When people say “the project budget” they usually mean two different things, and Microsoft Project keeps them apart. There is the cost of the plan: what Project calculates from resource rates and assignments. And there is the budget: the amount you have been given to spend, on people, on travel, on materials. The first comes from the tasks, the second comes from outside. The project manager’s job is to keep them side by side.
Here is the procedure step by step, with the piece almost nobody uses: budget resources, which exist in Project precisely to write the budget next to the plan. The broader picture of costs is in project costs in Microsoft Project.
In short
- To create a project budget in Microsoft Project you need the WBS, resources with their rates, a “Budget Type” field that groups them by category, and budget resources holding the authorised amount.
- Budget resources can be assigned only to the project summary task, row 0: Project refuses them on any other task. Measured in Project 16.0.
- The budget is not added to project cost: you read it in the Budget Cost and Budget Work columns and compare it category by category.
First the WBS: every cost sits on a task
An accurate budget starts from the structure of the work. Every cost Project calculates sits on a task, so a task missing from the WBS is a cost missing from the budget. It is worth showing the WBS column: a code like 2.2.1 is what accounts will want to see next to every row.
Resources, grouped by “Budget Type”
In the Resource Sheet every resource has its type and its rate: people are Work resources with an hourly standard rate, flights and hotels are Cost resources. Then add a custom text field on resources, “Budget Type”, holding the categories accounts use: in the example, Labor and Travel. Group the sheet by that field and each category gets its own total.
The budget: budget resources on row 0
In the same Resource Sheet, create one resource per category that neither works nor costs anything: “Budget – Labor” as a Work resource, “Budget – Travel” as a Cost resource. In the Resource Information dialog, tick the Budget box that makes it a budget resource, and give it its category in the “Budget Type” field, like the others.
- Show the project summary task: Format tab, Project Summary Task box. It is row 0.
- Assign the budget resources to row 0. Only there: in our test, when we assigned one to an ordinary task, Project refused it with a message saying budget resources can only be assigned to the project summary task.
- Switch to the Task Usage view, add the Budget Cost and Budget Work columns, and type the authorised amounts on the row 0 assignments: in our test, 100 hours of work and $2,000 of travel.
The point that matters: the budget does not enter project cost. In the test the plan cost $2,100 ($1,600 of work and $500 of flights) both before and after typing in the $2,000 travel budget. The budget sits next to the plan, not inside it: it is the yardstick you measure the plan with.

Assignments, and the comparison
People are assigned to tasks as usual, and their cost appears by itself. Cost resources, on the other hand, start at zero: the price of the ticket or the hotel is typed on the assignment, in the Task Information dialog or in the Task Usage view.
The comparison happens in the Resource Usage view grouped by “Budget Type”, with the Cost, Budget Cost, Work and Budget Work columns: in each group, the budget resource’s row says how much you can spend, and the total of the others says how much the plan expects to spend. In our test, 40 hours planned against 100 authorised, $500 of travel against $2,000.
Approval, baseline, control
When the plan fits the budget and is approved, you save the baseline. From then on there are three numbers for each category: the budget, what you were given; the baseline, what you said you would spend; and the plan’s current cost, what you expect to spend today. The Variance column of the Cost table measures the distance between the last two.
To communicate it there is the Report tab, available since Project 2013: reports can be customised with charts and tables on the fields you need, budget fields included.
The budget is what you were given, the baseline is what you promised, the cost is what you will spend: three numbers, three different questions.
Frequently asked questions
What is the difference between budget and baseline?
The budget is a limit that comes from outside, the authorised amount. The baseline is a snapshot of the approved plan, saved inside Project. They can match, but they don’t have to: a plan can be approved below budget and leave a margin.
Can I assign a budget resource to a phase?
No: only to the project summary task. If you need a budget per phase, the way to do it is one value per phase in a custom cost field, compared with the cost of the phase.
Does the budget change the project cost?
No. In our test the plan cost stayed at $2,100 after typing in $2,000 of travel budget and 100 hours of labor budget. The budget is read in its own columns and only serves the comparison.
Which versions have budget resources?
The desktop versions from Project 2007 onwards; the Report tab from Project 2013. The tests in this article were run on Project 16.0, the base of Project 2016, 2019, 2021, 2024 and Microsoft 365.
Where the cost numbers come from, how to build the S-curve and what Project’s cost side does not do are in project costs in Microsoft Project.