Bottom-up estimating: forty honest estimates, one optimistic total

Forty bottom-up estimates add up to fourteen months while the project actually takes eighteen: the optimism gap

This article is part of the guide Project estimating methods, which covers top-down, bottom-up and parametric estimating and when each one stops working.

Forty tasks, forty bottom-up estimates, each one made with the person who will actually do that piece. You add them up: fourteen months. It is the most accurate number bottom-up estimating can produce, and it cost three weeks of meetings.

Then the project takes eighteen. Not because one of the forty estimates was wrong — taken one at a time almost all of them were reasonable — but because of how forty estimates behave together. That is the structural flaw in bottom-up estimating, and it is in none of its lines.

In short

  • Two things make it the most accurate method: the person who knows does the estimating, and each piece is small enough to picture whole.
  • It is expensive, and the cost is why it belongs late: on moving scope you will simply do it twice.
  • Every line carries a small optimistic shortfall. They have the same sign, so they accumulate instead of cancelling.
  • Precise does not mean unbiased. That is the whole sentence you need to remember about bottom-up.
  • Three defences: ask for three numbers, compare against a different method, and put the reserve where it can be seen.

What bottom-up estimating is, and why it is the most accurate

You start from the bottom. The work is decomposed down to the level where a single piece is small enough to be estimated by one person, the one who will do it. Every piece gets its duration and its effort, and then it is all added up back through the structure.

The accuracy comes from two things the other methods do not have: the person who knows does the estimating, and each piece is small enough to be pictured whole. When somebody says “three days” about a thing they have already done eight times, that number is worth something.

There is also a side effect that is worth the ticket price on its own: decomposing the work surfaces the tasks nobody had thought about. Half the value of a bottom-up estimate is not in the number, it is in the lines that appear while you are making it.

It costs, and the cost is why it belongs late

Three weeks of meetings are three weeks of the people you were hoping were building something. And if scope moves, the estimate is done again from scratch: the second pass costs as much as the first.

Which is why bottom-up belongs to the narrow part of the cone, once the big decisions have been taken. Doing it earlier does not make it more accurate: it only makes it more expensive, because you will do it twice.

The trap: forty optimisms that add up

Here is the flaw that no single line reveals.

Forty task estimates each carrying a small optimistic shortfall with the same sign: errors that accumulate instead of cancelling out
Random errors cancel. These are not random: they all lean the same way.

Every estimate is made by a person picturing the version where nothing goes wrong: nobody interrupts them with other questions, the test environment is free, the data arrives clean. And it is made by a person who wants to be seen as capable, which does not help anyone say large numbers.

Taken on its own, each of those estimates is defensible: the shortfall is small, maybe half a day. The problem is that the shortfalls all have the same sign. They do not cancel the way random errors would: they pile up on the same side, and the total slides in a way no single line let you predict.

Precise does not mean unbiased. Bottom-up is the most precise estimate you have, and at the same time the one that inherits, in one block, the optimism of everybody who contributed to it.

Three ways to defend yourself

  • Ask for three numbers, not one. Optimistic, expected and pessimistic. Not so much for the weighted average that comes out of them, but because the question “and if it goes badly?” forces people to picture the scenario nobody pictures unprompted.
  • Compare against a different method. If bottom-up comes out shorter than the top-down estimate made months earlier with far less information, you are not looking at an improvement: you are looking at the sum of the best cases.
  • Put the reserve where it can be seen. An explicit reserve, with a name and an owner, is honest and can be argued about. Padding spread inside the forty durations is neither, and it disappears at the first request to shorten the plan.

And inside Microsoft Project?

Bottom-up is how Project thinks natively: summary tasks are not estimated, they are calculated from what sits underneath. You enter the durations at the lowest level and the phase forms itself.

Two things are worth knowing. First: the duration of a phase is not the sum of the durations of the tasks inside it, but the distance between the start of the first and the finish of the last — if two tasks run in parallel, the sum of the durations and the duration of the phase do not match, and that is correct. Anyone who wants a sum should look at Work, which does add up.

Second: to hold the three numbers of a three-point estimate you need three custom duration fields and a formula for the weighted average. The PERT analysis that used to do that arithmetic for you left the product with Project 2010, even though the field documentation is still online. The how-to is in the parent guide, project estimating methods.

Frequently asked questions

How small does a task have to be to be estimable?

Small enough to be pictured whole by one person. The practical test is that whoever is estimating it can tell you how they will do it: if the answer has to be “it depends”, the piece is still too big and needs decomposing.

Why does bottom-up often come out shorter than reality?

Because every estimate pictures the scenario in which nothing goes wrong, and forty shortfalls with the same sign do not cancel: they add. It is a systematic bias, not an oversight, which is why it cannot be fixed by asking for “more serious” estimates.

Is the duration of a phase the sum of the durations of its tasks?

No: in Microsoft Project it is the distance between the start of the first task and the finish of the last. With tasks in parallel the two numbers differ, and that is correct. If you need a total that adds up, look at the Work field.

Should I add a margin to every task?

No. A margin hidden inside every duration is invisible, therefore not discussable, and at the first request to shorten the plan it disappears without anybody knowing how much is left. An explicit reserve, with a name on it, can be defended in a meeting.

Do I still need a top-down estimate if I have done bottom-up?

Yes, if you already have one: comparing them is the cheapest diagnostic there is. A large gap is telling you something — about scope that has changed, or about the optimism of the individual lines — and either way you want to know before you sign up to the date.