This article is part of the guide Project dashboards: strategic, analytical, operational, which covers the three types and how to choose between them.
You export a Microsoft Project plan to Excel, open the file, and the first thing you do is delete rows: the summary tasks, the zero-duration milestones, sometimes the row for the whole project. By hand, every single time. A reader asked me exactly this: he exported from Project with his own maps and filters, and the summary rows kept arriving in a sheet that had no use for them.
To export Microsoft Project to Excel without those rows, the fix is a filter, but not just any filter: two conditions, applied inside the Export Wizard, with one checkbox that must stay unticked. Set it up once, save it with the map, and from then on the export comes out clean.
In short
- Export from File > Export > Save Project as File > Microsoft Excel Workbook, through the Export Wizard, choosing Selected Data.
- The right filter has two conditions joined by And: Summary does not equal Yes and Duration does not equal 0.
- The Show related summary rows box must be unticked, or the summaries come back into the sheet.
- The filter goes into the Export filter of the task mapping, and saving the map makes it reusable for every export.
Where the extra rows come from
A normal plan has more than one outline level: summary phases at the top, work tasks underneath, and a milestone closing each phase. In the sample plan used here, a marketing campaign, the first phase alone has one summary row, twelve tasks and one milestone: fourteen rows, of which only twelve are actual work.
An export without a filter takes all fourteen. The summary rows are containers whose duration, work and cost are the sum of the tasks inside them, so in Excel they count everything twice; the milestones are zero-duration markers. The goal is to export only the tasks with a duration greater than zero: no summaries, at any outline level, and no milestones.
The Export Wizard, step by step
Exporting to Excel always goes through Project’s Export Wizard, which maps the fields of the plan onto the columns of the sheet. The way in:
- Go to File > Export > Save Project as File, choose Microsoft Excel Workbook and click Save As. In Project 2010 you go straight through Save As and pick the Excel Workbook type.
- Name the file and click Save: the Export Wizard opens. Click Next.
- Choose Selected Data, not Project Excel Template: it is the option that lets you decide the fields and the filter.
- On the map page choose New map the first time, or Use existing map to start from one you already have.
- On the Task Mapping page, next to the destination worksheet name, there is an Export filter list: replace All Tasks with the filter we build below.
- On the last page click Save Map, give it a name, then Finish.
The filter that keeps summaries and milestones out
You prepare the filter in Project before exporting. The quickest way is to copy an existing one and change its conditions:
- On the View tab, open the Filter list and choose More Filters.
- Select Summary Tasks and click Copy: a new filter definition opens, already holding a condition on Summary.
- Give it a name you will recognise, such as “Work tasks”.
- First condition: Summary does not equal Yes. Only rows that are not summaries get through.
- Second condition, with And: Duration does not equal 0. Milestones stay out.
- Untick Show related summary rows, then click Save.
That last step decides the outcome. With the box ticked, Project puts back the summaries the filtered tasks belong to, and the sheet is exactly as it was: full of rows to delete. If you already use a filter of your own, just add the two conditions to it and untick the box.

The result in Excel, and one row worth watching
The sheet holds only the work tasks: no summary rows, no milestones. The row for the whole project, the project summary task with ID 0, stays out too, because it is a summary as well. That matters: if it reached the sheet and you summed it with the other rows, it would double work and cost.
From here the export is repeatable: open the wizard, pick the saved map, and the filter travels with it.
When exporting becomes a standing job
The Export Wizard is fine for one plan, now and then. It gets tight once the export becomes routine:
- Every week, for the same report: each time someone has to open Project, run the wizard and remember the right map.
- With many plans: each export works on the file you have open, and bringing every project manager’s plan into the same sheet stays manual work.
- For people without Project: with no Project installed there is no wizard.
- To feed another system, a dashboard or an ERP, that wants the same columns in the same order every time.
For those cases we built two tools that read the .mpp file directly, without Project. MppToExcel turns a plan into a ready-to-read workbook, with the task table and a Gantt chart drawn in the cells. OneClickExporter exports plans, master plans and whole folders of plans into files whose columns never move, an Excel workbook included, and does it overnight from the command line. Both have a free 15-day trial.
Frequently asked questions
Does this work in the latest versions of Microsoft Project?
Yes. The Export Wizard, maps and filters are the same from Project 2010 to Project 2024 and in Project for Microsoft 365, in the desktop version. Only the way in changes: from Project 2013 on it is File > Export, in Project 2010 it is Save As.
Can I export resources and assignments too?
Yes. When you create a new map, the wizard asks which types of data to export: tasks, resources, assignments. Each goes to its own sheet, with its own field mapping and its own export filter.
What if I need the milestones?
Remove the second condition, Duration does not equal 0, and keep only Summary does not equal Yes: tasks and milestones reach the sheet, still without summaries.
Isn’t copy and paste from the view enough?
Once, yes: apply the same filter to the view, select the columns and paste them into Excel. But you redo it every time, and the columns are those of whatever table is on screen at that moment. A saved map, instead, always exports the same fields in the same order.
When is the Export Wizard the wrong tool?
When the export becomes periodic, involves many plans at once, or has to reach people who don’t have Project. Then a tool that reads the file directly and always produces the same result is the better fit, with no trip through Project each time.
Further reading on this blog
Disclosure: this is the blog of a company that makes software for Microsoft Project files, including MppToExcel and OneClickExporter mentioned above. Everything in the steps works with Project desktop alone.