This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.
The project is accumulating delay. You see it first, before anyone else: the tasks on the critical path finish a few days later than planned, one after another, and the end-of-phase milestone moves at every update. And every time you think the same thing: “it is recoverable”. There are still seven months to go, things can be tightened, no need to alarm the client.
Then the seven months become two, the delay has not been absorbed and you have to say it right before the deadline. At that point you are no longer communicating a delay: you are confessing that you knew about it for months. The technical problem has become a trust problem, and it is the second one that cannot be recovered.
In short
- A delay kept quiet does not disappear: it grows, and every month of silence closes one recovery option. At month three you can still act on resources, sequence and scope; at month nine only the new date is left.
- The signal is there before the evidence: tasks on or near the critical path that take longer than planned for two consecutive updates. You can only see it with a saved baseline and a plan updated on a fixed schedule.
- You communicate when the trend is confirmed, not when the delay is certain: with the numbers (how much, in which direction, where it will end) and with the options, each with its cost.
- The client has in turn promised something to someone: knowing early lets them protect their own promise, and that turns the delay from a fault into a shared decision.
Why people keep quiet, and why it is mostly the young ones
Nobody hides a delay out of bad faith. They hide it out of hope: the hope, almost always sincere, that the time left will be enough to recover. And out of an understandable fear: the delay feels like a judgement on the person who reports it, and nobody wants to be the one who brings the bad news.
It is the typical attitude of project managers in their first roles. Those with a few more years behind them have been through it, have seen how it ends, and have learned the lesson the other way round: bad news given early is normal news; the same news given late is a crisis. I have been repeating it in my courses for years, and it is the advice on which I receive the most confirmations long afterwards.
What happens on the other side of the table
The client, whether an external customer or your own management, is not the end of the chain. They have promised someone, their own customer, their board, another project that depends on yours, that what you are building will be ready by a certain date. On your date they have built commitments of their own.
If they find out right before the deadline, they no longer have the time to protect those commitments: they are put in difficulty in front of their own counterparts, and they react accordingly. That is the moment the client becomes an adversary, and acts harshly towards whoever ran the project. Not because the delay is serious, but because they were denied the time to manage it. And it is understandable: in their place we would do the same.
The client does not resent the delay you told them about. They resent the time you took away from them to deal with it.

The delay shows earlier than you think
The delay that “explodes” at the end of the project was not born there. It had been visible for months in the numbers of the plan, for anyone who looked at them. The signal is precise: tasks on the critical path, or close to it, take longer than planned, and they do so regularly. One task slipping is an incident; three updates in a row in which critical tasks finish late are a trend, and the trend is what must be reported.
Seeing it requires three things, and none is optional:
- a real schedule, with links and durations, not a list of dates typed by hand;
- a baseline saved at the start, because without the term of comparison every update is a replan and the delay disappears from the numbers;
- a periodic update on a fixed schedule, with a status date and actual data: the cycle is described in the guide on how to update a Microsoft Project plan.

With these three things in place, the variance analysis is a one-minute job: the Variance table sorted by finish variance, the Tracking Gantt with the grey baseline bars under the current ones, the total slack of the critical tasks being consumed. If you want a single number you have the indices of Earned Value and, for time, Earned Schedule, which measures the delay in weeks instead of money. But the figure that decides is the direction of the delay: a delay that widens at every update is an emergency even if it is small; one that is absorbing itself is a problem that gets solved without spending. If you do not want to redo these sums by hand at every update, GanttDerivata, a tool of mine, reads the plan and shows the size and the direction of the delay over the next three weeks.
When to say it: at the confirmed trend, not at the certain delay
The question everybody asks is “how much delay is enough to talk about it?”. It is the wrong question, because it sets a threshold on size. The right threshold is on the trend: you communicate when two consecutive updates show the critical path slipping in the same direction, and the slack on the contractual milestones is being consumed.
An example with numbers. A twelve-month project; at every monthly update the critical path loses one week.
- At month three: three weeks of delay, four options. Add resources to the critical tasks; overlap tasks that were in sequence; trim the scope of an intermediate delivery; move an internal milestone without touching the final one.
- At month six: six weeks, two options. Reduce the scope, or renegotiate the date.
- At month nine: nine weeks, one option. The new date, announced from a position of weakness.
The delay is the same phenomenon in all three cases. What changes is how much time you left the client to decide.
Saying it at month three may seem premature, and sometimes the delay really does absorb itself. But communicating a trend together with the options to correct it is not alarmism: it is the difference between a project manager who controls the project and one who suffers it. The client understands, and next time trusts you more, not less.
How to say it: five lines, numbers and options
The communication that works has a fixed structure and fits in half a page:
- the fact, with the numbers from the plan: by how much the critical path slips, since when, in which direction;
- the cause, without looking for culprits: an optimistic estimate, a late supply, a resource shared with another project;
- the impact if nothing changes: the new finish date and, if any, the cost to complete;
- the options, two or three, each with its price in time, money or scope;
- the request: which decision is needed from the client, and by when, because the options have a deadline too.

