Practice pick · a piece of craft worth reading
Source: GAO Schedule Assessment Guide: Best Practices for Project Schedules
U.S. Government Accountability Office (GAO-16-89G), Best Practices 1 and 4 · 22 December 2015
Found via a discussion on r/MSProject
What to take away
Activity count is the wrong yardstick. GAO's guide ties detail to the update cycle: near-term activities should be no longer than the reporting period (a working week or less for weekly updates, about 22 working days for monthly ones), long activities are broken up where the work has logical breaks, and only as far as needed to show the hand-offs, and detail should follow the information available on that part of the work. A 3,000-activity baseline that cannot be statused honestly every month fails the same test as a 150-activity one that hides who is late — GAO warns that too much detail "may convolute the calculation of critical paths".
— Rosario Rizzo
Related
- Rolling wave planning: detail the next wave, leave the far future coarse: the next 30–90 days at task level, the rest as planning packages, and the window rolled forward at every control cycle
- How often should you update the project plan? The duration rule and the status date: how to choose the reporting rhythm that the near-term durations should then respect
Rosario Rizzo’s NewsRadar: curated news on reliable schedules, the Microsoft Project ecosystem and practical AI, each with a comment on why it matters to people who plan. How we choose the news