Products › OneClickExporter › How it works
Application guide — version 3.2.8How OneClickExporter works: from the plan to the files, step by step.
Open a plan, a master plan with all its subprojects or a whole folder of plans, choose what to export and in which format, press one button. Out come up to ten CSV files whose columns never move, ready for Power BI, Excel, Qlik or Tableau, or for the business system that imports them every week. Microsoft Project does not need to be installed.
What you need, and what you don't
The list is short on purpose: OneClickExporter reads the plan file by itself, without going through Project.
Windows 10 or 11, 64-bit
The .NET runtime travels inside the package, so there is nothing else to install. With the portable package you don't even need administrator rights.
A saved plan
An .mpp file or the .xml saved by Microsoft Project, a master plan with its subprojects included. The plan is exported as it is saved on disk: save before you export.
A destination folder
The folder your tool will read the files from. Every export rewrites the files under the same names, so whatever reads them never needs setting up again.
Six steps, done once
The application remembers your choices: from the second time on you select the plan and press Export data. The interface speaks six languages; the language menu sits at the bottom right, under Language.
Choose between a project and a folder
In the left panel choose Select a project to work on one plan at a time, or Select a folder to put every plan in a folder into a single dataset, the way a master plan would. That is the typical shared folder where each project manager drops their own file.
Folder export starts from the 5-project licence tier; the 15-day trial includes it.

With Select a folder every plan in the folder becomes a single dataset. Add the plan and select it
With Add project pick the
.mppor.xmlfile: it joins the list and stays there for next time. If it is a master plan, its subprojects come with it: you don't add them one by one. Select it, and the panel beside it shows what is inside before you export anything: period, progress, status date, calendar, tasks, milestones, resources and assignments, whether a baseline exists, whether it is a master plan or uses a resource pool, and earned value.Selecting the plan also proposes the date window for the time-phased data (the plan dates, two months before and two after) and switches the pool option on by itself when the plan uses one.

Once the plan is selected, the panel shows what it holds before you export anything, earned value included. Choose what to export
In Export options switch on only what your report uses. Projects, tasks, resources, assignments and the governance scorecard always come out; the rest is switched on here:
- Timephased Earned Value: the daily earned value curve of each project, up to the status date.
- Milestones, with the number of the custom field that classifies them (Custom Field #, 1 to 30, default 21).
- Preliminary works: the work that has to start earlier, with its deadlines.
- Shared resource pool, for plans that take their resources from a pool.
- Timephased assignments: work and cost day by day, in the From … to window you choose by dates or by years.
- Resource availability and overallocation: switches on together with timephased assignments.
Projects summary does the opposite: it exports only the summary row of each project, for a portfolio seen from above.

The options you switch on decide which files are filled; here the time-phased window is set by dates. Choose the format the receiver expects
In Export format decide what the files look like, depending on who reads them:
- CSV delimiter: comma (default), semicolon or tab. Where Windows uses the comma as the decimal separator, as in much of Europe, Excel expects the semicolon, or it opens everything in one column.
- CSV UTF-8 with BOM: switch it on if people open the files in Excel with a double click, so accented and special characters come out right. Power BI, Qlik and Tableau read UTF-8 without it.
- Also export JSON: one file per table, numbers as numbers and empty values as
null, for a pipeline or an application. - Also export Excel (XLSX): a single workbook,
OneClickExport.xlsx, with a sheet and a table for each file, real dates and real numbers. Excel does not need to be installed to produce it.

Comma delimiter and BOM, plus JSON and XLSX. Set the destination folder
In Destination folder for exported data use Browse to choose the folder your tool will read from. If you use OneClickReport, Power BI dashboard to open takes its file too, so it opens with one click after the export.

The folder your tool will read the files from; the dashboard to open is needed only with OneClickReport. Press Export data
Press Export data. While it works the application shows the current phase; at the end the Export completed summary tells you how many rows came out for each project, any warnings, the delimiter, the formats and the folder. A real master plan that used to take about twenty-five minutes through Project comes out in a few seconds.
Then point your tool at the folder. With OneClickReport, Open dashboard and a refresh are all it takes.

