“We are at 60%.” It is the most frequent sentence in progress meetings and also the least informative: 60% of what? Of the time elapsed, of the tasks closed, of the budget spent? A project can have used 60% of its time, spent 70% of its money and produced 45% of its work. Three true percentages, three different stories, and none of them alone says whether the project is healthy.
Earned Value Management (EVM) exists to put these quantities on the same scale, money, and compare them. Three numbers, all in currency, measured at the same date: how much work I should have done, how much work I have done, how much I have spent doing it. Every indicator of the method descends from these three, and Microsoft Project calculates them by itself, provided you have given it the three things it needs.
In short
- Earned Value compares three quantities in money at the same date: planned value (PV, how much work was planned), earned value (EV, how much work was done, valued at baseline cost) and actual cost (AC, how much was spent).
- Differences give the variances (SV = EV − PV, CV = EV − AC), ratios give the indices (SPI = EV / PV, CPI = EV / AC): below 1 is a problem, above 1 is better than planned.
- The indices project the future: the estimate at completion EAC = AC + (BAC − EV) / CPI says what the project will cost if it goes on like this.
- In Microsoft Project the fields are called BCWS, BCWP and ACWP and they calculate themselves, but only with a saved baseline, a status date and rates on the resources. Without one of the three, the numbers are zero or lie.
- Classic EVM has a weak spot: the schedule index SPI is a ratio between sums of money and drifts to 1 towards the end of the project even when the project is late. For time, use Earned Schedule alongside it: it projects the earned value onto the plan curve and measures the delay in days or months.
Three numbers to really know how a project is doing
All of Earned Value rests on three quantities, measured at the status date, that is, the date the plan update refers to.
- Planned Value (PV). The cost, according to the baseline, of the work that should have been completed by that date. It is the plan curve: the sum of the baseline costs of everything the original Gantt placed before the status date. In Project it is called BCWS, Budgeted Cost of Work Scheduled.
- Earned Value (EV). The cost, again according to the baseline, of the work actually completed by that date. Not how much was spent: how much the work that was done was worth at budget. In Project it is BCWP, Budgeted Cost of Work Performed.
- Actual Cost (AC). How much was really spent for that work. In Project it is ACWP, Actual Cost of Work Performed.
The quantity that makes the difference is the second. Earned value is the only one of the three that holds progress and money together: it turns “we have done 40% of the work” into “we have produced work that was worth €40,000 at budget”, and from that moment progress and costs become comparable. To these three you add the budget at completion (BAC): the total baseline cost of the whole project, that is, the planned value on the last day.

A worked example: the €100,000 project
A ten-month project with a budget at completion of €100,000, spread evenly. At the end of the fifth month the baseline said half of the work would be complete: PV = 50,000. The plan update shows instead that the completed work is worth, at budget, EV = 40,000. The accounts say that AC = 45,000 was spent to do it.
Three numbers, and the picture is already complete: less work was done than planned (40 against 50) and that work cost more than it was worth (45 against 40). The project is behind schedule and over budget, and we know it precisely, not by feel. The rest of the method is a way of expressing these two distances in forms that help decisions.
From variances to indices: SV, CV, SPI and CPI
The variances are differences in money:
- Schedule Variance, SV = EV − PV = 40,000 − 50,000 = −10,000. Negative: less value was produced than the plan expected at this date. It is a delay expressed in money.
- Cost Variance, CV = EV − AC = 40,000 − 45,000 = −5,000. Negative: the work done cost more than it was worth at budget.
The indices are ratios, and they are useful because they can be compared across projects of different size and over time:
- Schedule Performance Index, SPI = EV / PV = 40,000 / 50,000 = 0.80. For every euro of planned work, 80 cents were produced: the project runs at 80% of the planned pace.
- Cost Performance Index, CPI = EV / AC = 40,000 / 45,000 = 0.89. For every euro spent, 89 cents of value are obtained.
