Microsoft Project plan review checklist

A Microsoft Project plan lands on your desk. You did not build it, and you have to say whether it can be relied on. This is the Microsoft Project plan review checklist I use at that moment: nineteen checks in order, each with the exact place to look, what is normal to find and what should ring a bell.

It fits on one page. Print it, keep it next to the keyboard, tick the boxes as you open the file.

Download the inspection sheet

One A4 page, ready to print. No sign-up, no email.

➜ Microsoft Project plan inspection sheet (PDF, one page)

The order matters more than the single checks

The nineteen checks are not a list to pick from: they are a chain. Each one makes sense only if the ones before it gave an acceptable result, and the reason is practical. Reading the critical path of a plan full of constraints is wasted time, because what you read is not the critical path of the project: it is the drawing of the constraints somebody put in. In the same way, reading the variances of a plan with no saved baseline means reading zeros and taking them for punctuality.

The first three blocks tell you whether you can trust the plan. The others tell you what it is worth. If you have ten minutes and no more, run checks 4, 8 and 13: constraints, tasks with no successors, the calendar.

A · Structure: is it a plan or a list?

What you checkWhereHealthyAlarm
1 · The project summaryFirst row of the planRow with ID 0, switched on in ProjectA hand-made row 1 that contains everything
2 · Task namesTask Name column, sortedA verb for tasks; a check passed for milestonesNouns, codes, statuses in brackets
3 · The breakdownCollapse everything to level 15-8 rows that describe the projectFlat list; phases with one child

B · Time: are the dates calculated or typed?

What you checkWhereHealthyAlarm
4 · ConstraintsConstraint Type column“As Soon As Possible” almost everywhereMany “Must Start On”: more than 1 in 10
5 · Manual schedulingTask Mode columnAll automatic in the delivered planManual rows: that part is not calculated
6 · DurationsDuration columnValues that differ, 1 to 10 daysQuestion marks; all the same; 60-day blocks
7 · Links on phasesPredecessors column, bold rowsEmpty on summariesPhases linked to each other: a plan tied in blocks
8 · Dangling tasksPredecessors and Successors columnsOnly the first with no predecessor, the last with no successorDozens of rows with no successor: the network does not propagate
9 · The critical pathTotal SlackOne continuous chain from start to finishAlmost everything critical, or nothing, or in pieces; negative slack

C · Resources: who works, and when

What you checkWhereHealthyAlarm
10 · Resources on phasesResource Names column, bold rowsEmpty on summaries and on row 0A name on the phase: the budget is inflated, the sum is not a sum
11 · Names and hoursResource Sheet; Work columnReal people; work filled in“Resource A”, “Team”; zero work
12 · OverallocationResource Usage viewShort, explainable peaksPeople at 200% for weeks, on critical tasks
13 · The calendarChange Working Time → ExceptionsPublic holidays and company closures enteredEmpty list: the project works on Christmas Day

D · Control: is the plan running or stale?

What you checkWhereHealthyAlarm
14 · The baselineBaseline Start and Baseline FinishFilled in, and different from the current datesEmpty: nothing to measure. Same as current: saved again
15 · The status dateProject → Project InformationSet, recent, statedNA: the numbers change every time you open the file
16 · ProgressActual Start and Actual FinishFilled in up to the status dateEmpty while percentages are set: progress declared, not measured
17 · VariancesVariance table, sortedDifferent values, read and reportedZero across the board on a project under way

E · When the plan leaves your computer

What you checkWhereHealthyAlarm
18 · What travels with the fileRates, notes, links, baselinesA cleaned copy goes outThe original attached: costs and names go out
19 · The format for the recipientRead, work on it, or decide?A dedicated view, saved onceA 40-page PDF for someone who only has to decide

The test that is worth the whole count

In the end, how many alarms you ticked does not matter. What matters is whether the plan reacts. Change a duration in the middle of the network and see whether the finish date moves. If it does not, what you have in front of you is not a model of the project: it is a drawing, and it will serve to communicate but will not survive the first surprise. Then undo the change.

Every check on this sheet has a chapter that explains the mechanism, what Microsoft Project does at that moment, why the symptom appears and what happens if you do not fix it, in the guide The plan that holds: Microsoft Project best practices, symptom by symptom. For a shorter first look, there are also the five checks for a plan you did not build.

Frequently asked questions

How long does it take to run all the checks?

Ten minutes for the first three blocks, the ones that tell you whether you can trust the plan. Half an hour for all nineteen, on a plan of a few hundred tasks. Far less than the time you would lose trusting a wrong plan.

Does it work with every version of Microsoft Project?

Yes, from Project 2010 to Project 2024 and the desktop versions in Microsoft 365. The fields it needs, Constraint Type, Task Mode, Total Slack, the baseline and actual date columns, exist in all of them. Task Mode arrived in 2010: in earlier versions that check is simply not needed.

Can I use the checklist on a plan that is not mine?

That is what it was made for. Every check says where to look without changing anything: you add columns and switch views, which touch no dates, durations or links. The only test that changes the plan is the final one on the duration, and you undo it straight away.

Is there a score: how many alarms are too many?

The thresholds that circulate in schedule quality checklists, no more than ten percent of tasks constrained, no more than five percent without successors, are reasonable as orders of magnitude, but they remain conventions, not measurements on real plans. The most useful criterion is another one, and it is the final test: the plan reacts, or it does not.