IPA: 80% of projects finished later than their earliest (FEL 1) schedule, and 15% took about twice as long

Source: Why Do So Many Class 5 Estimates Miss the Mark?
Independent Project Analysis · Independent Project Analysis (IPA) · 5 October 2026

Why it matters

The headline is about cost estimates, but the schedule finding is just as stark: in IPA's data, 80% of projects finished later than their FEL 1 schedule and 15% took about twice as long. The first date a project gets is the one everyone remembers, and it is set when the least is known. Treat an early schedule as a range with its assumptions written next to it, and re-baseline openly when definition improves rather than carrying the first date as a commitment.

— Rosario Rizzo