Comparing top-down and bottom-up estimates in Microsoft Project

The build phase estimated twice, top-down in January and bottom-up in March, with the thirty per cent gap between them

This article is part of the guide Project estimating methods, which covers top-down, bottom-up and parametric estimating and when each one stops working.

In January you said the build phase would take four months. In March the team decomposed the work and estimated the individual tasks. The two numbers do not agree, and the question is by how much. Comparing top-down and bottom-up estimates is the check that answers it.

Almost everybody answers with a spreadsheet. There is no need: Microsoft Project puts the two estimates on the same Gantt bar, one above the other, and colours the difference. It is the cheapest check that exists on a project’s estimates, and it takes two minutes to set up.

In short

  • An estimate can only be checked by a different method. Adding up the phases of a top-down number returns the top-down number.
  • The mechanism is manual scheduling on the summary tasks only: the detail stays automatic, the phase accepts a typed duration.
  • The bar then splits: your phase estimate above, the roll-up of the detail below, with the overrun coloured.
  • Finding the summary tasks quickly: add the Summary column, filter on Yes, select them all at once. The same filter puts them back.
  • The number alone says nothing. What matters is the sign of the gap — and a detail estimate that comes out shorter is the one to worry about.

Why top-down and bottom-up estimates have to be compared

An estimate can only be checked with a method other than the one that produced it. Adding up the phases of a top-down estimate to verify it is a circular confirmation: you recover the number you started from.

The comparison with bottom-up, on the other hand, puts two genuinely independent things side by side: a whole-project judgement made with little information, and a sum of details made with a lot. When they disagree, the gap always has something to say.

How to set it up, inside the Gantt

The mechanism uses something in Project that almost nobody touches: manual scheduling applied to the summary tasks only.

  1. The detail tasks stay automatically scheduled, carrying the durations from the bottom-up estimate. That is the normal plan.
  2. The summary tasks switch to manually scheduled. From that moment they stop calculating themselves and accept a duration typed by hand.
  3. On the phase you type the top-down duration, the one you estimated from above months earlier.
The split summary bar in Microsoft Project: the manually typed top-down duration above, the roll-up of the detail tasks below, and the overrun coloured
One bar, two estimates. The overrun is visible from across the room, without reading a number.

The result is a bar split in two: your phase estimate above, the roll-up of what is actually inside below. When the detail overruns, Project colours the excess part, and the discrepancy can be seen from three metres away without reading a number.

It is a documented feature, not a trick: Microsoft calls it top-down planning and describes exactly this behaviour of the split bar.

The quick way to find the summary tasks

On a two-hundred-line plan, switching the phases by hand is tedious work full of mistakes. The field you need already exists.

  1. Insert the Summary column into the table; it reads Yes or No.
  2. Open the autofilter on the column header and leave only Yes ticked: the summary tasks are the only rows left on screen.
  3. Select them all together and change the scheduling mode in one go.

When the comparison is done, the same filter puts them all back to automatic. It is a reversible operation, which is the reason it is worth trying at all.

Reading the gap: four cases

The number on its own says nothing. What matters is the sign of the gap and its size.

Four ways the gap between a top-down and a bottom-up estimate can read, and what to do about each one
Four gaps, four different things to do. The third one is the case that looks like good news.
  • The detail overruns slightly (under 10%). This is the normal, healthy case: the estimate from above was good and the detail refined it. Update the phase and move on.
  • The detail overruns a lot. Either scope grew while nobody was watching, or the top-down estimate was optimistic. Those are two different problems and they need separating before you touch the dates: in the first case you renegotiate, in the second you learn something.
  • The detail is much shorter. The case that looks like good news and almost never is. It usually means something has not been decomposed: testing, data migration, training. Before celebrating, go and look for what is missing from the list.
  • They match exactly. Suspicious. If the bottom-up was done by somebody who knew the top-down number, this is not a check: it is an alignment. Independent estimates almost never coincide.

What to do with it afterwards

Comparing top-down and bottom-up estimates is not about deciding who was right: it is about bringing into the open a difference that would otherwise stay implicit until halfway through the project. Once you can see it, there are three honest exits: accept the new number and renegotiate the date, cut scope until it fits again, or declare the difference and carry on knowing you have an open risk.

What is not an exit is switching everything back to automatic and never mentioning it: the red bar disappears, the difference does not.

Frequently asked questions

Does putting the phases into manual mode ruin the plan?

No, and it is reversible: the Summary column with the filter lets you select every phase together and put them back on automatic when you have finished. While they are manual, though, the phases do not update themselves: it is a comparison mode, not a daily working mode.

What exactly does the split bar show?

The upper part is the duration you typed on the phase, which is the top-down estimate. The lower part is the real extent of the tasks it contains, which is the bottom-up result. The coloured portion is the difference between the two.

Does the comparison work on effort as well as durations?

On the Gantt you see durations. For effort the comparison is done on the Work field, which unlike duration really does add up through the structure: the duration of a phase is the distance between the first start and the last finish, not the sum of the durations underneath.

How often is it worth redoing the comparison?

Every time scope changes significantly, not on a calendar. A comparison run on a plan nobody has touched since last time returns the same gap as before and teaches you nothing.

The starting point for this technique came from an article by Tensix.


Disclosure: this is the blog of a company that makes project-control software. Nothing above needs our tools: the split bar is a feature of Microsoft Project itself, and the whole comparison is two minutes of setup.