“We’re still on schedule” measures one thing only: the distance from the delivery date. It does not say how much time is left to decide.
Marco Catania, in a LinkedIn article on the float that protects a contract (Il margine che nessuno vede, in Italian), puts it this way: every recovery option has a deadline of its own. An alternative supplier, an extra shift, a change of sequence only work if they start in time, and the time they need to start does not get shorter because the site is in a hurry.
That last useful date exists whether anyone writes it down or not. If it stays in the project manager’s head, you find it when it has already passed. If it is in the plan, you watch it come closer at every update.
In short
- Every option has a lead time: counted back from the date it is needed, it gives the last useful date to decide.
- In Microsoft Project it becomes the Deadline of a milestone: it moves nothing, but it gives the milestone a total slack that is the window to decide.
- At every update, read the window like slack: if it shrinks, the decision has to come earlier, even while the delivery is still on date.
1. On date, but for how long?
An example. Installation of the electrical panels starts in 24 working days. Supplier A provides the panels and still has to confirm the delivery date: the confirmation is expected in 8 days. If A does not confirm, there is supplier B, which needs 10 working days from the order.
The arithmetic is simple. To have B’s panels on day 24, the order has to go out by day 14. After day 14, B is no longer an option. Today the plan is on date, but the window to decide runs from day 8, when you will know about A, to day 14: six days. No column in the plan shows that number until you put it there.
2. In Project: a milestone with a Deadline
Three steps are enough.
Add a milestone, “Decision: supplier B”, with zero duration, and link it to A’s confirmation with a finish-to-start link: the decision cannot come before you know.
Link it to the installation as well, finish-to-start. That way the milestone does not dangle without a successor, which is one of the logic holes that distort the critical path.
Then open Task Information, the Advanced tab, and type the last useful date in the Deadline field: day 14.
A Deadline is not a constraint and does not move the milestone. Project draws it as a green arrow on the Gantt chart and shows an indicator once it is missed. But it does enter the slack calculation: the latest date the milestone can finish becomes day 14, because it is tighter than the one that comes from the installation. The milestone’s total slack is then exactly the window to decide.

3. At every update, watch the window
Now the plan moves on, one week at a time. A postpones its confirmation by three days at every update. The installation stays on date, and so does the delivery: in the meeting, everyone keeps saying “we’re on schedule”.
The milestone tells another story: nine days of slack, then six, then three, then zero. At the fourth update it is the last useful day. From the next day the slack is negative, the indicator changes, and B can no longer arrive in time, even though no delivery date has moved.

It is the same principle as the article on near-critical tasks: the value tells you where you are, the trend where you are heading. Here, though, what runs out is not a day of slack: it is a choice. And if you use a critical threshold tied to the update cycle, the milestone lands on the list to review in the meeting, which is exactly where it belongs.
4. One line for the meeting
Each option needs four pieces of information: what it is, what it costs, the last useful date, who decides. In the plan, the date is the milestone’s Deadline; the cost and the name of whoever decides can go in two custom fields, or in the notes. A filter on decision milestones with little slack gives you the meeting agenda.
For this to work, the plan has to be updated with a status date: the window is calculated from where the plan really is, not from where you hoped it would be.
The delivery date tells you whether you are late. The decision milestone tells you whether you still have time to choose.
In your plan, how many options have a date written down?
Frequently asked questions
What is the difference between a deadline and a constraint in Microsoft Project?
A deadline does not move the task: it shows an indicator once it is missed and it counts in the total slack calculation. A hard constraint, such as “Must Finish On”, fixes the date instead and stops delays from travelling through the plan.
Where do you set a task deadline?
In Task Information, on the Advanced tab, in the Deadline field. A green arrow appears on the Gantt chart at that date.
Why does the milestone’s slack go negative?
Because the milestone’s scheduled date has passed its Deadline. Project calculates slack against the tighter of the date that comes from the links and the Deadline: once the scheduled date goes beyond it, slack drops below zero.
If you want the same question, “which way is it heading?”, asked of every delay in the plan, GanttDerivata compares status dates and tells you, for each delay, whether it is widening or closing.