Keeping the original Microsoft Project task numbers when a schedule moves into P6

Practice pick · a piece of craft worth reading

Source: P6 and Store Microsoft Project Task IDs
Ten Six Consulting · 26 October 2026

What to take away

The takeaway is the order of operations: import the Project file through XML, copy the original numbers into a text field with a Global Change, and only then renumber in P6 with gaps of ten. One thing to add from the Microsoft Project side: the Task ID the article preserves is a row position, and it changes for every row below whenever a task is inserted in Project. If the .mpp keeps living alongside the P6 schedule, store the Unique ID as well, because that is the number that stays with the task.

— Rosario Rizzo