One plan, four readers: four different Excel workbooks from the same .mpp

One plan, four readers: four Excel workbooks from the same .mpp. The site manager gets the next three weeks, the client the milestones, the contractor its tasks and hours, accounts the costs

The same plan, for a logistics hub due in October, has to reach four people. The site manager wants to know what happens in the next three weeks. The client wants the milestones. Accounts want the costs. The electrical contractor wants only its own tasks and its own hours.

Sending all four of them the whole plan doesn’t work: each has to dig out their part from every row, and the client sees things they shouldn’t. Rebuilding four different workbooks by hand every time the plan changes doesn’t work either. In the first article of this series we took the plan into Excel with the Gantt chart. Here the same .mpp file becomes four different workbooks, one per reader.

In short

  • To filter a Microsoft Project plan in Excel by resource or by date without rebuilding the sheet by hand, the Pro edition of MppToExcel picks the rows before exporting: date window, resource, outline branch, milestones only, open tasks only.
  • Filters add up, summary tasks stay as long as something remains below them, and the line at the top of the sheet says how many tasks were left out.
  • Task notes and resource rates never leave the file; costs only if you ask for them.

The MppToExcel Pro spot: one plan, four readers, one click. Click to watch, 36 seconds

▶ One plan, four readers: the 36-second spot

The site manager: the next three weeks

A year-long plan is no use to the site manager: they need the stretch right in front of them. In the “Columns and filters” window, Filters tab, the “Next 3 weeks” button sets the date window from today to twenty-one days ahead. “open tasks only” drops the ones already finished, and with the day timescale the Gantt chart has one column per day, weekends in grey.

One detail that matters: a task is in the window if it touches it, not only if it sits entirely inside. A three-month job that started in July is still the site manager’s business over the next three weeks, and it stays in the sheet.

The Filters tab of MppToExcel Pro: open tasks only, milestones only, branch by outline number, resource, date window with the Next 2 weeks and Next 3 weeks buttons
The Filters tab: with nothing ticked, the whole plan is exported.

The client: the milestones, and nothing more

The client doesn’t need to read the sequence of concrete pours: they need to know whether the promised dates are holding. With “milestones only” the sheet keeps the milestones, each under its own summary task. And the milestones sheet, an extra sheet in Pro, lines them up by date: baseline start, current start, variance in days, reached or still to reach. A late milestone shows its variance in red: it is the first question the client will ask, so you might as well answer it on the sheet.

If the client follows only part of the work, the Branch filter takes an outline number and everything below it: “3” brings the racking and its sub-levels, and nothing else.

Accounts: the costs, because they asked

This is where the “Include cost data” box gets ticked. The sheet gains the Cost and SIL/SAL columns, the latter being the actual cost, and in the Columns tab you can also add Baseline cost and Cost variance. “Add the cost curves sheet” brings a period-by-period table of baseline cost, cost and actual cost with their running totals, plus the chart that draws them.

The box starts unticked at every launch, and without it the cost curves sheet can’t even be selected. That way the accounts workbook doesn’t turn into the client’s by mistake.

The electrical contractor: its tasks, its hours

The Resource filter searches the resource names for the text you type, even just part of it and regardless of case: “elettra” finds every task of Elettra Impianti. The resource load sheet adds one row per resource and one column per period, with the hours in the cells and the busiest periods in orange: the contractor sees at once the weeks when it needs more people.

And if someone at the same contractor prefers to think by week and by task, the “Who does what when” sheet brings the assignment data and a ready-made pivot table, with resources down the rows and weeks across the columns.

The four workbooks, in one table

ReaderFiltersExtra sheets
Site managerNext 3 weeks, open tasks onlynone: the day-scale Gantt chart is enough
Clientmilestones only, optionally one branchthe milestones sheet
Accountsnone, but with “Include cost data”the cost curves
ContractorResourcethe resource load, “Who does what when”
Four exports from the same .mpp file: a handful of clicks each.

Two behaviours keep the four deliveries in order. Filters are not remembered from one launch to the next: every time you start from the whole plan, and the site manager’s cut never ends up with the client by accident. Columns are: if you drop the columns nobody needs, the choice stays. And the line at the top of every filtered sheet states the filter and how many tasks were not exported: whoever reads it knows they hold part of the plan, not the plan.

The Columns tab of MppToExcel Pro: the list of columns to tick and reorder, eight of thirty chosen, and the Name column that cannot be removed
The Columns tab: thirty columns to choose from, in the order you need.

Filters, column choice and the extra sheets belong to the Pro edition; in Base they are visible, greyed out and marked “(Pro)”. The 15-day free trial is the full Pro edition: you can try all four workbooks on your own plan.

Frequently asked questions

Can I use several filters together?

Yes, and they add up: a task is exported only if it meets all of them. For example “open tasks only”, Resource “elettra” and “Next 3 weeks” give the work Elettra Impianti still has to do over the next three weeks.

Will the client see task notes or resource rates?

No. Task notes and resource rates are never exported, in any edition. Costs come out only if you tick “Include cost data”, which always starts unticked.

What happens to summary tasks when I filter?

The filter picks the detail tasks; a summary task stays if something remains below it and disappears if it is left empty. That way every exported task keeps its path through the plan’s structure.

What if the filter leaves nothing?

The program doesn’t write an empty sheet: it tells you that no task matches the filters, and you widen them or remove them with “Clear filters”.


This is the second of three articles on MppToExcel. The next one covers what MppToExcel does not do, and when you don’t need it.

#MSProject #Excel #GanttChart #ProjectReporting