Deleted tasks and the baseline in Microsoft Project: inactivate, don’t delete

A task is no longer needed? Inactivate it, don't delete it: the same plan after the change costs $3,200 against a $4,800 baseline, and only the inactive row explains the $1,600 variance

You saved the baseline, the project is under way, and at some point a task is no longer needed: the client took it out of the contract, or someone else is doing it. The natural reaction is to select the row and press Delete. The plan gets shorter, costs go down, and everything looks fine.

It isn’t. The project summary still says the baseline was worth what it was before, and the variance that appears no longer has a row that explains it. With one task you can work it out in your head; with thirty, assigned to resources with different rates, you can’t. Microsoft Project Professional has a command made for this: Inactivate. Here is why it is better to inactivate a task in Microsoft Project than to delete it, and the one step that spoils it.

In short

  • If you delete a task after saving the baseline, the project summary keeps the old baseline values: the variance is there, but nothing shows where it comes from.
  • With Task → Schedule → Inactivate the task stays in the plan, struck through: it drops out of cost, work and scheduling, but its row explains the variance.
  • Don’t remove the links before you inactivate it: the inactive task holds the chain, and the successor stays where it was. The command exists only in Project Professional.

What happens to the baseline when you delete a task

The example is deliberately small: three tasks in a chain, Task 1 lasting one day, Task 2 two days, Task 3 three days, all assigned to a resource at $100 an hour. The baseline is saved as usual, from Project → Set Baseline → Set Baseline, for the entire project.

In the Cost table, right after that, total cost and baseline cost match: $4,800, that is 800 + 1,600 + 2,400. Then Task 2 is deleted. Total cost drops to $3,200, the project’s baseline cost stays at $4,800, and the variance shows $1,600. Yet every remaining row has a cost equal to its baseline: none of them says where that $1,600 went.

This is not a Project bug: the summary’s baseline values were saved with the baseline, and deleting a subtask doesn’t recalculate them. Our test showed one more effect, the one that does the most damage in a real plan: Task 3 lost its predecessor and moved back to the first day of the project. After a deletion, always check the links of the neighbouring tasks.

Inactivate instead of deleting

  1. In the Gantt Chart view, select the task’s row.
  2. On the Task tab, in the Schedule group, click Inactivate.
  3. The task stays where it was, greyed out and struck through. To make it active again, click the same command.

Now the Cost table tells the same story as before, but in full: the project costs $3,200 against a $4,800 baseline, and the struck-through row of Task 2, with its $1,600 baseline cost, says where the difference comes from. It no longer counts towards the total: cost, work and dates ignore it, as Microsoft’s documentation also states.

Before you inactivate, don’t remove the links

A common piece of advice is to remove the task’s links before inactivating it. We measured both ways in Microsoft Project 16.0, and that step does more harm than good.

  • Links kept: the inactive task no longer counts as duration, but it holds the chain. Task 3 starts right after Task 1, as it should, and the project finishes on November 5.
  • Link removed, then inactivated: Task 2 has no predecessors any more, Task 3 depends only on it and runs in parallel with Task 1. The real sequence of the work is lost, and the plan finishes a day earlier than it really can.
Three Gantt charts with the same baseline: Task 2 deleted, Task 3 loses its predecessor and starts on day one; Task 2 inactivated with its links kept, Task 3 stays after Task 1; link removed and then Task 2 inactivated, Task 3 starts together with Task 1
Same costs in all three cases, different plans: only case B keeps both the explanation of the variance and the sequence of the work.

A baseline is there to compare against: remove a row, and you also remove the answer to “why does it cost less?”.

When inactivating is not the right move

  • For finished tasks. Inactivating is not a way to archive them: Microsoft warns it can have unexpected effects on the rest of the schedule. A finished task is marked 100% complete.
  • When the scope changes by contract. If the client removed a piece of work with a change order, the baseline has to be updated, because the reference really has changed. Inactivate the removed tasks, then save the new baseline in one of Baseline 1–10: the first one stays for the comparison with the original contract, and the struck-through rows record what was taken out.
  • In Project Standard. The command isn’t there. Before deleting, write down the task with its baseline cost and work, and put the reason in the summary task’s notes: it is the only way to find the explanation of the variance later.

Frequently asked questions

Which versions of Microsoft Project have the Inactivate command?

Only Project Professional, from version 2010 onwards; Project Standard doesn’t have it. The tests in this article were run on Project 16.0, the same base as Project 2016, 2019, 2021, 2024 and Microsoft 365; the behaviour of the links in particular was measured there, and on Project 2010 it is worth checking with a test plan.

Does an inactive task count in the project totals?

No. Its cost and work stay visible in its own row, but the project summary doesn’t add them up, and the assigned resource is no longer booked for it. The summary’s baseline cost, on the other hand, stays the one saved with the baseline.

Does an inactive task still push its successors?

Not with its duration. If the links stay, the successor behaves as if the inactive task took no time at all: it starts when the inactive task would have started. That is why it pays to keep them.

Can I make a task active again?

Yes: select it and click Task → Schedule → Inactivate again. It counts once more in cost, work and scheduling, with the baseline values it had.


The idea comes from an article by Nenad Trajkovski. The measurement of the links and the conclusions drawn from it are ours. For the bigger picture, read what a baseline is and when to set it and how to update a Microsoft Project plan.