Source: FEED: The Critical Engineering Phase Too Often Overlooked in Capital Projects
Michael Mace · Independent Project Analysis (IPA) · 29 October 2026
Why it matters
IPA reports that 55% of large projects (over $20 million) are authorised without a completed FEED, that skipping it means 10% to 20% more slip in detailed engineering, and that the execution slip it causes lasts longer than the time the shortcut was meant to save. For a planner, that is the risk hiding in a compressed front end: the execution schedule is built on a definition that is not there yet. When FEED is cut short to hold a date, it is worth saying so on the plan, as an assumption with its own risk, rather than letting the execution durations quietly carry it.
— Rosario Rizzo
Related
- The cone of uncertainty: it does not close because time passes: why an estimate narrows only when decisions are taken, not as the calendar moves on
- IPA: 80% of projects finished later than their earliest (FEL 1) schedule, and 15% took about twice as long: NewsRadar, 26 October 2026: IPA's data on how far finish dates move from the earliest schedule
- IPA's Edward Merrow: many capital projects are schedule driven in sectors where speed adds little value: NewsRadar, 29 October 2026: why so many projects are driven by the schedule even where speed adds little value
Rosario Rizzo’s NewsRadar: curated news on reliable schedules, the Microsoft Project ecosystem and practical AI, each with a comment on why it matters to people who plan. How we choose the news