The summary of a master plan: three subprojects in a single export, with the total.
Ten files, always with the same names and the same columns
Each file is a table: rows and columns that a BI tool relates to one another, not one flat sheet. A file whose option is off is still written, with just its header row: whatever reads the folder always finds every file in place.
| File | What it holds | When it is filled |
|---|---|---|
Projects.csv | One row per project: dates, durations, work, costs, status, days late, consolidated earned value | Always |
Tasks.csv | The tasks, custom fields included | Always |
Resources.csv | The resource sheet: type, work, costs, rates, calendar, custom fields | Always |
Assignments.csv | The assignments: planned, actual and remaining work and cost | Always |
Governance.csv | The plan scorecard for the PMO, one row per project | Always |
Milestones.csv | The milestones, with status, type and days late | Milestones |
TimePhasedAssignments.csv | Daily work and cost of every assignment | Timephased assignments |
TimePhasedResources.csv | Daily availability, remaining work and overallocation of every resource | Resource availability and overallocation |
EarnedValue.csv | The daily earned value curve of each project | Timephased Earned Value |
PreliminaryWorks.csv | The preliminary works, with their three dates and deadline status | Preliminary works |
ISO dates (2026-09-30), a decimal point and no thousands separator, whatever the Windows language. File and column names in English, fixed.
An open format, for any tool
CSV was chosen on purpose: every analysis tool can read it, and even a system from twenty years ago can import it. Power BI is one destination, not the only one.
Power BI
Build your own model on the files, or use OneClickReport, the kit of dashboards built on these very CSVs: open, refresh, and the plan data is in place.
Excel
Power Query and the Excel data model connect the same files and build the same analyses: we rebuilt the OneClickReport dashboards in an Excel workbook fed by the same CSVs. To just open a file, there is the XLSX output.
Qlik, Tableau and other BI tools
They read CSV and have data-modelling tools on a par with Power BI's, if not better. Separate tables and ISO dates are what those tools expect.
Business and legacy systems
An ERP, a timesheet system, a data warehouse: their importer wants a file that never changes shape. Here file name, columns and order stay put. How to feed a system that predates APIs.
Pipelines and applications
The JSON output gives one file per table, with the types already right. Together with the command line, it is the way to bring Project data into an automated process.
The five most common stumbles
Excel opens the CSV all in one column
Accented characters come out garbled
The numbers don't match what I see in Project
An output file is reported as in use
The project name in the files ends with [TRIAL]
Projects.csv and Governance.csv. Once you activate a key in the same window, the mark disappears from the next exports.Fifteen days on your own plans, no key
The trial is a portable package: unzip it and it runs, with no installation and no administrator rights. It runs the complete product, command line included, on as many projects as you like.
Download the trial
Portable for Windows x64, about 100 MB: the .NET runtime is inside the package. No card details asked for.
Download the free 15-day trialBuy a licence
Yearly subscription per seat, from €79 to €999 excluding VAT, depending on how many projects a single export covers. The key goes into the copy you already have: nothing to download again. You have 14 days to change your mind.
Buy OneClickExporter Compare the six licence tiersWindows may say it does not recognise this program yet, or block the download of a file few people have downloaded. Check that the publisher is Rosario Rizzo — every file in the package is digitally signed.
Questions about using it
Do I need Microsoft Project installed to export?
.mpp or .xml file directly, so it exports on a machine that has never had Project installed, including a plan a supplier or a client has sent you.Do I need Power BI?
Does the export change my plan?
.mpp file, and the files go into a folder you choose, on your machine. Nothing is uploaded anywhere.Can I export several plans together?
Do I have to set everything again each time?
The plan stays in Project. The data goes where it is needed.
Choose once what to export and in which shape. From then on it is one click, or none.