There is only one reading rule: 1 is the plan. Below 1 the project is doing worse than planned on that dimension, above 1 better. The two indices together place the project in one of four quadrants, and the quadrant tells you what kind of decision is needed.

The weak spot: SPI measures time in money
SV and SPI are called “schedule” indicators, but they contain no dates. They compare two sums of money, earned value and planned value at the same date, and from that comparison infer a delay. As long as the project is halfway through, the reasoning holds. The problem appears towards the end, and it is structural.
Let us continue the example. The project runs at 80% of the planned pace for its whole life, so it closes at month 12.5 instead of 10: two and a half months late. At month 10, the planned finish, the work done is worth 80,000 out of 100,000 and SPI reads 0.80, correctly. But from there on the planned value stops growing, because the plan is over and PV has reached the budget, while the earned value keeps rising: at month 11 SPI reads 0.88, at month 12 it reads 0.96, at month 12.5 exactly 1.00. The index returns to “all on plan” precisely when the project closes with its maximum delay. It is not a calculation error: EV and PV both converge to the budget, and the ratio of two numbers converging to the same value can only tend to 1.

Earned Schedule (ES) solves the problem by changing the unit of measure. Instead of asking “how much value have I earned compared to what was planned”, it asks “at what date did the plan expect the value I have earned today“. You project EV onto the planned value curve and read the corresponding date: that is the Earned Schedule. Its difference from the status date (AT, actual time) is the delay expressed in time, SV(t) = ES − AT; the ratio is the index, SPI(t) = ES / AT.
In the example, at month 5 the earned value of 40,000 is what the plan expected at month 4: ES = 4, SV(t) = −1 month, SPI(t) = 0.80. So far the two indices coincide. At month 12 the EV of 96,000 corresponds to month 9.6 of the plan: SV(t) = −2.4 months and SPI(t) still 0.80, while the classic SPI reads 0.96. Earned Schedule tells the truth until the last day, and tells it in months, which is the unit a sponsor uses to think about delays. The example uses a uniform plan to keep the arithmetic readable; with the S-curve of a real plan, SPI starts inflating before the planned finish, as the planned value slows down towards the budget, and SPI(t) oscillates around its value instead of staying a straight line. The underlying behaviour does not change.
The practical rule that follows: for costs use CPI, which does not suffer from this defect; for time, put Earned Schedule next to SPI, and beyond the midpoint of the project look only at Earned Schedule. Microsoft Project does not calculate Earned Schedule among its built-in fields, but you can derive it from its BCWS and BCWP fields with a spreadsheet. Earned Schedule has limits of its own that you should know, from the critical path it does not see to its dependence on the weighting and on a stable baseline: I covered them in full in What is Earned Schedule in project control.
Looking ahead: EAC, ETC, VAC and TCPI
So far Earned Value has described the past. Its real value lies in projecting it: if the project continues with the efficiency shown so far, where will it end?
- Estimate at Completion, EAC = AC + (BAC − EV) / CPI = 45,000 + 60,000 / 0.89 = €112,500. It is the most used formula and the one Microsoft Project applies: the remaining work will cost with the same inefficiency as the work done. There are more cautious variants, which also divide by SPI, and more optimistic ones, which assume efficiency 1 from here on; the choice should be stated.
- Estimate to Complete, ETC = EAC − AC = €67,500: how much is left to spend.
- Variance at Completion, VAC = BAC − EAC = 100,000 − 112,500 = −€12,500: by how much the budget will be exceeded if nothing changes.
- To-Complete Performance Index, TCPI = (BAC − EV) / (BAC − AC) = 60,000 / 55,000 = 1.09: the efficiency the remaining work would need to finish within the original budget. If the historical CPI is 0.89 and the required TCPI is 1.09, the question in the meeting becomes concrete: what changes, from tomorrow, to go from 89 to 109 cents of value per euro spent? If the answer is “nothing”, the budget must be revised now, not at the end of the project.
