Yes, you can — and without a server. Microsoft Project desktop on its own does not email assignments — but you need neither Project Server nor Project Online: you need a tool that reads the plan and prepares one email per resource. In this guide: why the answer you find online is wrong, the three honest routes (manual, VBA macro, dedicated application) and when to choose each one.
First things first: the answer you find online is twenty years old
Search the web (or ask an AI) and you still find advice about Project’s old “workgroup” feature — the “E-mail only” option the PM used to send TeamAssign messages from the toolbar. That feature no longer exists: Microsoft removed it from modern versions of Project almost twenty years ago, moving everything to the server (Project Server first, then Project Online — and the latter closes on 30 September 2026). On today’s Project Standard and Professional that menu simply is not there. The real routes are three.
Route 1 — By hand: filters, copy and paste
For a small plan and the occasional send:
- In the Resource Sheet, fill in the email addresses.
- In the Gantt, apply the Using Resource filter (or filter by Resource Names) to isolate one person’s tasks.
- Copy the rows and paste them into an Outlook email, or export the view to PDF and attach it.
- Repeat for every resource.
It works, it costs nothing, and with ten resources it becomes a lost morning — every week. No return trip either: the answers come back as free-form emails you then re-type into the plan by hand.
Route 2 — The VBA macro
This is the standard forum answer: a loop over the resources, a loop over the assignments, one Outlook email each. A 30-line macro covers the basic case, and if you know VBA it is a good exercise. The real limits are these:
- Maintenance: the macro is yours — if anything changes (fields, format, Outlook) you are the one who fixes it.
- Security: macros must be signed or authorised, and in many companies policy blocks them outright.
- One way only: the macro sends, but the return trip (progress flowing back into the plan) stays manual.
- Format: a plain-text email, with no structured form where the resource can enter their hours.
Route 3 — A dedicated application: SendTask
(Full disclosure: SendTask is my own product, under the Project Edge Tools brand. The limits of the alternatives above are true regardless.)
SendTask reads the plan’s .mpp file directly (MPXJ library): you pick the resources, hit send, and every person receives their own tasks by email — with an Excel timesheet already laid out for entering hours and progress. Three properties that matter:
- Recipients install nothing. No Project, no Excel, no app: they open the email, find their tasks and the form to fill in.
- No server, no mandatory cloud. The send starts from your PC; the plan’s data never passes through a third-party platform.
- Each person sees only their own. The full plan stays with you: rates, costs and other people’s work do not travel.
And the return trip? That is the job of the twin product, GanttTimesheet: it collects the filled-in timesheets, lets you approve them line by line and writes the progress into the plan. Together they close the loop that used to require Project Server: assignments out, progress back in.

Which route to choose
| Situation | Route |
|---|---|
| Small plan, occasional send | By hand (filter + Outlook) |
| You know VBA, sending is enough, macro policy permitting | Macro |
| Recurring sends, a team without Project, progress must come back | SendTask (+ GanttTimesheet) |
| The timesheet also feeds finance/HR, with corporate approvals | An enterprise system (TimeControl, SCMPP) |
Frequently asked questions
Do I need Project Server or Project Online?
No. The manual and VBA routes use Microsoft Project desktop; SendTask does not even need that: it reads the .mpp file directly. (Project Online, incidentally, is being retired by Microsoft on 30 September 2026.)
Do the people receiving the tasks need Microsoft Project?
No. With SendTask they receive an email with their tasks and a fillable Excel timesheet; they install nothing. With the manual route they receive a PDF or a table.
Does the PM need Project installed?
No: SendTask reads the .mpp file directly (MPXJ library), without Microsoft Project installed on the sending PC. The plan file is enough, and that includes a master plan with inserted subprojects: SendTask reads every subproject and groups the tasks by the project they came from.
Does the progress come back into the plan by itself?
With the manual route and with the macro, no. With GanttTimesheet yes: collection, line-by-line approval and write-back into the plan.
Getting tasks to the team is one of the four directions a plan has to travel. The other three — out to the client, out to the leadership, and back in with the actuals — are covered in project planner tools: what you need besides Microsoft Project.
Sending the tasks out is half the cycle. Getting the numbers back — actual dates and remaining work — is the other half: how to collect actuals from your team and update the plan.
SendTask reads a Microsoft Project plan from the file and sends every resource their own assignments by email, with an Excel timesheet attached. No Project, no Excel, no add-in, no administrator rights; the plan is never modified. In six languages, with a 15-day trial that needs no key.
#MicrosoftProject #ProjectManagement #ProjectServer #Timesheet #SendTask
This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.