Before an .mpp file goes to a client, a subcontractor or a support desk, someone has to take out the rates, the names and the notes. There are three ways to do it today: two tools sold as an MPP cleaner, ProjectCleaner and GanttShield, or Microsoft Project and a checklist. This page compares them on what they actually remove, what they need on the machine, and what they leave behind.

Disclosure first: we make GanttShield, so read the comparison with that in mind. Everything said here about ProjectCleaner comes from its vendor’s own pages, read on 21 October 2026 and linked below; we have not tested it.
In short
- ProjectCleaner is an add-in for Microsoft Project. Its vendor lists three things it removes: resource rates, resource names and work progress.
- GanttShield for Microsoft Project is a standalone Windows application. It renames tasks and resources, clears notes, costs and baselines, and writes the copy as .mpp (with Project installed) or .xml (without it).
- By hand, Microsoft Project and a checklist cover everything, at the cost of time and attention every time you send a plan.
- Whichever you use, check the bytes of the copy before you send it.
What has to leave the file
A plan carries more than its Gantt chart shows. The usual suspects, in order of how often they hurt:
- Names: people in the resource sheet, clients in task titles.
- Money: hourly rates, costs, fixed costs, budget figures.
- History: up to eleven baselines, which show what you promised and by how much you missed.
- Notes: where the honest remarks live.
- Custom fields: a column renamed «Client» or «Margin» keeps its name even when its values are empty.
- Traces in the file itself: the folders it was opened from and saved to, and old text left behind by an ordinary Save.
The full list, with where each item hides, is in How to remove sensitive data from an .mpp file before sharing it. Here the question is narrower: which tool takes care of which part.
ProjectCleaner: an add-in inside Microsoft Project
ProjectCleaner comes from Synami, the team behind ScheduleCleaner for Primavera P6 files. Its announcement calls it an add-in for Microsoft Project that removes or anonymises three categories of data:
- the cost rates of work resources: standard rate, overtime rate and cost per use;
- the names of work resources, which its product page says become «res1», «res2» and so on;
- the work progress, with % Complete set to zero in the saved file.
It works on a copy: the changes are saved in a new .mpp file and the original is not modified. Because it is an add-in, it runs inside Microsoft Project, so Project has to be installed. The vendor’s pages do not mention task names, notes, baselines or custom fields; if those matter to you, ask during the demo the vendor offers. No price is published for ProjectCleaner: the site offers a free trial on request and a 30-minute online demo.
GanttShield for Microsoft Project: a standalone application
GanttShield is a Windows desktop application, not an add-in. You open the plan in it, choose what to scrub, and it writes a clean copy next to the original, which it opens read-only and never saves. What it does to the copy, as stated on its product page:
- Tasks become stable IDs such as TASK-000214, so reviewers can still refer to them by number; structure, dates and durations stay readable.
- Resources become neutral codes such as RES-0007, or are removed together with the financial data.
- Money and history: costs, actuals, fixed costs, work, assignments, all eleven baselines and the numeric custom fields Cost1–10 and Number1–20 are zeroed in one pass.
- Notes are emptied; dependencies can be removed too, if you choose.
There are two outputs. The .mpp copy is written by driving Microsoft Project, so Project must be installed on the same machine; in that copy the text, flag, date, duration and outline code custom fields are not touched. The .xml copy needs no Microsoft Project at all, also empties those custom fields and their names, and carries no folder paths; Project opens it like any plan. GanttShield refuses master plans and files connected to a shared resource pool rather than half-process them.
Doing it by hand
Nothing above requires a tool. Microsoft Project has no Document Inspector, but it has every field you need to clear, and a few lines of PowerShell can tell you whether a word is still in the file. The procedure, in order, is in our step-by-step guide. It costs nothing and covers everything, including the custom text fields and the folder paths. What it costs is time, and the attention not to skip a step on the tenth plan of the month.
Side by side
Which one, when
- You share a plan a few times a year: do it by hand with the checklist. A tool will not pay back the time it takes to learn it.
- You only need to hide rates and people, and want to stay inside Project: ProjectCleaner covers exactly the three things its vendor lists. Ask the vendor about the rest before you rely on it.
- Task names, notes and baselines have to go too, every week, or the person preparing the copy has no Microsoft Project licence: that is the case GanttShield was built for, with the .xml copy for machines without Project.
What no tool does for you
None of the three tells you what your sensitive words are. A client name typed into a calendar exception, a view name or a filter can survive any automatic pass. Before you send the copy, search its bytes for the three or four words you would least like the recipient to read; the guide shows a short PowerShell check that does it. And never finish with an ordinary Save over an existing file: in our tests that left renamed text readable inside the file, while Save As to a new name left none.
Frequently asked questions
Does Microsoft Project have a Document Inspector?
No. Microsoft documents the Document Inspector for Word, Excel, PowerPoint and Visio. Project only offers an option to remove personal information from the file properties on save, which does not touch the plan itself.
Can I clean an .mpp file without Microsoft Project?
Not with an add-in, which runs inside Project. GanttShield can read the .mpp and write the clean copy as Project XML without Microsoft Project installed; the recipient opens it in Project as usual.
Does hiding the cost columns protect the data?
No. A view decides what is displayed, not what is stored. Anyone who opens the file can add the columns back.
How do I know the copy is clean?
Search the saved file for the words that matter to you: client names, surnames, your own user folder. A byte search proves what is absent, which no view in Project can.
Sources: Synami, ProjectCleaner announcement (published 18 November 2021, updated 21 July 2026) and Project Cleaner product page; Project Edge Tools, GanttShield product page. All read on 21 October 2026. If the ProjectCleaner vendor has updated its feature list, write to us and we will correct this page.