CPI says how it went. TCPI says what would have to happen for it to end well. The distance between the two is the conversation to have.
How Microsoft Project calculates Earned Value
Project has all these fields ready: BCWS, BCWP, ACWP, SV, CV, SPI, CPI, BAC, EAC, VAC, TCPI, plus SV% and CV%. They appear in three dedicated tables, reachable from View → Tables → More Tables: the Earned Value table with the base quantities and the forecasts, and the two tables of cost indicators and schedule indicators. Since Project 2013 there is also a graphical Earned Value report among the built-in reports (Report → Costs).
To calculate them Project uses three ingredients, and it is worth knowing where it takes each one from:
- BCWS comes from the baseline: the baseline cost of each task, spread over time, summed up to the status date. Without a saved baseline it is zero, and everything else with it.
- BCWP comes from the baseline multiplied by progress: by default the task’s percent complete, or the physical percent complete, a field you fill in with an estimate of the output produced instead of the time elapsed. The method is chosen per task (Task Information → Advanced → Earned value method) or as the project default.
- ACWP comes from the actual costs, which Project normally calculates by itself: actual work hours times the resource rate, plus the fixed and material costs recorded. If the resources have no rate, the actual cost is zero and CPI is undefined.
Everything refers to the status date (Project → Project Information). If it is empty, Project uses the current date, and the numbers change every day even if the plan is not touched. In File → Options → Advanced, in the section on Earned Value calculation, you choose which of the eleven baselines to use and the default method for BCWP.
A practical tip for those who do not manage costs in Project but still want Earned Value: give all resources an identical nominal rate, for example €1 per hour. BCWS, BCWP and ACWP become hours of work instead of money, the formulas stay valid and the indices measure efficiency on work. It is a legitimate use of the method, as long as you say so.
The conditions without which the numbers lie
Earned Value is a calculation, and a calculation returns what it receives. Before reading a CPI it is worth knowing whether the plan it comes from meets four conditions.
- A baseline saved at the start and not re-saved at every update. If the baseline is overwritten every month, PV follows EV and SPI is always 1 by construction. The baseline is the least known feature of Project, and the first cause of meaningless indicators.
- A plan updated with the right method. Actual dates written when they happen, progress recorded at the status date, remaining work rescheduled after it. It is the cycle described in the twin guide to this one, on how to update the plan: that one explains how the data is produced, this one how it is read. The actual dates in particular decide where ACWP ends.
- Honest progress. Percent complete is the weak point of the method, because it is an estimate. Fixed rules help: 0/100 (the task is worth zero until it is finished), 50/50, or physical percent complete for long tasks. Better a rigid rule always applied than a “felt” percentage different every time.
- A constant update rhythm. The indices make sense as a time series, not as an isolated snapshot: a CPI of 0.89 is a problem if it was 0.95 the month before and a recovery if it was 0.80. One CPI is a number; twelve are a diagnosis. The update period is agreed at the start and respected.
The limits of the method, stated
An article that lists only what Earned Value does well is advertising. Here is what it does not do.
SPI stops telling the truth towards the end. It is the weak spot seen above: EV and PV converge to the budget and the ratio goes to 1 whatever the delay. A project six months late can show SPI 0.97. For time, the index to watch is the SPI(t) of Earned Schedule.
It does not see the critical path. Earned Value weighs tasks by their cost, not by their criticality. An expensive, non-critical task running late lowers SPI without moving the project finish; a cheap, critical task running late moves it while barely touching SPI. The indices must be read next to the Gantt chart, never instead of it.
It depends on the quality of the percent complete and on a stable baseline: two conditions that in practice are often the most fragile. And it measures only what has a cost: quality, risk, client satisfaction do not enter the calculation. For those you need other project indicators, and EVM is one instrument on the dashboard, not the dashboard.
How to read it in the meeting
Three habits make these numbers useful to the people who decide.
