IPA study of 91 pipeline projects: two thirds missed mechanical completion, and slip tracks planning quality measured before FID

Source: Delivering Predictable Gas Pipeline Projects to Meet Increased LNG and Power Generation Demand
Parth Kothekar · Independent Project Analysis (IPA) · 9 October 2026

Why it matters

The useful number here is not that two thirds of the 91 pipelines missed mechanical completion, but that IPA could see it coming: projects with better planning, measured before the investment decision, slipped about 10% in execution on average, while for the poorly planned ones the slip approached 50%. The main driver IPA names is the failure to define the project well before making commercial commitments. If you are handed a target date at sanction, the honest deliverable is a schedule that shows what that date assumes, so the gap is visible before the contracts are signed.

— Rosario Rizzo

Related

Rosario Rizzo’s NewsRadar: curated news on reliable schedules, the Microsoft Project ecosystem and practical AI, each with a comment on why it matters to people who plan. How we choose the news

Scroll to Top