Microsoft Project: earned value can follow time spent or physical progress, and the default is time

Source: Change % complete type for earned value analysis
Microsoft · Microsoft Support · accessed 28 October 2026
Found via a discussion on r/MSProject

Why it matters

By default, Microsoft Project measures earned value from % Complete, which tracks duration, not from what was physically built. Microsoft's own example is a wall of 100 stones: 60% built, but only 50% complete by time. If you pay by the stone, you want Physical % Complete, and you set it in File > Options > Advanced, which applies only to new tasks, or task by task. Decide it per project at the start, because every earned value figure downstream depends on that choice.

— Rosario Rizzo