Friday afternoon, progress meeting. You open the plan, ask around “where are we”, type a few percentages, stretch the late task by two days, save. The Gantt chart is up to date. Or so it seems.
What you actually did is something else: you replanned. The plan you are looking at now says where the project will end, but it no longer says where it was supposed to end, how far you have drifted, or whether the drift is growing or shrinking. You have lost the one piece of information that makes a plan a control tool: the comparison between what you promised and what is happening.
Updating a plan in Microsoft Project is a cycle of five steps, always in the same order: set the baseline, set the status date, enter the actuals, reschedule the remaining work, read the variances and communicate them. This guide walks through the cycle step by step.
In short
- Updating is not replanning: without a saved baseline, every edit to the plan erases the term of comparison. The baseline is set once, before work starts, and re-saved only for an approved change.
- Every update refers to an explicit status date, not to “today”: it is the line against which Project decides what is past and what is future.
- Project keeps three families of dates: baseline (fixed), scheduled (recalculated by the engine) and actual (written once, when things happen). Updating means writing the actuals and letting the engine recalculate the scheduled dates.
- After the actuals, uncompleted work must be rescheduled after the status date; then you read the variances against the baseline and their trend, and report them at the agreed rhythm.

Updating is not replanning: why you need a baseline
The baseline is a photograph of the plan taken a moment before you start executing it: for every task, start, finish, duration, work and cost as they were when the commitment was made. From that moment the plan lives and changes; the baseline does not. It is the least known feature of Microsoft Project, and its absence is the reason so many “updates” are really replans: what a baseline is, when to set it and what changes after has its own guide.
Try a mental test. You have a ten-day task; halfway through you realise it needs twelve and you extend the duration. Without a baseline the plan now says “twelve days”, full stop: no trace of the fact that it used to be ten. With a baseline the plan says “twelve days, ten planned, variance plus two”, and the project finish shows how far it has moved from the promise. Same edit, two very different pieces of information.
Updating a plan without a saved baseline is not updating: it is replanning, and losing every time the memory of where you meant to go.
The baseline also has a side that surprises people: if you delete a task after saving it, its cost and work stay in the baseline of the summary task, and the resulting variance has to be explained. That is not a bug: it is the baseline doing its job, remembering what you promised.
Step 1: set the baseline, once
The command is Project → Set Baseline → Set Baseline, for the entire project. You run it when the plan is approved and before the first task starts. From then on the Tracking Gantt view shows a grey bar under every task bar: that is the baseline, and the distance between the two is the variance you read at a glance. If the plan is not yours, review it first: a baseline saved on a plan full of hard constraints freezes the wrong promise.
Three rules to avoid regrets:
- do not re-save it at every update: if you overwrite the baseline every week, every week the project is “on track” and the delay disappears from the numbers, not from reality;
- re-save it only for an approved change, for example a scope change signed by the client: in that case the promise has genuinely changed;
- keep the previous versions: Project holds up to eleven baselines (Baseline, then Baseline1 to Baseline10). Before re-saving, copy the current one into a numbered baseline, so the history of promises stays readable.
If the project has already started and there is no baseline, save it now: you will not have the comparison with the original plan, but from today on the cycle works.
Step 2: set the status date
Every update answers one precise question: “where was the project as of date X?”. That X is the status date, and it is set in Project → Project Information → Status date. It is not today’s date: it is the date the data you collected refers to. If the teams sent you Friday’s progress and you update the plan on Monday, the status date is Friday.
It is worth making it visible: Format → Gridlines → Status Date draws a vertical line across the Gantt chart, and the effect of the status date becomes obvious. Everything completed should sit to the left of the line; everything still to do, to the right. A task at 40% whose completed part sticks out past the line, or whose remaining part starts before it, is a task telling an impossible story.
Project can fix these inconsistencies by itself, if you ask. In File → Options → Schedule, under the calculation options for the project, four check boxes move the end of completed parts and the start of remaining parts to the status date. Turning them on makes every update consistent with the line; leaving them off means doing it by hand, task by task.
