“How often do we update?” It is one of the first questions a client asks, usually in the same meeting where the plan is approved, and usually the answer comes by instinct: “every week”, or “at the end of each month, with the progress report”. It is not a small choice. That number decides how many times, from here to the end of the project, you will hold an updated plan in your hands, and therefore how many chances you will have to notice in time that something is off.
But it also decides how much time you will spend collecting data instead of managing the work. The update period is a compromise between these two things, and like every compromise it is better chosen with a rule in front of you than by feel.
In short
- The update period is the fixed interval between two snapshots of the plan at the status date. It normally coincides with the reporting period to the client and is agreed at the start, not improvised.
- The starting rule is the duration of the project: a three-month project is updated every week, a one-year project every month, a five-year project every six months. The table gives a minimum and a maximum frequency for each duration.
- Within that range the choice is moved by risk, project phase, contractual requirements and team stability. More uncertainty, more frequent.
- Every update costs: collection, entry, analysis, presentation. If you spend more time measuring the project than managing it, the frequency is wrong.
- How often you collect information from the resources is a different matter, and it is usually more frequent than how often you report to the client.
Two rhythms, not one: reporting and collection
The first confusion to clear up is between two frequencies that are often called by the same name. The first is the reporting period: how often the client, management or the sponsor receive the status of the project, with the numbers and the decisions to be taken. The second is the collection frequency: how often you, who run the project, gather from resources and suppliers the information about what has really been done.
The update period of the plan coincides with the first. There is no point in presenting a project status calculated on a plan frozen three weeks earlier, and no point either in updating the plan twice as often as it is read: the update exists to produce a snapshot comparable with the previous one, and the snapshot is looked at together with the client.
Collection, on the other hand, can and often should be more frequent. If reporting is monthly and you hear from the resources once a month, the day before the meeting, you discover the delay when it is already four weeks old. If you hear from them every week, or every day in a delicate phase, the weak signals arrive earlier and you walk into the meeting already knowing what to say. The trend shows before the evidence, but only if someone is looking: that is why it pays to watch the direction of the delay, not just its size.

What an update costs
Updating a plan is not clicking a button. For each period you do five things, in order:
- collect from the resources the actual start and finish dates, the work done and the work remaining, the costs incurred;
- enter the data into the plan;
- move the status date to the new period;
- compare the result with the baseline;
- prepare the presentation for those who decide.
Between the project manager’s time and the often forgotten time of the people who have to stop and answer, a serious update of an average plan takes from half a day to a full day.
Multiply by the frequency and the sum is quickly done. A weekly update on a two-year project is a hundred updates: a hundred half-days of collection and analysis, and a hundred times the team is interrupted to say where it is. It is the classic case of spending more time measuring the project than managing it, and one in which the resources, after a while, answer at random just to get it over with. At that point the data is unreliable too.
The opposite extreme costs more, but in a different way. A one-year project updated every three months has four snapshots in total: when the second one shows a delay, a quarter of the project has already gone by and the options for recovery are half of what you had. The cost of an update shows immediately; the cost of a missed update shows at the end.
The starting rule: the duration of the project
The table below is one I first wrote down in 2010, and I have found no reason to change it. For each duration it gives the minimum and the maximum frequency that a reasonable client asks for, or that it makes sense to propose. The update period is chosen within that range.
There is a logic behind it, and it is worth seeing because it helps with the durations that are not in the table. If you count how many updates each row produces, the number is almost always the same:
- 3 months, every week: 13 updates;
- 1 year, every month: 12;
- 2 years, every two months: 12;
- 5 years, every six months: 10.
On the “maximum” side of the table you get 24, 26, 30. A project, whatever its duration, needs about ten checkpoints as a minimum and about thirty as a maximum. Below ten you cannot see the trend; above thirty the control costs more than it protects.

This also gives the practical rule for an eight-month project, or a three-year one, which do not appear in the table: divide the duration by twelve or fifteen and you have the base update period. Eight months divided by twelve is about three weeks; three years divided by twelve is a quarter. Then you adjust with the factors that follow.
