Reading negative float in P6, and the same signal in Microsoft Project

Practice pick · a piece of craft worth reading

Source: Negative Float in Primavera P6
Ten Six Consulting · 19 October 2026

What to take away

The takeaway is the article's own line: negative float is a diagnostic, not an error, and clearing it by dragging bars or accepting a new constraint only hides the date you are going to miss. The same holds in Microsoft Project, where negative slack always traces back to a missed constraint or a missed deadline, and a deadline does not move the task, it only takes away its slack, so the warning stays visible. Before an update goes out, filter for negative slack and write one line per case on which date drives it and what you will do about it.

— Rosario Rizzo