Step 3: the actuals, in the right order
This is where most mistakes happen, because Project has many dates and they do not all behave the same way. It helps to think of them as three families:
- the baseline dates (Baseline Start, Baseline Finish): they are the baseline, you do not touch them;
- the scheduled dates (Start, Finish): the engine calculates them from durations, links, calendars and actuals. Typing them by hand creates a constraint and takes away the plan’s ability to react;
- the actual dates (Actual Start, Actual Finish): you write them, once, when the thing happens. They are the only door through which reality enters the plan.

Actual dates have precise rules. Actual Start is set by hand when the task really starts, and from that moment the task no longer moves: it is anchored to reality. If instead you type a percent complete on a task with no actual start, Project sets one for you, equal to the scheduled start, which may not be the true date. Actual Finish, when you write it, takes the task to 100% and closes the matter.
Hence the right order for every task touched by the update:
- if it has started, write when it started (Actual Start);
- then how far it has progressed: percent complete, or better actual duration and remaining duration, which force an honest estimate of what is left instead of a gut-feeling number;
- if it has finished, write when it finished (Actual Finish), not 100%: 100% on its own closes the task on the scheduled date, not the real one.
The place to do it is the Update Tasks dialog (Task tab, Schedule group, under Mark on Track), which shows percent complete, actual and remaining duration, actual start and actual finish together. The 0%, 25%, 50%, 75%, 100% buttons on the ribbon are convenient and dangerous: they do step 2 without step 1 and step 3.
One distinction worth knowing: % Complete measures elapsed duration, % Work Complete measures hours done. On a task with several resources the two can diverge a lot, and for cost control it is the second one that counts.
Step 4: reschedule the remaining work
After the actuals, the plan often has an inconsistency: unfinished tasks whose remaining part still sits before the status date, that is, in the past. Nobody will do that work yesterday. The command Project → Update Project → Reschedule uncompleted work to start after the status date moves everything remaining forward and splits it from the completed part: the Gantt chart shows a split task, with a done stretch and a to-do stretch. It is the honest photograph of where you are.
Two warnings:
- rescheduling is not extending. The remaining duration stays as estimated in the previous step; if the remaining work will take longer, the right move is to correct the remaining duration with an estimate, not to drag the bar;
- the command applies to the whole project, so it also reschedules what you forgot to update. Before running it, a filter on the tasks that should have been in progress at the status date tells you whether any data is missing.
A special case is the stop imposed from outside: a site shut down for months, a suspension decided by the client. The sequence is the same with one extra step: save a numbered baseline before touching anything, set the status date to the day of the stop, record the progress up to that day, then move the remaining work to the restart date. The variance against the original baseline documents the impact of the stop, which is exactly what you will need in a claim or an extension request.
Step 5: read the variances, then communicate
Now the plan says three things at once: what you promised, what happened, what will happen if the rest goes as planned. You read them in three places:
- Project → Project Information → Statistics: current duration, work and cost next to the baseline ones, in a single dialog. It is the first thing to look at;
- the Variance table (View → Tables → Variance): for every task, how far start and finish have moved from the baseline. Sorted by Finish Variance, it puts the problems at the top;
- the Tracking Gantt view, where the distance between the bar and the grey bar is visible without reading a number.
The number alone is not enough, though. A ten-day delay that widens at every update is an emergency; the same delay that is absorbing itself is a problem that gets solved without spending; the same delay unchanged for three weeks is a third story. That is why it pays to look at the direction of the delay, not just its size, to find the late tasks in three clicks, and to concentrate on the next few weeks rather than on the whole horizon.
When the plan is updated this way, the Earned Value numbers become computable and meaningful: planned value, earned value and actual cost come out of the same columns, and the Earned Value guide, the cost S-curve and the Earned Schedule explain how to read them. Without a baseline and without a status date, those indicators either do not exist or lie.
And then you communicate, even when the news is bad. Hiding a delay that keeps growing is the most expensive mistake a project manager can make: the client has in turn promised something to someone, and finding out close to the deadline turns a technical problem into a trust problem. The updated plan is exactly the tool for saying it early, with the numbers in hand.
The rhythm: how often to update
The update period usually coincides with the reporting period to the client and is agreed at the start; how to choose it is a separate article. There is no universally right frequency: you choose it from the duration and the risk of the project, weekly for short or critical projects, fortnightly or monthly for long and stable ones. Every update costs collection and analysis time: overdoing the frequency means spending more time measuring the project than managing it.