The factors that move the choice within the range
Duration says where the range is. Within the range, four things decide whether to stay close to the minimum or to the maximum.
- Risk. A project with many technical unknowns, suppliers never seen before or a scope still moving is updated more often than one that repeats things already done ten times. The update is the only moment in which an unknown becomes a number.
- Phase. The period does not have to be the same for the whole life of the project. Start-up, integration and testing phases deserve a tighter rhythm; a long production phase at steady state can bear the looser one. Say so in the communication plan, so that nobody reads it as a change of course.
- The contract. Many clients require a monthly progress report or a quarterly report by contract. That is the reporting period, and the update period must be aligned with it: updating at a different rhythm from the one you report at produces snapshots nobody looks at, or reports based on stale data.
- Team stability. Dedicated resources, always the same, provide data in five minutes; resources shared across several projects, external, or spread over several sites have a much higher collection cost, and the frequency must take that into account, or the collection must be organised so that it does not go through the project manager.
A fifth factor, less noble but real, is the calendar that already exists. If the company has a steering committee on the first Monday of the month, the monthly period with the status date on the last Friday of the previous month imposes itself. Fighting the existing rhythms to defend a theoretical frequency is a battle you always lose.
Fixing the rhythm in Microsoft Project: the status date
Once the period is decided, in Microsoft Project the rhythm materialises in one thing: the status date. It is set in Project → Project Information → Status date, and it is moved forward by one period at every update, always on the same day of the week or of the month. It is the date at which the plan declares “up to here I know what happened”: percent complete, actual work, the Earned Value indicators are all calculated against it, not against today. It is the most neglected and most important field in the whole file.
The update period is, in practice, the distance between two consecutive status dates. If it is fixed, the snapshots are comparable and the trend can be read: the finish variance of a critical task that was two days at the previous status date and five at this one says that the delay is growing. If the status dates fall at random, one after ten days and the next after forty, comparisons lose their meaning and every update starts from scratch.
Three small habits make the difference between a declared rhythm and a respected one:
- make the status date visible in the Gantt chart, with the vertical line you turn on in Format → Gridlines → Status Date: whoever opens the file sees at a glance how current it is;
- enter progress with real actual dates, not just a percentage: it is the actual start and finish dates that make the plan a record of what happened, and not just an updated estimate;
- keep a saved baseline and do not re-save it every period: without the comparison with the baseline, the update says where you are but not how far you have moved.
The complete cycle, from collection to reading the results, is described step by step in the guide on how to update a Microsoft Project plan: this article answers only the question “how often”, that one answers “how”. What you then measure on the updated plan is the subject of the Earned Value guide.
When to change the period, and when not to
The period is agreed at the start, but it is not a life sentence. You tighten it when the project enters a critical phase, when a delay on the critical path is confirmed for two updates in a row, or when a key supplier starts missing dates: in all these cases the value of each extra snapshot is high and the cost is justified. A one-year project that moves from monthly to fortnightly in its last three months is not admitting failure, it is doing its job. Recovering a delay, in particular, almost always requires a shorter period until the delay is absorbed.
You loosen it rarely, and only with a reason you can state: a long and stable phase, a team that provides reliable data without prompting, a client who asks for less. You never loosen it because the project is going badly and updating has become unpleasant. It is the most human mistake and the most expensive: the missing snapshot is exactly the one that would have shown the problem while it was still recoverable.
In both cases the change is communicated to the client before it is applied, with the reason. A client who receives the report every two weeks instead of every month, with no explanation, does not think “how diligent”: they think “what is he hiding from me”.
The mistakes I see most often
- Updating “when needed”. That is, when someone asks for the plan. The plan is updated in a hurry on the day of the meeting, with data collected by phone that morning, and the status date is “today”. No snapshot is comparable with the previous one.
- Status date left empty. Project then uses the current date, which changes every day: opening the file on Monday and on Thursday gives two different progress states without anyone having entered anything.
