Source: Change % complete type for earned value analysis
Microsoft · Microsoft Support · accessed 28 October 2026
Found via a discussion on r/MSProject
Why it matters
By default, Microsoft Project measures earned value from % Complete, which tracks duration, not from what was physically built. Microsoft's own example is a wall of 100 stones: 60% built, but only 50% complete by time. If you pay by the stone, you want Physical % Complete, and you set it in File > Options > Advanced, which applies only to new tasks, or task by task. Decide it per project at the start, because every earned value figure downstream depends on that choice.
— Rosario Rizzo
Related
- Earned Value: the complete guide to PV, EV, AC, SPI and CPI in Microsoft Project: planned value, earned value and actual cost at the same date, with a worked example in Project
- How to collect actuals from your team and update the plan: what to ask your team for: three numbers, not a percentage
Rosario Rizzo’s NewsRadar: curated news on reliable schedules, the Microsoft Project ecosystem and practical AI, each with a comment on why it matters to people who plan. How we choose the news