This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.
An .mpp file lands in your inbox. A supplier sent it, or a colleague from another division, or the project manager of a programme you have just been handed. The review is tomorrow morning and you are expected to say something sensible about that plan: whether the dates hold, whether the project can be controlled, whether a decision can be built on top of it.
Opening it and looking at the Gantt chart is not enough. A Gantt chart looks fine even when the plan underneath is fiction: coloured bars, everything neatly lined up, and not one of the dates you see was calculated by Project — they were typed in by hand, one at a time.
What follows is the order in which I look at a plan I did not build. Five checks, from the fastest to the deepest. The first three are almost always enough to know what you are dealing with.

Thirty seconds: is it a plan or a list?
Before you even read the task names, look at the shape.
Open Project → Project Information → Statistics: one small window gives you total duration, work and cost, with the baseline columns next to the current ones. It is the cheapest overview there is.
Then three quick questions.
Is there a structure, or is it a flat list? Three hundred tasks all at the same level are not a plan: they are a to-do list. A real WBS has summary tasks, and the summaries make hierarchical sense.
Are there milestones? Zero-duration tasks marking deliveries, approvals, releases. A plan without milestones has no checkpoints: you will never know you are late until it is obvious.
How many durations say “1 day?” That question mark means estimated duration: it is the value Project fills in by itself when you create a task. If you find it on half the plan, nobody estimated anything — they typed the task names and moved on.
The check that exposes everything: are the dates calculated or typed by hand?
This is the one check worth the other four put together.
In Microsoft Project dates are not typed: they are calculated. You supply durations and links, and the engine tells you when things happen. If someone types the dates by hand they get the same Gantt chart, but they have built a drawing, not a model: when something slips — and it will — the plan does not react.
There are two ways to spot it, and thirty seconds is enough.
Add the “Constraint Type” column. The healthy value is As Soon As Possible: it means the task is free to slide along, following its links. The values that should make you sit up are Must Start On and Must Finish On: they are nails driven into the calendar, and the plan can no longer move. In a healthy plan the hard constraints can be counted on one hand — they are the genuine contractual dates, and there are usually fewer than five. If more than one task in five carries a constraint, that is not a plan: it is a calendar somebody drew.
Look at the icons in the Task Mode column. Since Project 2010 there are manually scheduled tasks: Project leaves them exactly where you put them and never recalculates them. They are genuinely useful in the very early stages, when information is missing, but in a plan that is supposed to be executable they are time bombs. If you find many, ask why.
There is one more tell worth knowing: deadlines. They are the correct way of saying “this has to be done by such a date” without nailing the task down: Project shows an arrow on the Gantt chart and warns you if you overshoot, but leaves the plan free to calculate. A plan that uses deadlines instead of constraints was built by someone who knows what they are doing.

Does the network hold? Dangling tasks and tasks that lead nowhere
A plan is a network: every task should know what it depends on and what it sets in motion. In practice whole sections often turn out to be disconnected.
Add the Predecessors and Successors columns and sort.
Tasks with no predecessors hang from the start of the project: they are free to begin on day one, and that is almost never true. Apart from the first real task, each of them is a question to ask.
Tasks with no successors are more insidious, because they make no noise: they finish, and nothing starts. If a task has no successors, delaying it has no consequences on the plan — which is almost always false in reality. Apart from the last one, each is a missing link in the chain.
A second useful check: links on summary tasks. Linking summary tasks instead of the detail tasks underneath them is a shortcut that looks convenient and makes the plan opaque, because it hides the real dependencies and produces critical paths that nobody can explain.
Is the critical path telling you the truth?
Turn on critical path display (Format → Critical Tasks in the Gantt view) and look at how long it is. There are two pathologies here, and they are opposites.
Almost everything is critical. If 90% of the tasks are red, the plan has no slack anywhere: whatever goes wrong, the finish date moves. Sometimes that is true — it happens in compressed projects — but more often it is the symptom of a network built as a single chain, with no real parallelism.
Almost nothing is critical, or the critical path is broken into fragments. This is the most common signal, and it is the direct consequence of the previous chapter’s problem: hard constraints interrupt the critical path calculation. If the dates are nailed down, Project has nothing to propagate, and the critical path becomes decoration.
The field to look at to really understand it is Total Slack: how many days a task can slip without moving the end of the project. If you find negative slack, the plan is already late against itself: there is an imposed date that the planned work cannot meet. In a review meeting that piece of information is gold, and the Gantt chart does not show it.
Resources and calendar: who works, and when
The last two checks take a couple of minutes and complete the picture.
