.
  • The estimate is not improved by the tool. Rates times hours is exact; the hours were a guess. A precise-looking Cost column built on rough estimates is still rough, and the honest thing is to say so.

Frequently asked questions

Where does the cost of a task come from in Microsoft Project?

From four sources added together: work resources (hours × standard rate), material resources (quantity × unit rate), cost resources (an amount typed on the assignment) and the Fixed Cost typed on the task itself. Summary tasks add up their children and the project summary task adds up the whole plan.

How do I set a budget in Microsoft Project?

Put rates on the resources, assign them to the tasks, check the total against the estimate, get it approved and save the baseline. Baseline Cost is the budget; from then on the Variance column shows how far the plan has drifted from it. Without a baseline there is a cost but no budget.

How do I see how much each resource costs on the project?

Open the Resource Sheet view and apply the Cost table: one row per resource with Cost, Baseline Cost, Variance, Actual and Remaining. Sort by Cost descending. For the task-by-task detail of one resource, use the Gantt Chart with the Cost table, hide the summary tasks and apply the Using Resource filter.

How do I add indirect or recurring costs to a plan?

With a hammock task tied to the start and finish of the project (or of a phase), so it stretches when the plan does. Build it with paste links on Start and Finish, or with a summary task holding two milestones linked start-to-start and finish-to-finish. Assign the overhead resources to it and update its % Complete in proportion to the time elapsed.

What is the difference between Cost, Baseline Cost and Actual Cost?

Cost is what the plan now expects: actual to date plus remaining. Baseline Cost is the approved budget, frozen when the baseline was saved. Actual Cost is what the recorded progress has consumed so far. Variance is Cost minus Baseline Cost, and it is the number to watch.

Can Microsoft Project replace my cost accounting?

No. It knows what the work costs and when it is expected to be consumed; it does not know invoices, payment terms, VAT or purchase orders, and it works in one currency per plan. Use it for the budget, the variance and the S-curve, and let the ledger be the ledger.


Disclosure: this is the blog of a company that makes project-control software. Nothing above needs our tools: the Cost table, the Resource Sheet, the Using Resource filter and the Resource Graph are standard Microsoft Project, and the hammock task is a habit older than the software.

#ProjectCosts #MSProject #ProjectBudget #ProjectControl #EarnedValue