Three things not to write. “We expect to recover”: if you had a plan to recover you would already have put it among the options, with its cost. “The delay is due to…” followed by a name: the cause is for choosing the remedy, not for handing out blame, and the client knows it. And “we will keep you posted”: the update already has an agreed date, and the delay is measured again at the next one, with the same numbers.
Contracts ask for it more and more often
One thing has changed compared with a few years ago: more and more clients require, and write it into the contract, that the supplier keeps a schedule, updates it on a fixed cadence and delivers it periodically. It is not bureaucracy: it is how the client buys the time to react. A schedule updated every month makes it impossible to keep a delay quiet, and this protects both parties, the supplier included, who at that point has a certain date on which the delay was declared.
The frequency is agreed at the start: weekly for short or critical projects, fortnightly or monthly for long ones. How to choose the update period is a separate article; here it is enough to say that the period must be respected even when the news is bad, indeed especially then. Skipping an update because “there is nothing new to say” is the first step towards the delay kept quiet.
The opposite case: when it is not the time to raise the alarm
Not every slip is news. A task off the critical path that finishes late within its slack moves nothing, and reporting it as a delay trains the client not to listen. A swing of a few days on a single update, with no trend, is noise. The criterion stays the one above: on or near the critical path, confirmed trend, slack on the milestones being consumed. If even one of the three is missing, you note it down and wait for the next update. Communicating everything is the same as communicating nothing.
Frequently asked questions
How much delay is “significant”?
There is no percentage valid for everyone. A delay is significant when it consumes the slack of the contractual milestones and repeats in the same direction for two consecutive updates. On a one-year project it may be two weeks; on a construction site with daily penalties, two days. The threshold should be decided at the start with the client and written into the communication plan, so that when the moment comes there is no debate about whether it is worth mentioning.
What if the client reacts badly anyway?
They will react badly, sometimes: it is bad news. But they react to the delay, not to you, and the next day they have options to choose from and the time to do it. The reaction to a delay discovered right before the deadline is of a different nature: it hits the person, not the problem, and it lasts beyond the project. Of the two, the first is the one you can bear.
Should I tell my manager first or go straight to the client?
Your manager first, always, and on the same day. Not to cover yourself, but because some options, adding resources, renegotiating the scope, are theirs to decide. Presenting them the communication already structured in the five lines keeps the conversation short and takes it straight to the options. Then the client, with your manager informed or present.
What if the delay is caused by the client themselves?
You communicate it the same way and with more urgency, because the variation must be documented as it happens, not reconstructed afterwards. The updated plan with the saved baseline is the evidence: it shows the date on which an approval or a supply from the client was expected and the date on which it arrived, and the effect on the critical path. It is exactly the case in which you save a numbered baseline before rescheduling, as described in the guide on updating the plan.
How do I document the communication?
In writing, with the date, attaching the updated plan or an extract of it: the Variance table or the Tracking Gantt at the status date. The five lines in an email are enough. What matters is that a dated trace exists, because it is that trace which, months later, distinguishes a declared delay from a delay kept quiet.
How do I see the direction of the delay without redoing the sums at every update?
By hand, you compare the Variance table of two consecutive status dates: if the finish variance of the critical tasks grows, the delay is widening. Alternatively GanttDerivata, a tool of mine, reads the .mpp file with no Microsoft Project installation required and shows how far the critical path has slipped and whether the delay is growing or shrinking, focusing on the next three weeks. The method is the same as in this article; the only difference is that it does the sums for you.
This article is part of two guides on this blog
Disclosure: this is the blog of a company that makes project-control software, so take the paragraph below for what it is. Nothing in the method above requires our tool, or any tool: a saved baseline, the Tracking Gantt and the Variance table are standard Microsoft Project, and the five-line message is written by hand.
If you want the size and the direction of the delay at every update without redoing the comparison yourself, GanttDerivata reads the .mpp file and shows how far the critical path has slipped and whether the delay is growing or shrinking over the next three weeks.
#ProjectManagement #Delay #MSProject #ProjectControl