- Collection and reporting at the same rhythm. If you hear from the resources once a month, every problem has had a month to grow before you knew about it. Collection must be kept more frequent than reporting.
- Different rhythms for plan and report. The plan updated every week and the monthly progress report built by hand in a separate sheet: after three months the two no longer say the same things.
- Confusing update and replanning. The update records what happened up to the status date; replanning decides what to change from there on. They are done on the same day, but the second is optional and the first is not.
The opposite case: when the table is not enough
The table reasons about projects with a plan of defined duration, managed by snapshots. There are at least three contexts in which the rhythm is decided by something else.
- Project run in sprints. The update period is the sprint, usually two weeks, whatever the total duration: the table would say “every month” for a one-year project, and it would be wrong, because the cadence is already decided by the method.
- Construction site with daily penalties. In the last weeks the update is daily even if the project lasts two years, because every day has a price written in the contract.
- One-month project with external resources who do not report every day. The maximum frequency of the table is simply unreachable, and you might as well say so at once instead of chasing data that never comes.
The table remains the starting point: it gives you a reasoned proposal to put on the table. Then context always wins, as long as the decision is taken and written down, not left to chance.
Frequently asked questions
For a one-year project: every week or every month?
The table says every month as a minimum and every two weeks as a maximum. Every week is too much for the whole year: fifty updates cost more than the control they give. The most common choice that works is monthly in stable phases and fortnightly in critical phases, declared that way in the communication plan from the start.
Do I have to update the plan even if nothing has changed?
Yes. The update does not record only changes; it records that at the status date things stood that way. Moving the status date, confirming the actual dates and saving is the proof that control took place; and a period in which “nothing changed” on tasks that were supposed to progress is, in itself, a piece of information worth having.
The client wants a daily update on a two-year project. What do I do?
I ask what they want to know every day. Almost always the answer is “whether there are problems”, and that is communication by exception, not a plan update: you agree a channel for the unexpected and keep the plan on a monthly rhythm. If they really want the numbers every day, I show them the cost with the table: five hundred updates, each with its own collection. Usually the request shrinks by itself.
Which day should the status date be?
A fixed day, always the same, and preferably the end of a natural unit of work: Friday for a weekly period, the last working day of the month for a monthly one. Collection is done the day before, the update on the day itself or the first working day after, the presentation within a few days. If two weeks pass between status date and report, the report is already old when it is read.
Are the plan update and the progress report the same thing?
No, but they must have the same rhythm. The update is the operation on the plan: the actual data is brought in at the status date. The progress report, or status report, is the document that comes out of it and goes to the client: what was done, what is late, what is decided. A report built from a plan updated at the same date is credible; a report written by hand with a plan frozen a month earlier is an opinion.
The table dates from 2010: is it still valid?
Yes, because it does not depend on the software but on the ratio between project duration and the number of useful snapshots. What has changed is the ease of collection: today resources can report progress from a shared sheet or an app instead of by phone, and that lowers the cost of each update. The effect is that you can afford to stay closer to the maximum frequency of the range, not that the range has changed.
This article is part of two guides on this blog
- How to collect actuals from your team and update the plan
- Project planner tools: what you need besides Microsoft Project
- Project dashboards: strategic, analytical, operational
- How to update a Microsoft Project plan: baseline, status date and progress
- Earned Value: the complete guide to PV, EV, AC, SPI and CPI in Microsoft Project
- Your project delay has a direction, not just a size
- Your late tasks, in three clicks
- Rolling wave planning: detail the next wave, leave the far future coarse
Disclosure: this is the blog of a company that makes project-control software, so take the paragraph below for what it is. Nothing in the method above requires our tool, or any tool: the duration table, the status date and the Gridlines option are all standard Microsoft Project, and the collection from your team can be done with a shared sheet.
If collecting the actuals from the team is what makes each update expensive, GanttTimesheet lets each resource report the hours worked on their own tasks against the Microsoft Project plan, so that the collection step no longer runs through the project manager.
#MSProject #ProjectControl #StatusDate #ProjectReporting