The analytical project dashboard: five reports and the drill-down

The analytical project dashboard answers the question why: from the aggregate number, nine per cent over budget on the portfolio, down to three quarters from one phase and two testing tasks

This article is part of the guide Project dashboards: strategic, analytical, operational, which covers the three types and how to choose between them.

The strategic page says the portfolio is nine per cent over budget. That is a fact, and it is useless on its own: it does not tell you which project, which phase, which task, or what to do about it tomorrow morning. Getting from that number to something you can act on is the whole purpose of the analytical project dashboard.

It is also the dashboard people confuse most often with the other two. It is not a strategic page with more rows, and it is not an operational page with charts. It has its own reader, its own moment, and one function the other two do not have: drill-down.

In short

  • The analytical project dashboard answers why we are here. Its reader is the project manager, the PMO, the controller: whoever has to explain a variance and choose the corrective action.
  • You read it before the meeting, not during it. That is the practical difference from the strategic page, which is built to be looked at in the room.
  • Drill-down is what defines it: portfolio, then phase, then task and resource. A page that stops at the second level is a strategic page with more rows.
  • Five reports carry it: variances, indicator trends, issues with their causes, Earned Value and milestone status.
  • It needs one condition the others do not: continuity of readings. A missing period declared is information; a missing period passed over in silence is an error.

Who reads it, and when

The reader is whoever has to account for a number. Usually the project manager, often the PMO, sometimes a controller who needs to understand a cost line before signing it off. What they have in common is that they will be asked a question they cannot answer with a colour.

The moment matters as much as the reader. The analytical dashboard is consulted before the meeting, while you are working out what you are going to say, and again afterwards when you are chasing down something that came up. Projecting it on a screen during the meeting is the most common way to waste it: it is built to be explored by one person with half an hour, not read by eight people in ninety seconds.

Its update rhythm follows the reporting period rather than the calendar. Every time the plan is updated, the page has something new to say; between updates it says nothing new, and refreshing it more often only adds noise.

The five reports

Each one closes a question that somebody will actually ask. That is the test: if a tile closes no recurring question, it comes off the page.

  1. Cost and schedule variances. Closes “where did we drift from the plan?”. A filterable pivot table, or bars sorted by variance so the biggest gaps come first. It requires a saved baseline: without one, every variance on the page is zero or invented.
  2. How the indicators move over time. Closes “are we getting better or worse?”. Lines over the reporting periods, with milestones and corrective actions marked on them, so you can see whether an action had any effect. Needs at least three readings before it says anything.
  3. Issues, with their causes. Closes “where does the problem start?”. A table with drill-down, plus a view of how issues concentrate by area. This is the report where drill-down earns its keep, and the one most often left out.
  4. Earned Value. Closes “what will finishing cost at this rate?”. A table of indices per project with bars marking the ones outside threshold. Without a baseline the indices are arithmetic on nothing; the guide to PV, EV, AC, SPI and CPI covers how they are built.
  5. Milestone status. Closes “do the dates that matter still hold?”. A Gantt trimmed to the milestones, or a status table. Keep contractual and internal milestones apart: mixing them makes the contractual ones look negotiable.
Five reports of the analytical dashboard and the question each one closes: cost and schedule variances, how indicators move over time, issues with their causes, Earned Value and milestone status
Five reports, five questions. If a tile closes no recurring question, take it off the page.

Drill-down: the function that defines it

Take the nine per cent from the opening. On the first level it is a portfolio fact and nothing more. Drop a level and you find that three quarters of the overrun comes from one phase, testing, on one project. Drop again and you are looking at two specific testing tasks, one started and one not, sharing a resource who is also committed to another project.

Only the third level is actionable. You cannot do anything about “nine per cent”; you can do something about a shared resource on two testing tasks. A page that does not reach that level is a strategic dashboard with more rows, and it will produce meetings where everyone agrees there is a problem and nobody knows what to change.

Drill-down in three levels: the portfolio says nine per cent over budget, the phase level says three quarters comes from testing, the task level names two testing tasks and the shared resource
Three levels. The aggregate number says there is a problem; the third level says what to act on tomorrow morning.