A different matter is how often you collect information from the resources: that can, and often should, be more frequent than the reporting, because it is from the weak signals of mid-week that a delay shows up before it becomes a red bar.
The mistakes I see most often
- Extending the duration instead of recording progress. That is replanning: the delay disappears from the numbers and stays in reality.
- No baseline saved. Variance table all zeros, Tracking Gantt without grey bars: the plan has no memory.
- Baseline re-saved at every update. The project is always “on track” by definition. Re-save only for approved changes, keeping the previous versions.
- Status date always equal to today. If the data is Friday’s and you update on Monday, you have three days of phantom or missing work.
- Percentages without actual dates. 100% closes the task on the scheduled date, not the real one; 50% on a task that has not started invents an actual start.
- Remaining work left in the past. After the actuals, rescheduling uncompleted work after the status date is not optional.
- Scheduled dates typed by hand. Every date typed into Start or Finish is a constraint: the plan stops reacting exactly where it should.
Frequently asked questions
The project has already started and I never saved a baseline: what do I do?
Save it now, with Project → Set Baseline. You will not have the comparison with the original plan, which is lost, but from this moment every update will have a term of comparison. If a copy of the file from when the plan was approved still exists, you can rebuild the baseline from there, but in practice it is rarely worth it: better to start straight away with what you have.
I deleted some tasks after saving the baseline: why do the baseline costs not add up?
Because the baseline of the summary task remembers the cost and work of the deleted tasks: that was what you promised. The negative variance you see is correct and should be explained that way. If the deletion is part of an approved scope change, this is the typical case where you re-save the baseline, after keeping the previous one in a numbered baseline. In Project Professional you can also inactivate the task instead of deleting it: the row stays, struck through, and explains the variance.
What is the difference between % Complete and % Work Complete?
Percent complete measures how much duration has elapsed: a ten-day task on day five is at 50%. Percent work complete measures how many hours have been done out of the total. They coincide only if the work is spread evenly; with several resources or variable loads they diverge. For dates look at the first, for costs and Earned Value at the second.
Can the status date be equal to today’s date?
It can, if the data you are entering is current as of today. The point is that it must be the date the collected information refers to, not the date you find the time to update the file. If you leave the status date empty, Project uses the current date, and that is how inconsistencies arise between what the teams reported and what the plan shows.
The client stopped the work for three months: how do I record it without losing the history?
First save a numbered baseline, so you keep the plan as it was at the moment of the stop. Then set the status date to the day of the suspension, record the actual progress up to that day and reschedule the uncompleted work to start on the restart date. Tasks in progress will appear split; tasks not yet started will slide as a block. The variance against the original baseline documents the impact of the stop, which is exactly what you will need for a claim or an extension.
Further reading on this blog
- The plan that holds: Microsoft Project best practices, symptom by symptom — the diagnostic guide, symptom by symptom
- How to collect actuals from your team and update the plan
- Project planner tools: what you need besides Microsoft Project
- Project estimating methods: top-down, bottom-up and parametric
- Project dashboards: strategic, analytical, operational
- What is a baseline in Microsoft Project, when to set it, and what changes after
- How to review a Microsoft Project plan you did not build: five checks
- How often should you update the project plan? The duration rule and the status date
- Don’t hide the delay from your client: how to see it early, when to say it and how
- Your late tasks, in three clicks
- Your project delay has a direction, not just a size
- How to show the cost S-curve in Microsoft Project
- Earned Value: the complete guide to PV, EV, AC, SPI and CPI in Microsoft Project
- What is Earned Schedule in project control
- The work S-curve in Microsoft Project: the three fields nobody points you to
- Rolling wave planning: detail the next wave, leave the far future coarse
Disclosure: this is the blog of a company that makes project-control software, so take the paragraph below for what it is. Nothing in the method above requires our tool, or any tool: the baseline, the status date, the Update Tasks dialog and the Variance table are all standard Microsoft Project, from 2010 to 2024 and Microsoft 365, and the whole cycle can be run with them alone.
If you want to see the size and the direction of the delay without redoing the comparison by hand at every update, GanttDerivata reads the .mpp file, with no Microsoft Project installation required, and shows how far the critical path has slipped and whether the delay is growing or shrinking over the next three weeks.
#MSProject #ProjectControl #Baseline #StatusDate #EarnedValue