Do the resources have names? Open the Resource Sheet. If you find “Developer 1”, “Resource A”, “Team”, you are looking at a plan that was never negotiated with anyone: no real person said yes to those dates. Then check whether there is work in hours, not just durations: duration is how long it takes, work is how much effort it costs. Without the second, the plan cannot tell you whether the load is sustainable.
And glance at overallocations (the Resource Usage view, the numbers in red). A plan full of people allocated at 200% tells a story that is not going to happen. In a portfolio, where the same people appear on several plans at once, this is where the trouble usually starts.
Is the calendar telling the truth? Check the project calendar: are the public holidays there? The summer shutdown? If the plan happily works through Christmas and the August break, every date you see is optimistic by days or weeks — and nobody will notice until the summer arrives.
The check almost everybody forgets: is there a baseline?
I keep this for last because it is the one that separates plans that will be useful from plans that will die in a drawer.
Add the Baseline Start and Baseline Finish columns. If they are empty, that plan has no saved baseline: it means that a month from now, when the dates have changed, there will be no way of knowing by how much. No variances, no earned value, no measure of the delay — just the feeling that things are getting worse.
It is a five-second check that changes the kind of conversation you are having: a plan without a baseline is not yet an approved plan, whatever the email that brought it says.
The table I use in the meeting
When I need to give a quick verdict, these are the symptoms and what they actually mean.
| What you see | What it means | The question to ask |
|---|---|---|
| Many durations showing “1 day?” | Nobody estimated | What are these durations based on? |
| Many Must Start On constraints | Dates were typed, not calculated | Which of these dates are contractual and which are not? |
| Tasks with no successors | The network is incomplete | What starts when this one finishes? |
| Critical path missing or fragmented | Constraints broke the calculation | Can we remove the constraints and see what happens? |
| Negative total slack | The plan is already late against itself | Do we know this date is not achievable? |
| Generic resources | Nobody said yes to these dates | Who are the real people behind these roles? |
| No baseline | Nothing can be measured | When do we save the baseline? |
| Calendar without holidays | The dates are optimistic | Does the calendar account for holidays and shutdowns? |
No single symptom condemns a plan. Three or four together do: it means that file is a presentation document, not a control tool, and that decisions taken on its dates are decisions taken in the dark.
Frequently asked questions
How long does this review really take?
Ten minutes for the first three checks, which are the ones that tell you whether you can trust the plan. Half an hour for everything, if the plan has a few hundred tasks. That is far less than the time you would lose by trusting a wrong plan.
Does it work on every version of Microsoft Project?
Yes. Constraint Type, Total Slack, critical path, the Resource Sheet and the baseline fields are identical from Project 2010 to Project 2024 and in the desktop versions shipped with Microsoft 365. Task Mode (manual or auto) appeared in Project 2010: on earlier versions that check simply does not apply.
I do not have Microsoft Project: can I still review an .mpp file?
You can read the file with a viewer, but most of these checks require adding columns and switching views, which free viewers often do not allow. Another route is to bring the plan into Excel and run the checks there, with tools you already know: MppToExcel — a tool of mine — reads the .mpp file directly, with no Project installation required, and from there filtering constraints, sorting by total slack or counting tasks with no successors becomes pivot-table work.
If I find all these problems, should the plan be thrown away?
Almost never. A plan with constraints and dangling tasks can be recovered: remove the constraints, link the disconnected tasks and see where the date lands. The point is not to fail the plan, it is to know what you are holding before you make commitments on its dates.
What if the plan is mine, not someone else’s?
Same thing, and even more useful: these checks are the checklist to run before you send a plan to anyone. Run them yourself, before somebody else runs them on you in a meeting.
Further reading on this blog
- Your project works on Christmas Day (unless you tell it not to)
- What is a baseline in Microsoft Project, and when to save one
- How to update a Microsoft Project plan: baseline, status date and progress
- Bottom-up estimating: forty honest estimates, one optimistic total
- Comparing top-down and bottom-up estimates in Microsoft Project
- Task dependencies: the four link types, hard and soft, and where the link goes
Disclosure: I build the Project Edge Tools suite. If you receive .mpp files often and do not have Microsoft Project at hand, MppToExcel reads the file directly — no Project installation required — and lays the plan out in Excel, where every check in this article becomes a filter or a pivot table. The method above stands on its own; the tool just makes it faster.
This article grew out of a 2012 note on a guide by Tamzin Morphy, published on PM Hut, on how to read a Microsoft Project plan. The method above is my own — years of plans received from suppliers and colleagues — but the spark came from there, and it is only fair to say so.