Two practical notes. The first: the problem is nearly always concentrated in one place. People expect an overrun to be spread evenly and are surprised when it is not, which is exactly why the second level is worth building. The second: drill-down has to be real navigation, not three separate pages someone has to remember to open. If getting to the third level means opening a different file, it will not happen during the twenty minutes you have before the meeting.

ReportThe question it closesThe form that works
Cost and schedule varianceswhere did we drift from the plan?pivot table, or bars sorted by variance
Indicator trendsgetting better or worse?lines over periods, actions marked
Issues and their causeswhere does the problem start?table with drill-down, concentration by area
Earned Valuewhat will finishing cost at this rate?index table, bars on the out-of-threshold ones
Milestone statusdo the dates that matter hold?Gantt trimmed to milestones, or a status table
The five reports, the question each one closes and the form that works for it.

The extra condition: continuity of readings

The analytical dashboard needs everything the other two need: a saved baseline, a correct status date, a real periodic update. It also needs one thing they do not, because its value is in the time series rather than the snapshot: the readings have to be continuous.

A single cost index is a number. Twelve consecutive ones are a diagnosis, because the shape of the line tells you whether the situation is deteriorating steadily, recovered after an action, or has been flat since the start. Skip two periods and the line still draws, but it now says something that is not true.

A missing reading that is declared is information. A missing reading that is passed over in silence is an error.

The practical rule: mark gaps on the chart rather than interpolating across them, and keep the reporting period fixed from the start of the project. A series with a visible hole is honest and still usable; a smooth line drawn through a hole is neither.

The mistakes I see most often

  • Projecting it in the meeting. It is built for exploration by one person. On a screen in front of eight people it reads as clutter and the meeting slows down.
  • Drill-down that stops at level two. You learn which phase, and still cannot say what to change. The third level is the one that costs work to build and the one that pays.
  • Indices without a baseline. SPI and CPI computed on a plan with no baseline are arithmetic on nothing, and they look exactly as convincing as real ones.
  • Absolute values with no history. A CPI of 0.89 on its own is almost meaningless; 0.89 after 0.95 and 0.92 is a trend and a reason to act.
  • Contractual and internal milestones mixed together. It makes the contractual ones look negotiable, which is the opposite of what the page should convey.
  • Interpolating over missing periods, so the chart looks tidy and reports a recovery that never happened.

When you do not need one

Three cases, and they are common. On a small project of a few weeks, the plan itself plus the variance columns already tell you everything an analytical page would. Where costs are not tracked in a system at all, half the reports have no data and the page becomes a schedule view with extra steps. And on a project that has just started there is no history, so the most valuable part of the page, the trend, has nothing to draw yet.

In that last case the right move is to start collecting readings on a fixed cadence now and build the page after three or four periods, when the lines have something to say.

Frequently asked questions

What is an analytical project dashboard?

It is the dashboard that explains why a project is where it is. Its reader is the project manager, the PMO or a controller, and it carries variances against plan, how the indicators move over time, issues with their causes, Earned Value and milestone status, with drill-down from the portfolio down to the individual task and resource.

How is it different from a strategic dashboard?

The strategic page says which projects to discuss and is read in ten seconds, usually in the meeting. The analytical page says why one project is where it is, is explored over half an hour, and is read before the meeting rather than during it. The clearest test is drill-down: the analytical one has it, the strategic one does not.

How many levels of drill-down do I need?

Three: portfolio, phase, then task and resource. The first two tell you there is a problem and roughly where it sits; only the third produces something you can act on. A page that stops at two levels is a strategic dashboard with more rows.

Can I build an analytical dashboard without a baseline?

Not usefully. Variances and Earned Value indices are both computed against the baseline, so without one the page can show where you are but never how far you have moved. Save a baseline first, even late, and mark on the chart the date from which the comparison is valid.

What do I do about a reporting period nobody updated?

Show the gap. Mark the period as missing on the chart rather than interpolating across it: a series with a visible hole is honest and still readable, while a smooth line drawn through a hole reports a trend that did not happen. Then fix the cadence, because one missed period usually becomes three.


Disclosure: this is the blog of a company that makes project-control software. Nothing above needs our tools. A pivot table on data exported from the plan, refreshed every reporting period, is already a working analytical dashboard.

#ProjectDashboards #EarnedValue #ProjectControl #PMO #MSProject

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top