IPA: a majority of large projects are authorised before FEED is complete, and the execution slip outlasts the time saved

Source: FEED: The Critical Engineering Phase Too Often Overlooked in Capital Projects
Michael Mace · Independent Project Analysis (IPA) · 29 October 2026

Why it matters

IPA reports that 55% of large projects (over $20 million) are authorised without a completed FEED, that skipping it means 10% to 20% more slip in detailed engineering, and that the execution slip it causes lasts longer than the time the shortcut was meant to save. For a planner, that is the risk hiding in a compressed front end: the execution schedule is built on a definition that is not there yet. When FEED is cut short to hold a date, it is worth saying so on the plan, as an assumption with its own risk, rather than letting the execution durations quietly carry it.

— Rosario Rizzo

Related

Rosario Rizzo’s NewsRadar: curated news on reliable schedules, the Microsoft Project ecosystem and practical AI, each with a comment on why it matters to people who plan. How we choose the news

Scroll to Top