This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.
The file is called Plan_v12_FINAL_rev3.mpp and was modified yesterday at 6:40 pm. It looks alive. You open it: the Gantt bars are tidy, every date is there, the critical path is coloured. All good.
Then you ask one question: “up to what date is it updated?”. And you find out that the last real progress is from March. Since then somebody opened the file, moved a few bars, saved. The modified date says the file was touched: it does not say the project was measured. What you have in front of you is a plan that is not up to date, and in Microsoft Project you cannot see it by eye.
It is the most common situation in plans that come from outside, and the most dangerous, because a stale plan does not look stale: it looks like a plan. Here are the seven signs that give it away, fastest first.
In short
- The file’s modified date tells you nothing: it says somebody saved it, not that the project was measured.
- Seven signs reveal a plan that is not up to date: no status date, round percentages, empty actual dates, finished work in the future, a straight progress line, zero variances, bars moved by hand.
- The test that does not lie is the Actual Start and Actual Finish columns: the last actual date in the file is the last real update.
- The right question is not “is the plan up to date?” but “up to what date, and by what procedure?”.
Sign 1: there is no status date
First move, five seconds: Project > Project Information, and look at the Status date field. There are three possible answers, and they tell three different stories.
- It is empty (it shows NA). Nobody ever declared “this plan is updated to such a day”. Without a status date Project uses today’s date for its calculations, which means every time you open the file the numbers change: variances, progress indices, the line on the Gantt. In our test the planned value of the same phase was €4,750 with the status date empty and €8,750 with the status date set to the end of the month. A plan like that is not measurable; it is measured at the moment you look at it.
- It is months old. At least it is honest: it says how far the plan goes. That is already information, and it is the information you needed.
- It is recent. A good sign, but not enough: the status date is typed by hand, and typing it updates nothing. Carry on with the other checks.
Sign 2: the percentages are all round
Show the % Complete column and scroll. If the values are only 0, 50 and 100, nobody measured anything: somebody clicked the quick progress buttons in a meeting while the others were talking. 50% is the universal percentage for “we’re working on it”.
The opposite case says just as much: every percentage at zero on a project that started months ago. There, not even the pretence is left.
One warning that holds in every case: % Complete measures elapsed duration, not work done. A ten-day task on day six is at 60% even if the bulk of it has not started. The column that tells the effort is % Work Complete; the most honest of all is Remaining Work, because it looks forward.
Sign 3: the actual dates are empty
This is the check that does not lie. Insert the Actual Start and Actual Finish columns: they are the fields where Project records when something really started and finished, and they fill in only if somebody tells it.
If the plan claims tasks at 40% and the Actual Start column is empty, those percentages were typed over a plan that never started. If the actual dates are there, the plan was really updated, and you can see how far they go: the last actual date in the file is the real date of the last update, far more reliable than the file’s modified date.
Sign 4: finished work sits in the future
Sort by finish and look at the tasks at 100%: is there one that finishes next week? A completed task with its finish in the future is a logical impossibility, and Project accepts it without a warning: in our test a task set to 100% kept an actual finish two weeks ahead. Plans often hold dozens of them. It means the percentages were typed without touching the dates, or the dates were left to run forward while completion was being declared.
The twin of this sign is the backward cascade: tasks not started, zero percent, whose start date is in the past. Nobody started them and nobody moved the plan: they stayed there, and every day the plan grows more false. In a correctly updated plan, unfinished work is rescheduled after the status date, and nothing is left to do to the left of the line.
Sign 5: the Tracking Gantt tells you nothing
This is the visual check, and it is worth the four above put together. Switch to the Tracking Gantt view: each task shows two bars, the baseline underneath and the current plan on top. Then display the progress line at the status date, from Format > Gridlines > Progress Lines.
- In an updated plan the line is jagged: it bends left where work is late, right where it is ahead. Ugly to look at and full of information.
- In a plan that is not up to date the line is straight as a string, or it cuts through dozens of bars with no progress. Nobody told Project where things stand.
- If the lower bar is not there at all, it is not about updating: there is no baseline, and then there is nothing to measure against. A different and worse problem, covered two signs below.

Sign 6: every variance is zero
Apply the Variance table and look at the finish variance column. If it is zero on three hundred tasks, and the project has been running for months, there are only three explanations, and none of them is “we are perfectly on schedule”.
- The baseline was never saved. Variances are calculated against it: without one, they show zero by definition. The most frequent case, and you can check it in five seconds by seeing whether Baseline Start and Baseline Finish are empty.
- The plan was never updated. The current dates are still the starting ones, so they match the baseline. Zero variance because zero movement.
