This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.
Here is the moment. In May the project went sideways, the client approved a new date, you replanned and you re-saved the baseline. Today is the September progress meeting. You open the plan, you look at the Finish Variance column, and it says seven days.
Seven days against what? Against the May replan. But the sponsor who signed in January is not thinking about May: he is thinking about September, the date you promised him. And that number is no longer in the plan.
This is the trap of every project that gets replanned, and it is really a question about how Microsoft Project baselines work: the moment you re-save one, the plan forgets what it promised. Nothing breaks, no warning appears. The columns simply start measuring something else, and nobody notices until somebody asks the wrong question of the right column.
In short
- When you re-save the baseline, the variance columns stop measuring against the signed plan and start measuring against the latest replan. Nothing warns you.
- There are eleven Microsoft Project baselines: Baseline plus Baseline1…Baseline10, picked from a drop-down in Project → Set Baseline. The ready-made variance columns read the unnumbered one only.
- On day one you save the baseline twice, into Baseline and into Baseline1. The second one is the signed plan, and you never touch it again.
- At every approved replan you archive the old plan into a numbered baseline before you change any dates: Set Baseline photographs the plan in front of you, not yesterday’s.
- There is no ready-made column for slippage against the signed plan: you build one with a custom Number field and the formula
ProjDateDiff([Baseline1 Finish],[Finish]). - Applies to every desktop version, from Project 2010 to 2024 and Microsoft 365.
It is not one question. It is three
“Let us compare against the baseline” sounds precise, and it is not. Behind it sit three different questions, with three different answers, asked by three different people.

The project manager asks the first one, and it is the only one Project already answers. The sponsor asks the second, and it takes a little work. Almost nobody asks the third, and it is the one that says the most.
Microsoft Project baselines: eleven of them, and only one is read for you
Microsoft Project does not keep one baseline: it keeps eleven. There is the unnumbered one, simply called Baseline, and then ten numbered baselines: Baseline1, Baseline2, up to Baseline10. They are not a hidden setting — you choose one from a drop-down when you save, in Project → Set Baseline.
All eleven are identical containers: each one holds the start, finish, duration, work and cost of every task, photographed at the moment you saved it. Identical, with one exception that changes everything.

The variance columns — Start Variance, Finish Variance, Duration Variance, Cost Variance, Work Variance — exist in a single copy, and they read the unnumbered baseline only. Microsoft documents Finish Variance as exactly that: Finish minus Baseline Finish. The other ten have their own fields (Baseline1 Finish, and so on), which you can put in any table, but no column that works out the variance for you.
The consequence is simple and heavy: which plan ends up in the unnumbered baseline decides what Project tells you when you open the file. Everything else is a number you have to go and fetch.
The rule: on day one you save it twice
What follows costs thirty seconds at the start of a project and cannot be recovered afterwards. It assumes you already save a baseline at all; if you do not, start from how to update a Microsoft Project plan and come back.
- On day one, save the baseline twice: once into Baseline, once into Baseline1. Same data, two places. Both from Project → Set Baseline, picking the destination from the drop-down each time.
- Baseline1 is the signed plan, and you never touch it again. It is the only copy of the promise you made, and in six months nobody will remember it unaided.
- At every approved replan, before you touch the plan, archive the one you are about to abandon into the first free numbered baseline: Baseline2, then Baseline3. Only then do you change the dates and re-save Baseline with the new plan.
The order in step 3 is not pedantry: it is the step almost everybody gets wrong. Set Baseline always saves the plan in front of you right now, not yesterday’s. If you edit first and archive afterwards, Baseline2 ends up holding the new plan — a copy of what you are about to save into Baseline anyway — and the old plan is gone for good.
One honest note: the plan you archive at replanning time is not identical to the one from six months earlier, because it has absorbed actual progress in the meantime. That is not a problem. It is exactly what you want: a photograph of the plan as it stood when you decided to change it.
The columns to put in the table
With the baselines in order, the rest is a question of which columns you add. Four are enough.