First: look at the trend, not the value. A CPI brought to a meeting on its own generates a discussion about the number; the same CPI over a series of five updates generates a discussion about the direction, which is the one that matters. The same goes for delays: how much and in which direction are two different questions.
Second: bring the EAC, not the CPI. To a sponsor, “CPI 0.89” says little; “if we go on like this the project will cost 112,500 instead of 100,000, and to get back on budget we would have to work at 109% efficiency from tomorrow” says everything, and opens the right decision: reduce the scope, increase the budget or accept the delay.
Third: say it early. The advantage of Earned Value is that at 20% of the project it can already say how things are going, while there is still time to act. Keeping a delay to yourself in the hope of recovering it is the choice these numbers exist to make indefensible.
Frequently asked questions
Why is my BCWP zero in Project even though the tasks have progressed?
Almost always for one of three reasons: the baseline was not saved (Project → Set Baseline), the resources have no rate and therefore the baseline cost is zero, or the status date is earlier than the start of the tasks. Check in this order: BAC different from zero, baseline present in the Variance table, status date in Project Information.
Can I use Earned Value if I do not manage costs in Project?
Yes, by giving all resources the same nominal rate, for example €1 per hour. The BCWS, BCWP and ACWP fields then express hours of work instead of money, and SPI, CPI and EAC measure efficiency on work. The formulas do not change. The only thing to do is to say so to whoever reads the reports, because an EAC of 12,000 will be hours, not euros.
Percent complete or physical percent complete?
Percent complete measures the elapsed part of the duration and Project uses it by default for BCWP. Physical percent complete is a field you fill in with an estimate of how much output has been produced, regardless of time. For short tasks the first is fine; for long tasks or tasks with measurable deliveries (metres of excavation, modules released, documents approved) the second gives a much more honest earned value. The method is set per task in Task Information → Advanced.
What is the difference between SPI and Earned Schedule?
SPI compares two sums of money, EV and PV, and by construction tends to 1 as the project approaches its end, even if it is late. Earned Schedule projects EV onto the plan curve and reads at what date the plan expected that value: the difference from the status date is the delay in days or weeks, and it stays correct until the last day. For costs use CPI; for time, put Earned Schedule next to SPI.
Does Earned Value make sense on a small project or on an agile project?
On a small project yes, if it has a baseline and a periodic update: the cost of the method is almost nil because Project does the sums by itself. On an agile project the scope changes by definition and the baseline becomes unstable, which is the condition in which EVM works worst; there you use variants that measure value in story points or in features released per iteration. The principle, comparing what was done with what was planned at the same date, stays the same.
Further reading on this blog
- The plan that holds: Microsoft Project best practices, symptom by symptom — the diagnostic guide, symptom by symptom
- Project estimating methods: top-down, bottom-up and parametric
- Project dashboards: strategic, analytical, operational
- What is a baseline in Microsoft Project, when to set it, and what changes after
- How to update a Microsoft Project plan: baseline, status date and progress
- What is Earned Schedule in project control
- How to show the cost S-curve in Microsoft Project
- One CPI is a number. Twelve are a diagnosis.
- Your project delay has a direction, not just a size
- How often should you update the project plan? The duration rule and the status date
- Don’t hide the delay from your client: how to see it early, when to say it and how
- Your late tasks, in three clicks
- The work S-curve in Microsoft Project: the three fields nobody points you to
- Project costs in Microsoft Project: where the number comes from, the budget, indirect costs and the S-curve
Disclosure: this is the blog of a company that makes project-control software, so take the paragraph below for what it is. Nothing in the method above requires our tool, or any tool: BCWS, BCWP, ACWP and every index in this guide are standard Microsoft Project fields, and the Earned Value tables and report are built in from Project 2010 onwards.
If you want these indicators lined up update after update, as a series rather than a snapshot, OneClickReport reads Microsoft Project files and builds Power BI dashboards from them, so that each update adds a point to the CPI and SPI history.
#EarnedValue #ProjectControl #MSProject #EVM #EarnedSchedule