A Microsoft Project plan lands on your desk. You did not build it, and you have to say whether it can be relied on. This is the Microsoft Project plan review checklist I use at that moment: nineteen checks in order, each with the exact place to look, what is normal to find and what should ring a bell.
It fits on one page. Print it, keep it next to the keyboard, tick the boxes as you open the file.
Download the inspection sheet
One A4 page, ready to print. No sign-up, no email.
The order matters more than the single checks
The nineteen checks are not a list to pick from: they are a chain. Each one makes sense only if the ones before it gave an acceptable result, and the reason is practical. Reading the critical path of a plan full of constraints is wasted time, because what you read is not the critical path of the project: it is the drawing of the constraints somebody put in. In the same way, reading the variances of a plan with no saved baseline means reading zeros and taking them for punctuality.
The first three blocks tell you whether you can trust the plan. The others tell you what it is worth. If you have ten minutes and no more, run checks 4, 8 and 13: constraints, tasks with no successors, the calendar.
A · Structure: is it a plan or a list?
B · Time: are the dates calculated or typed?
C · Resources: who works, and when
D · Control: is the plan running or stale?
E · When the plan leaves your computer
The test that is worth the whole count
In the end, how many alarms you ticked does not matter. What matters is whether the plan reacts. Change a duration in the middle of the network and see whether the finish date moves. If it does not, what you have in front of you is not a model of the project: it is a drawing, and it will serve to communicate but will not survive the first surprise. Then undo the change.
Every check on this sheet has a chapter that explains the mechanism, what Microsoft Project does at that moment, why the symptom appears and what happens if you do not fix it, in the guide The plan that holds: Microsoft Project best practices, symptom by symptom. For a shorter first look, there are also the five checks for a plan you did not build.
Frequently asked questions
How long does it take to run all the checks?
Ten minutes for the first three blocks, the ones that tell you whether you can trust the plan. Half an hour for all nineteen, on a plan of a few hundred tasks. Far less than the time you would lose trusting a wrong plan.
Does it work with every version of Microsoft Project?
Yes, from Project 2010 to Project 2024 and the desktop versions in Microsoft 365. The fields it needs, Constraint Type, Task Mode, Total Slack, the baseline and actual date columns, exist in all of them. Task Mode arrived in 2010: in earlier versions that check is simply not needed.
Can I use the checklist on a plan that is not mine?
That is what it was made for. Every check says where to look without changing anything: you add columns and switch views, which touch no dates, durations or links. The only test that changes the plan is the final one on the duration, and you undo it straight away.
Is there a score: how many alarms are too many?
The thresholds that circulate in schedule quality checklists, no more than ten percent of tasks constrained, no more than five percent without successors, are reasonable as orders of magnitude, but they remain conventions, not measurements on real plans. The most useful criterion is another one, and it is the final test: the plan reacts, or it does not.