Source: I looked at ~300 real .mpp schedules: 86% had no baseline saved, 63% had tasks with no links
u/Sheeebooo · r/MSProject (post by the founder of Onplana, a scheduling software vendor) · 17 October 2026
Why it matters
These are a vendor's figures from schedules that people chose to upload to a free health check, so they describe that sample, not the industry: take the direction, not the decimals. Two findings still deserve a look at your own plans. 86% without a saved baseline means a slip cannot even be measured, and a missing baseline is zero, not "today's plan"; and the "safer" unlinked plans are an artefact, since a task that nothing drives cannot be pushed by a simulation any more than by reality. Quality percentages also move a great deal with what you count, so ask any checker which tasks are in the denominator before you compare two scores.
— Rosario Rizzo
Related
- What is a baseline in Microsoft Project: what it is, when to set it, and what a missing one does to every variance
- How to review a Microsoft Project plan you did not build: five checks: typed versus calculated dates, network integrity and the other fast checks
Rosario Rizzo’s NewsRadar: curated news on reliable schedules, the Microsoft Project ecosystem and practical AI, each with a comment on why it matters to people who plan. How we choose the news