How to show the cost S-curve in Microsoft Project

The cost S-curve in Microsoft Project: cumulative cost of a construction job in June, September and December

Every project manager learns to read a Gantt chart early. Almost nobody learns to read a cost S-curve — which is the chart the finance side actually uses to decide whether a project is affordable. The good news is that Microsoft Project draws it for you, and hardly anyone asks it to.

This guide shows how to get the cost S-curve in Microsoft Project, how to tell it apart from the chart that looks almost the same but means something else, and how to read it once you have it.

What an S-curve actually is

An S-curve is the cost of the project added up period after period: this month’s cost plus everything spent before it. The name comes from the shape. Spending starts slowly, because few resources are on site and you are still setting up; it accelerates once the work is in full swing; it flattens at the end, when what is left is finishing, testing and handover. Plotted over time, that story draws a stretched S.

The “period” is yours to choose: it is the interval at which you control the project. If you review it monthly, the period is the month; on a fast job it may be the week.

Why finance asks for it before the project manager does

A project manager thinks in dates: this task finishes on the 14th, that one slipped three days. Whoever pays thinks in cash: how much goes out this month, how much next, when the credit line is needed. Two different languages — and the S-curve is where they meet.

A Gantt chart tells you when the work happens. An S-curve tells you what it costs, and above all when the money leaves.

That is why finance and administration ask for it when they build medium and long term liquidity forecasts. They do not care which activity ends on the 14th; they care how much has to be in the bank in June.

Before you start

  • Microsoft Project desktop. The steps below are the same in Project 2010, 2013, 2016, 2019, 2021, 2024 and in Microsoft 365: the icons changed, the route did not.
  • Resources with cost rates. The curve is built from resource costs, so resources with no standard rate contribute nothing and the curve stays flat at zero.
  • A saved baseline, if you also want the comparison in the last section. Without it there is nothing to compare today’s spending against.

The six steps

  1. Open the plan and go to View → Resource Sheet.
  2. Still on the View tab, in the Split View group, tick Details. The window splits in two.
  3. Click in the top pane and press Ctrl+A to select every resource.
  4. Click in the bottom pane and choose View → Resource Graph.
  5. Right-click inside the graph and choose Cumulative Cost.
  6. Right-click again, choose Bar Styles, and under Selected resources set Show as: Line.

Then set the time base: View → Timescale, and pick days, weeks or months. The curve redraws itself — it is the same data read at a different step.

Step 6 is the one almost everyone skips. Without Show as: Line the graph stays a set of bars: the numbers are already right, but the S shape does not appear, and the shape is what communicates.

“Cost” and “Cumulative Cost” are two different menu entries

In the right-click menu the two sit next to each other, and they are easy to confuse. The difference shows at a glance: the cost of the period goes up and down, the cumulative cost only goes up. If your chart drops at any point, you are not looking at an S-curve.

Monthly cost as bars and cumulative cost as a line: the S-curve of the same nine months of a construction job
The bars are what each month costs, the line is the running total. In June the bar drops; the line does not.

The figures above are real, taken from a construction job. In May the month costs € 132,128; in June it drops to € 65,538, and the bar comes down with it. Over the same step the cumulative line still climbs, from € 203,081 to € 268,619, because money already spent does not come back. By December the job has absorbed € 3,635,186.

One curve tells you nothing. Two do

On its own, the budget S-curve is a forecast: it says what you expected to spend. It becomes a control instrument when you put the actual curve next to it. That is why saving the baseline before the work starts (Project → Set Baseline) is worth the ten seconds it takes: skip it, and halfway through you will have nothing to compare against.

Baseline S-curve and actual cost curve compared at today, showing the gap in money and the gap in time
With two curves the distance reads in two directions: vertically in money, horizontally in time.

With two curves, read at today’s date, you get two distances. The vertical one is money: how much more, or less, you have spent than planned. The horizontal one is time: how long ago the project should have reached the level of spending it has only reached now.

And this is where the most common misreading hides. An actual curve below the baseline looks like good news, and it rarely is: usually it does not mean you are saving money, it means you have not yet done the work you should have done by now. The saving is apparent; the delay is real. On measuring that delay in weeks rather than in euros, there is a separate article on Earned Schedule.

From 2013 there is also the report route

The Resource Graph is built for looking, not for printing: it lives inside a split window, and getting it out of Project is awkward. From Project 2013 onwards there is a Report tab, and in the Costs group you will find ready-made reports — Cost Overview and Cash Flow — that refresh themselves and paste into a slide.

The rule of thumb is simple: the Resource Graph is for you while you work, the Reports are for when you have to show something to somebody else. And if you need the raw numbers, Visual Reports exports them to Excel.

If something goes wrong

  • You see bars instead of a line. Step 6 was skipped: open Bar Styles and set Show as: Line under Selected resources.
  • The curve goes down somewhere. You picked Cost instead of Cumulative Cost. They are adjacent entries in the same menu.
  • The curve is flat at zero. Either the resources carry no standard rate, or the money in your plan sits in task fixed costs, which are not resource costs and never reach this graph.
  • Only one resource shows up. The selection in the top pane was lost. Click in the top pane, press Ctrl+A, and check that Selected resources — not Resource — is the column you styled.

Frequently asked questions

Can I get the S-curve of work instead of cost?

Yes. In the same right-click menu, choose Cumulative Work instead of Cumulative Cost: you get the same curve expressed in hours. It is useful when rates have not been loaded yet, or when you would rather not circulate costs.

Are task fixed costs included in the curve?

No, and this is the expensive trap. The Resource Graph adds up resource costs: a fixed cost attached to a task belongs to no resource and stays out of the total. If your plan uses them, build the complete curve from the Task Usage view instead, adding the Cumulative Cost field to the timephased details.

Can I export the curve to Excel?

Yes, through Visual Reports, which hands the timephased cost data to Excel as a PivotTable. From there the cumulative series is one running-total column away.

My curve is not S-shaped. Am I doing something wrong?

Probably not. If the project is short, or resources are loaded flat from start to finish, the cumulative line comes out nearly straight — it is correct, that project simply has no ramp-up phase. The S appears when effort grows and then tapers. And if you are looking at part of the timeline only, you are seeing part of the S.


A note on who writes this. Project Edge Tools builds desktop apps for the work Microsoft Project leaves to you; OneClickReport takes a plan into Power BI, where a cumulative cost series becomes a chart you can share instead of a window you have to screenshot. The method above needs none of that — it is plain Microsoft Project.

The spark for this article was a 2012 note on a piece by Calvin Jones, published on HubPages, about the use of S-curves in construction projects.