- The baseline was saved again recently. The most insidious one: saving the baseline again resets every variance, and a plan three months late is magically back on track. It is almost never bad faith: it is what someone does after replanning, saving again to “start clean”, without knowing it erases the history.
To tell the third case from the other two, the dates are enough: if the baseline columns are full but match the current dates across the whole plan, and tasks show as started, the baseline was rewritten recently. What to do when that has happened, and which baseline to compare against then, is covered in baselines after replanning: Project can keep up to eleven baselines, and hardly anyone knows it.
Sign 7: the plan was “updated” by moving the bars
The seventh is the hardest to see and the worst of all. The plan shows as late, the dates differ from the baseline, so at first sight it looks updated. But the actual dates are empty and the percentages are zero: nobody recorded anything. Somebody simply dragged the bars forward, or retyped the dates by hand, until the plan looked like reality again.
The damage is double. First: every date typed or dragged becomes a constraint. In our test, dragging a bar changed the task from “As Soon As Possible” to “Start No Earlier Than”, with no warning and no indicator. From that moment the plan no longer reacts to change: it stops being a model and becomes a drawing. Second: there is no longer any trace of what really happened, because the fact that “this task started on 12 March” was never recorded anywhere. The plan is updated in appearance and empty in substance.
If the plan is yours
Updating a plan is a procedure of five moves, always the same, always in the same order: save the baseline once, set the status date, enter the actuals, reschedule unfinished work after the status date, read the variances. The full cycle, step by step, is here, and the part that usually goes missing, getting the numbers from the people doing the work, is in how to collect actuals from your team.
What counts more than the procedure is the rhythm. A plan updated every two weeks with approximate data is far more useful than a plan updated once a year with perfect data: the value of updating is in the series, not in a single measurement, because the series shows the direction. How to choose the right period, which depends on the length of the project and of its tasks, is in how often to update a project plan.
If the plan was sent to you: spotting a Microsoft Project plan that is not up to date
Three checks in two minutes, and you know what you are dealing with.
- The status date in Project Information. If it is empty, the plan is not being run: it is still a planning document.
- The Actual Start and Actual Finish columns. The last actual date in the file is the real date of the last update. Compare it with the declared status date: if they are weeks apart, the plan was “dated” without being measured.
- The Tracking Gantt with the progress line. It tells you at a glance whether somebody really recorded progress, and where.
And the right question is not “is the plan up to date?”, because the answer will always be yes. It is: “up to what date, and by what procedure?”. Whoever really updates has an immediate, precise answer, something like “every Friday, with the figures the site managers send me”. Whoever does not answers by talking about the file.
One last warning, because it is where many people lose time: a plan that is not up to date is not a plan to throw away. It is a plan whose limit you know. You can use it for everything about how it is built, structure, links, durations, resources, and for nothing about status. Mixing the two up is why some meetings end with decisions taken on March figures.
Frequently asked questions
Isn’t the file’s modified date enough to tell whether it is up to date?
No, and believing so is the starting mistake. The modified date says somebody saved the file: they may have changed a colour, added a column or just opened and closed it. The only reliable trace of an update is inside the plan, in the actual dates and the status date.
If the status date is empty, what does Microsoft Project use for its calculations?
Today’s date, the date of the computer the file is open on. The consequence is that variances and indices change from one day to the next without anyone touching the plan, and two people opening the same file on different days see different numbers. That is why the status date should always be set explicitly before looking at any indicator.
Can I set the percentages by eye?
You can, and on many projects it is the only data available. The point is to know it: a percentage estimated by eye is not a measurement, it is an opinion turned into a number. If the project matters, measure at least the remaining work, how many hours are left, which people doing the work can answer far better than “what percentage are you at”.
I inherited a plan that has not moved in six months: do I update it or start again?
It depends on one thing: whether there is a saved baseline and whether it is still the approved one. If there is, the plan can be recovered: enter the actuals you can reconstruct, set the status date to today, reschedule the rest, and you keep the comparison with the original commitment, which is what has value. If there is no baseline, that plan is only a well-made task list: you can start from it for the structure, but measurement starts today.
How can I tell quickly whether the baseline was saved again recently?
The signal is two things that do not usually go together: tasks started or completed, and variances at zero across the board. If the project is under way and nobody is a single day late, the point of comparison was rewritten. It is worth asking when and why: an approved replan is legitimate, but it must be stated, or the variances you are reading measure the last decision instead of the original commitment.
The same checks as a sheet to keep next to the keyboard: the Microsoft Project plan review checklist, with a one-page PDF to print.
Further reading on this blog