Sending the plan out is the easy half. The hard half is collecting the actuals: the dates a task really started and really finished, and how much work is genuinely left. Those numbers exist only inside other people’s heads, and they go stale within days.

This article is about getting those numbers out of people. It is the return path, one of the four directions a plan has to travel in project planner tools: what you need besides Microsoft Project. What to do with the numbers once you have them, in the right order, is a separate job covered in updating a Microsoft Project plan.
In short
- Ask for three things: actual start, actual finish, and how many hours are left. Nothing else.
- Stop asking how far along people are. A percentage is an opinion; remaining work is an estimate you can act on, and it is the one that moves the finish date.
- The cost per person has to be measured in seconds. Anything requiring a login gets done late, then not at all.
- Approve before writing. Numbers that go straight into the plan arrive already recorded, which makes the errors invisible.
- The date of the cycle never moves. That is what makes one period comparable with the next.
The three numbers, and the one to stop asking for
Almost every progress conversation opens with the same question: how far along are you? It feels like the right question and it is the wrong one, for a reason worth understanding rather than memorising.
A percentage is a judgement about the past. It compresses what has been done into a single number that nobody can verify, and it is systematically optimistic: the last ten per cent of almost any task holds more than ten per cent of the work. Worse, a percentage says nothing about the future, and the future is the only thing a plan is for.
What you need instead is three things:
- Actual start. The day the task really began. It anchors the task to reality and stops the plan sliding it around.
- Actual finish. The day it really ended, for tasks that are done. It closes the matter.
- Remaining work. How many hours are still needed. This is the number that matters, because it is the only one that changes the finish date.
“Eighty per cent done” and “two days left” sound like the same statement. Only one of them can be wrong in a way you can see next week.
There is a practical bonus. Asking for remaining work changes the conversation from defending the past to estimating the future, and people are noticeably more honest about the second. Nobody likes admitting they are behind; almost everybody will tell you a task needs three more days if the question is simply how many days it needs.
One distinction to keep straight if you do use percentages for reporting: in Microsoft Project, % Complete measures elapsed duration while % Work Complete measures hours done. They answer different questions and they rarely agree.
The cycle, in five steps
Whatever route you choose, the shape is the same, and it repeats on a date that does not move.

Step four deserves the emphasis. Somebody will report a task finished that is not finished, and somebody will forget a whole week and report nothing. Both are normal. What is not normal, and what causes real damage, is letting those numbers land in the plan unreviewed: once written, they look exactly like the correct ones.
Four ways to collect, and what each one costs
These are the routes people actually use. None of them is wrong; they simply break at different sizes.
Notice what the first three have in common. They all collect information successfully, and they all leave the translation on the planner: reading fourteen replies, working out what each person meant, and typing it in. That translation is where the hours go, and it is what scales badly.
The four rules that decide whether any route works
- The date never moves. Same day, same time, every period. A cycle that slips by two days once will slip by a week within a month, and the series stops being comparable. Choosing the period matters less than never moving it.
- Seconds per person, not minutes. Two dates and a number, in something already open on their screen. If it requires logging into a system, opening a tool or remembering a password, it will be done late and then not at all.
- One shape for everybody. The same columns, in the same order, every period. This is what makes the returns mergeable without reading them one by one.
- Approve before writing. Look at what came back, question what looks wrong, then write. Five minutes here saves the meeting where somebody says the plan is wrong and is right.
There is a fifth rule that is not about mechanics: tell people what happened to their numbers. A team that never sees the consequence of reporting stops reporting carefully. Showing the updated plan, even briefly, is what turns the cycle from an administrative tax into something people can see the point of; an operational dashboard is one way to make that automatic.
What this does not solve
- A culture where admitting a delay is unsafe. If reporting bad news gets punished, you will receive optimistic numbers forever, collected very efficiently. No cycle and no tool fixes that; it is a management problem and it has to be solved as one.
- A plan that is too coarse to report against. If a task is eight weeks long, “remaining work” is a guess for seven of them. The fix is in the plan, not in the collection: tasks short enough that the answer is observable.
- Estimates that were wrong from the start. Collecting actuals tells you the truth sooner. It does not make the original number better, and it does not choose the corrective action for you.
- The very small project. Four people who talk every day do not need a cycle. They need the planner to listen on Friday and write it down.
If something goes wrong
- Dates move backwards after you enter progress. Almost always the status date is not set, or it was set after the actuals were entered. Set it first, enter the actuals second, and then check that unfinished work has been pushed beyond it rather than left sitting in the past.
- The returns stop coming after three or four periods. Look at the cost per person before blaming the team. If filling it in takes five minutes, five minutes is the reason. If it takes twenty seconds and it still stops, the reason is that nobody ever saw what their numbers were used for.
- Two people report the same task. A task with two owners has no owner. Split it, or name one person responsible for reporting it, and say which.
- Somebody reports a task complete and it reappears next period. This is the case step four exists for. When it slips through, do not silently correct it: go back and ask, because the same misunderstanding will repeat.
Frequently asked questions
How often should I collect actuals?
Weekly suits most projects with tasks of a few days each; fortnightly or monthly suits long engineering or construction work. The frequency matters far less than keeping it fixed: a series collected every Monday is comparable period to period, while one collected whenever there is time is a set of unrelated snapshots.
Why not just ask for percent complete?
Because a percentage is a judgement about work already done, and it is systematically optimistic. Remaining work is an estimate about the future, it can be checked against reality next period, and it is the number that actually moves the finish date. If you need a percentage for reporting, derive it rather than asking for it.
Do I need the team to have Microsoft Project?
No, and it is usually a mistake to give it to them. People filling in two dates and a number need a format they already know how to open, not a scheduling tool. Sending the assignments out is the other half of this cycle, covered in emailing each person their tasks without Project Server.
Should the team write straight into the plan?
It removes your typing and it removes your review at the same time, which is a bad trade. Errors that arrive already recorded are invisible: they look identical to correct data. Keep the approval step, even when it is fast.
What if somebody simply does not report?
Leave the gap visible rather than filling it with an assumption. A task marked as not reported is information; a task quietly rolled forward with invented numbers is an error that compounds every period. If the same person is missing three periods running, that is a conversation, not a data problem.
Disclosure: this is the blog of a company that makes project-control software, so take the paragraph below for what it is. Nothing in the method above requires our tools, or any tool: on one project, a spreadsheet with the same four columns every week and five minutes of review covers all of it.