The one-week test: does your construction schedule calculate, or is it drawn?

The one-week test: add five days to one task halfway through the schedule; in a calculated schedule the handover moves, in a drawn one it does not

This article is part of the guide The plan that holds: Microsoft Project best practices, symptom by symptom, nineteen things you can see in a plan and the move that reveals each one in thirty seconds.

The construction schedule is attached to the contract, and at every progress claim someone updates it: they move the bars of the late tasks, adjust a few dates, and send it back to the owner’s representative. The handover date, meanwhile, stays where it was. It stays there for months, until two progress claims before the end the numbers stop adding up and the date slips all at once, when there is nothing left to decide.

It is a typical story, and it is rarely the fault of whoever does the updating. It is the schedule that cannot do its job. To check a construction schedule from this angle you need neither software nor an expert: a five-minute test is enough, and it works on any schedule, including the ones other people send you.

In short

  • Add one week to a task halfway through the schedule and watch what happens after it: in a schedule that calculates, the following tasks and the handover move on their own.
  • If nothing moves, it is a drawing: every date was typed by hand, and the schedule has no way of noticing a delay.
  • It is not about the software: an Excel sheet built with formulas passes the test, a Microsoft Project file with typed dates may fail it.

How to check a construction schedule in five steps

  1. Work on a copy. Leave the real schedule alone: save a duplicate and run the test there.
  2. Pick a task halfway through, one that has not started yet and sits on the way to the handover. The second-floor partition walls, for example: after them come the MEP rough-in on that floor, then plastering, finishes, handover.
  3. Add five working days to it, one week on site. Change its duration and nothing else.
  4. Look first at the tasks right after it, then at the end. If the tool needs you to recalculate, recalculate before you look.
  5. Throw the copy away. The test was there to tell you something, not to change the schedule.
Two construction schedules side by side: in the calculated one, a task that gets longer pushes every following task and the handover; in the drawn one, the other bars stay put and the handover does not change.
The same test on two schedules. At the top the tasks are linked and the handover slips by a week; at the bottom the MEP rough-in lands on top of the partition walls, and the handover still looks on time.

How to read the result

What you seeWhat it means
Nothing movesIt is a drawing. The dates were typed by hand, one by one.
Everything moves, all the way to the handoverThe schedule calculates. The delay reaches where it should.
The following tasks move, but not the handoverThis one calculates too: that task had float, more than a week of slack before it touches the end. Run the test again on another task.
It moves up to a point, then stopsThe chain is broken. From that point on there is a typed date, or a task that does not say what it comes after.
The four outcomes of the one-week test.

The last row is the most interesting one, because it also tells you where to look: the first task that did not move is where the schedule stops calculating.

Why one schedule calculates and another does not

A construction schedule calculates when every task says what it comes after: the second-floor MEP rough-in after the second-floor partition walls, plastering after the rough-in. With these links nobody writes the start date of a task: it is the result of what comes before. Make the partition walls longer, and the rough-in starts later on its own, because its date depends on when the partition walls finish.

In a drawn Gantt chart the date is an input, not a result. Someone put each bar in its place, and there it stays. The delay is real, but the schedule has no way of knowing it: whoever updates it has to remember to move everything that comes after by hand, and sooner or later they will not.

This is why the test is not about the tool. An Excel sheet where the start date of each row is a formula based on the finish of the row before passes the test: it is awkward to maintain, but it calculates. A Microsoft Project or Primavera file where the dates were typed in and the tasks are not linked fails it: it looks like a serious schedule, and it is a drawing.

The risk is not that the job runs late. It is that the schedule keeps showing the handover on the right date when it no longer is.

In Microsoft Project, step by step

  1. File > Save As, and save a copy of the file.
  2. In the Gantt Chart table, in the Duration column of the task you picked, add five days: from 10 days to 15 days, for example.
  3. Look at the Start and Finish columns of the rows that come after it, all the way to the handover.

If the dates do not move, in Project the cause is almost always one of three:

  • Calculation is off. Under File > Options > Schedule, Calculation can be set to Off, and then Project recalculates only when you press F9. Before you conclude that the schedule is a drawing, press F9 and look again.
  • The tasks are manually scheduled. A manually scheduled task stays where you put it: even if its predecessor finishes later, its start date does not change. The Task Mode column shows them.
  • The dates were typed by hand. When you type a start date into an auto-scheduled task, Project sets a Start No Earlier Than constraint. That constraint does not stop the task from slipping later, but if the task has no predecessor, there is nothing upstream to push it. The Must Start On and Must Finish On constraints, on the other hand, keep the task on its date even when the predecessor is late. The Constraint Type column lets you count them.

How to count and fix them, symptom by symptom, is in the guide The plan that holds.

What the test does not tell you

The test tells you whether the schedule calculates, not whether it is right. A schedule can move the handover perfectly and still have made-up durations, a wrong sequence, or a single crew that would need to be in three places at once. Those are different checks, and each one has its own question.

And one test is not enough. On a long schedule, repeat it on two or three tasks in different parts of the job: in the foundations, halfway through the structure, in the finishes. A schedule can calculate well in its first half and turn into a drawing in the last one, the part that was added in a hurry before the bid.

Frequently asked questions

Does it work for Primavera P6 and other scheduling tools?

Yes. The test only asks you to change a duration and look at what happens next: you can run it with any tool. If the tool recalculates only on command, recalculate before you look.

Can I run it on a schedule built in Excel?

Yes, and that is where it gives the clearest answer. If the dates are typed into the cells, nothing moves. If the start dates are formulas that depend on the finish of the rows before, everything that depends on the row you changed moves.

The schedule is attached to the contract: am I allowed to change it?

The test does not change it: you run it on a copy, and you throw the copy away. The contract schedule stays as it is.

How often should I repeat it?

When you receive a schedule from a contractor or a subcontractor, before you trust its dates, and after every major revision of your own. You do not need it at every progress claim: if the schedule calculated last month and nobody has retyped the dates, it still calculates.

Do the causes described for Project apply to every version?

The test applies to all of them. Of the three causes, calculation turned off and constraints were already there in Project 2007; manually scheduled tasks arrived with Project 2010.


The same checks as a one-page sheet to keep next to the keyboard: the Microsoft Project plan review checklist.

Would your construction schedule pass the test today?

#ConstructionManagement #Scheduling #MSProject #ProjectControl