Friday afternoon, progress review. You update the percentages, look at the plan, and ask the question you always ask: “how far behind are we?”
It’s the wrong question. Or rather: it’s half of the right one.
Because “minus ten percent” tells you nothing about what to do on Monday. A ten percent delay that is widening is an emergency. The same ten percent that is reabsorbing on its own is a problem that fixes itself without spending a euro. And a ten percent that has been sitting there for three weeks is a third story altogether. Same number, three different decisions. The full question is: “how far behind are we — and which way are we heading?”
Driving by the rear-view mirror
The classic way of controlling a plan — the Gantt chart updated at month’s end — has a structural flaw: it photographs what has already happened. By the time the bar turns red, the damage is done. You’re driving by the rear-view mirror.
That’s why I wanted a tool in the suite that does the opposite: watch the direction of the delay, not just its size. It’s called GanttDerivata, and the name is the whole program — in mathematics, the derivative is the speed at which something changes. Here: the speed at which your delay grows or shrinks.
The three clicks
The title isn’t a slogan, it’s the procedure.
Click one: “Open plan…”. GanttDerivata is a standalone application: it reads the plan file — .mpp or .xml — directly, without Microsoft Project installed. And if you do have Project, the file can stay open there while you analyze it.
Click two: pick the file. The analysis runs by itself. For every task, the program compares actual progress with what you should have at the status date, and shows the variance in percentage points: green if you’re ahead, red if you’re behind.
Click three: the filter. A real plan has hundreds of rows; a filter leaves you facing only the ones that deserve attention. And this is where the part everyone can do ends — and the part this tool exists for begins.
The direction: same variance, three fates
Next to every row, GanttDerivata writes two things a Gantt chart cannot say: the trend and the suggested action. It computes them by comparing today’s reading with those of the previous weeks. Three tasks with the same variance today can tell three opposite stories — watch them reading after reading:
| The derivative of the delay · three readings side by side | |||||||||
| Scenario 1 · Worsening | |||||||||
→ The gap doubles at every reading → reinforcements, now. | |||||||||
| Scenario 2 · Recovering | |||||||||
→ The gap is closing on its own → no pointless overtime. | |||||||||
| Scenario 3 · Dragging | |||||||||
→ The gap isn’t moving → it only matters if it’s on the critical path. | |||||||||
| Bar length is the delay (variance in % points). Same today-variance in all three stories: opposite fates. |
- Worsening (last week −10, today −20): the gap is widening. At this pace the crew will never catch up: you need reinforcements now, not at the next meeting.
- Recovering (−15 last week, −10 today): you’re still behind, but the crew is moving faster than planned. Instinct says “pay for overtime”; the trend says the delay is zeroing out on its own. Don’t pay twice for a recovery that’s already happening.
- Dragging (−10 and −10): the delay is stable, neither worsening nor closing. Before spending anything, the right question is a different one: is this task on the critical path? If it isn’t, that slippage may cost you nothing.
This is the difference between knowing where you are and knowing what to do. The photograph versus the direction.
The next three weeks, not the next two years
Another choice of the method: instead of looking at the whole life of the project, GanttDerivata projects each task over the three weeks following the status date — W1, W2, W3. That’s your real window for action: what happens in there, you can still change.
The window for action: past readings build the trend; the three weeks after the status date are where you can still act. |
Select a task and, for each window, you read how much should be done, the expected cost, the earned revenue and the margin delta: the delay translated into the language of the profit and loss account — the one you’ll then use with management. For the big picture there are the EVM gauges (SPI and CPI) and a sprint Gantt chart ready to bring to a meeting.
And how do I recover? The what-if
Knowing you’re late is diagnosis. The next question is therapy: how much do I need to accelerate to get back on track?
The Time what-if button answers with a slider. Move the future progress pace — “what if, starting Monday, the crew went ten percent faster?” — and you immediately see the effect on the estimated finish and on the gap to the plan. You try the scenarios on screen before you buy them on site: how many times has an expensive acceleration turned out to be only half needed?
The Friday routine
The method — it’s called SPRINT, by Giovanni Canciullo, PE — doesn’t ask you to change the way you work:
- update the completion percentages in Project as you always have, with the status date set to the day of the reading;
- three clicks in GanttDerivata: open, look at the red rows, read the trend and the suggested action;
- export: the file comes out with a dated name (project + status date), and saving the exports in the same folder builds your project history, reading after reading.
What it doesn’t do
Three things, for honesty’s sake. It doesn’t decide for you: it suggests, and the project manager’s judgement remains irreplaceable. It needs a saved baseline: without one, the comparison with “where you should be” doesn’t exist — if you needed a reason to save it, here it is. And on the first analysis there’s no trend yet: direction is born from comparing readings, so it shows up from the second week onwards. The Friday discipline is half the method.
GanttDerivata is part of the ProjectEdgeTools suite: find it here, with a free trial.
This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.