The superintendent moved the crew: don’t rewrite the links

The crew jumped areas, the logic should not: in a test plan, keeping the links and recording actuals moves the finish from 13 March to 27 March, while one option switched off leaves it at 13 March and hides the delay

This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.

Every Monday, the same job. The schedule says Area A, then B, then C. On site, the superintendent took the framing crew to half in A, then moved it to B for a couple of days, then to C, to keep people busy. So the project manager opens the plan and rewrites predecessors and successors until it matches what happened.

A project manager asked exactly this in a forum for construction managers: how do I keep up with this without changing the links every week? The short answer is that you should not be changing them at all.

In short

  • When the crew moves between areas, leave the links alone: they describe the building, not the week.
  • Record what happened as actuals: actual start, actual finish, days still needed, per area.
  • In Microsoft Project, keep Split in-progress tasks on, or the delay will not show.

The links say what must happen, not what happened

A link between framing in Area A and the electricians in Area A says something about the building: the electricians need the walls. That does not change because the crew went somewhere else for two days. The link was right on Monday and it is still right.

What changed is what the crew did. That goes somewhere else in the plan: into the actuals. For each area, three things: the day the work really started, the day it really finished if it did, and how many days it still needs. Framing A started on the 5th, half done, five days to go. Framing B started on the 12th, six days to go. Framing C started on the 19th, eight to go. That is the whole update for a week of out-of-sequence work, and not one link is touched.

Gantt chart of the plan and the site by 23 January: framing was planned in area A, then B, then C; on site the crew did half of A, then moved to B and then to C, while the electrical work in area A is still waiting for the walls
Grey: the plan. Dark blue: what the crew actually did, a piece of each area. The electricians in A are still waiting.

When you rewrite the links instead, you are not updating the plan. You are drawing a new one every week that agrees with the site, and a plan that always agrees with the site can never tell you anything you did not already know.

What the plan says if you leave the links alone

We built this exact case in Microsoft Project: three trades, three areas, a planned finish on 13 March, and the week of jumping recorded as above. With the links left as they were, the finish moved to 27 March. Two weeks later, because Area A is still half framed and the electricians cannot start there, and everything after them waits too.

That is not the plan going wrong. That is the plan doing its job: the two days of fill-in work did not save two days, they left three areas half done and none of them ready for the next trade. Better to see it in January than two months before handover.

A plan that always agrees with the site can never warn you about it.

One checkbox to look at

There is one condition. In Microsoft Project, the option Split in-progress tasks (File > Options > Schedule) has to be on. It is on by default, but plans get passed around and options get changed. We ran the same update with it off, and the finish stayed on 13 March: the work still to do in Area A stayed in a week that was already over, and the delay simply did not show.

Two Gantt charts after the same update: with Split in-progress tasks on, the rest of framing A moves after the status date, the electrical work in area A waits and the finish moves from 13 March to 27 March; with the option off, the rest of framing A stays in a week already gone, the electrical work starts as if area A were done and the finish stays at 13 March
Same week, same actuals, same links. With the checkbox on the plan shows the two weeks; with it off, it hides them.

If your schedule never seems to slip until the last two months, and then slips all at once, that checkbox is the first thing to check.

Frequently asked questions

So should I never change the links?

Change them when the order of the work changes for good, for example when you decide that from now on framing goes C, B, A. Do it once, write down why, and keep the baseline as it was. A crew moved for a few days is not a new order: it is progress, and it goes into the actuals.

Why not just ask for percent complete?

Because on a site the question is where, not how much. Framing at 40% spread over three areas hands nothing over to the next trade; the same 40% in one area may hand over a whole floor. More on what to ask for in how to collect actuals from your team.


If getting the dates back from the field is what eats your week, GanttTimesheet sends each person their own rows, imports what comes back, lets you approve it line by line, and writes it into the plan.