Look at the last row, the go-live, and at the two numbers that come out of it. Seven days is the slippage against the July replan: Project works it out for you, and it answers the first question.
Seventy-nine days is the slippage against the signed plan, and it answers the second. Here Project has no ready-made column. But you do not have to subtract by hand — you build the column: a custom field of type Number, with the formula
ProjDateDiff([Baseline1 Finish],[Finish])
From then on it behaves like any other column: you sort it, you filter it, you print it. The function returns working minutes, so divide by the minutes in your working day if you want it in days.
Two truths about the same project on the same day, eleven times apart. Bringing the first one to a meeting when the sponsor is asking for the second is not dishonesty. It is reading the wrong column.
A shortcut I would not trust without testing it
There is advice circulating on forums that changing the baseline used for Earned Value calculations (Options → Advanced → Earned Value) also moves what the variance columns measure against, so that they start reporting against Baseline1. Microsoft’s own documentation for Finish Variance says only “Finish minus Baseline Finish” and neither confirms nor denies it; in the thread where the idea is offered, the person who asked signs off with “I will try that” and never reports back.
If it works it is one click instead of a formula. But it would silently change what every variance column in the file means, for anyone who opens it. Try it on a copy before you adopt it, and if you do adopt it, write it down in the plan — because from that moment “Finish Variance” no longer means what it means to everybody else.
The third question: the drift
That leaves Baseline2 and Baseline3, the ones holding the intermediate replans. They answer a question that does not fit inside the plan, and that usually arrives from the client at an uncomfortable moment: how many times have you moved the date on me?

Taken one at a time, every replan was defensible: three weeks for a late supplier, a month for a regulatory requirement that changed, four weeks for a failed test cycle. Not one of them, alone, set off an alarm. Lined up they make seventy-nine days, and you only see the line if you kept the baselines.
Project does not draw this chart. You build it by hand, and it takes four numbers: the project finish read from Baseline1 Finish, Baseline2 Finish, Baseline3 Finish and Baseline Finish. Four cells, one row in a spreadsheet, and you have the history of promises that nothing else in the plan keeps.
What this does not give you
- It does not tell you why the plan changed. Baselines keep dates, not reasons. The reason for each replan belongs somewhere else — project notes, meeting minutes — and without it, a year from now, the staircase says you were wrong without saying what happened to you.
- Ten numbered baselines run out. They feel like plenty until you run a multi-year programme that replans quarterly. When they are gone you have to choose what to sacrifice, and it is better to decide that in advance.
- New tasks do not join a saved baseline by themselves. Tasks added after the save have no baseline values: add them with Set Baseline limited to selected tasks, or every comparison will ignore them.
- Deleted tasks take their baseline values with them, and the planned total shifts under your feet with nothing to flag it.
- It is not a measure of progress. It tells you how far the dates moved, not how much work got done. For that you need other instruments, starting with Earned Schedule.
If something goes wrong
- Every variance column reads zero and you know the project is late. You almost certainly re-saved the baseline a moment ago: the plan matches the baseline because they have been the same thing for five minutes. The delay is still there — it now lives in the numbered baselines only.
- Baseline2 holds the wrong plan. You archived after editing. Set Baseline photographs the present. If the earlier file still exists somewhere, that is the only way back.
- Baseline1 Finish is empty on some tasks. Those are the tasks born after the save. Select them and run Set Baseline on selected tasks only, otherwise they stay invisible to every comparison.
- The numbers do not match last month’s and nobody replanned. Check whether somebody deleted tasks: the baseline total drops quietly.
- You have one baseline and you need the original. It cannot be reconstructed from the plan. It can only come from the file as it was — which is why a copy of the approved plan, archived on the day it was signed, is worth as much as the baseline itself.
Frequently asked questions
How many baselines does Microsoft Project really keep?
Eleven: Baseline plus Baseline1 through Baseline10. Each one holds the start, finish, duration, work and cost of every task. The ready-made variance columns, though, read the unnumbered one only.
Should I re-save the baseline after a replan?
If the new date has been approved, yes: measuring against a plan nobody is following any more serves no purpose. But archive the old one into a numbered baseline first, and keep one baseline dedicated to the signed plan that you never touch.
Can I compare two different project files directly?
Yes. Project has a function that compares two versions of a project and produces a report of the differences. It is useful when the older plan is a separate file. When the versions all live inside the same plan, the numbered baselines are more convenient, because you read them as columns alongside everything else.
The project has already started and I only have one baseline: what now?
Save the current plan into a numbered baseline straight away, so the history starts existing from tomorrow, and write down the original finish date somewhere if you remember it or have it in a document. The past cannot be reconstructed; the future can.
Does this apply to every version of Microsoft Project?
To every desktop version, yes: from Project 2010 to 2024 and Microsoft 365. The eleven baselines and the variance columns have always been there; the icons changed, the commands did not. Project for the Web handles baselines differently, and none of this applies there.
How many times can you replan before it becomes a problem?
There is no number, and I would distrust anyone who gives you one. There is a signal, though: when the slips become regular — one a quarter, always about the same size — the plan has stopped being a forecast and has become a register of what happens. The staircase exists so you can see that moment while it is happening, instead of afterwards.
Disclosure: this is the blog of a company that makes project-control software, so take the paragraph below for what it is. Nothing in the method above needs our tool, or any tool: the baselines belong to Microsoft Project, and the staircase of dates is four numbers in a spreadsheet.